2015/12/11 13:30 - | 2015/12/11 13:30 - |
Line 6: | Line 6: |
Participants: | Participants: |
Line 8: | Line 8: |
== Schedule == |
== Schedule == |
Line 27: | Line 26: |
* Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi) * Balast mass design |
* Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi) * Balast mass design |
Line 35: | Line 34: |
* Clean work procedure | * Clean work procedure |
Line 37: | Line 36: |
Line 42: | Line 41: |
* Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table. | * Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table. |
Line 50: | Line 49: |
Line 61: | Line 60: |
* Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws | * Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws |
Line 63: | Line 62: |
Line 65: | Line 64: |
* Out sourcing: Need to send the plates to the company -> Sent 6 sets on Tue. One set remaining at the site. | * Out sourcing: Need to send the plates to the company -> Sent 6 sets on Tue. One set remaining at the site. |
Line 93: | Line 92: |
* Next week (from 12/7) plan | * Next week (from 12/7) plan |
Line 95: | Line 94: |
* Mon: * Tue: * Wed: * Thu: * Fri: * PR2 * Mon: * Tue: * Wed: |
* Mon: * Tue: * Wed: |
Line 105: | Line 98: |
* Fri: | * Fri: * PR2 * Mon: * Tue: * Wed: * Thu: * Fri: |
Line 113: | Line 112: |
* Fujii: | * Fujii: |
Line 115: | Line 114: |
* Hirata: | * Hirata: |
Line 119: | Line 118: |
* Takahashi: * Shoda: * Mark: * Fabian: * Okutomi: * Fujii: * Ishizaki: * Hirata: * Ohishi: |
* Takahashi: * Shoda: * Mark: * Fabian: * Okutomi: * Fujii: * Ishizaki: * Hirata: * Ohishi: |
Line 130: | Line 129: |
Line 132: | Line 131: |
Line 135: | Line 133: |
Line 151: | Line 149: |
Line 158: | Line 155: |
* Roadmap discussion with Ando-san (Schedule Chart) | * Roadmap discussion with Ando-san ([[attachment:bKAGRA15summer-VIS-20151211.pdf|Schedule Chart]]) |
Line 165: | Line 162: |
* Waiting for shipping information: | * Waiting for shipping information: |
Line 173: | Line 170: |
2015/12/18 (Fri) 13:30 - | 2015/12/18 (Fri) 13:30 - |
VIS Meeting on 2015/12/11
2015/12/11 13:30 -
Kamioka NAOJ Room + SeeVogh
Participants:
Schedule
- Schedule status (Aso)
- Latest schedule chart
PR
- Test Hanging Status (Takahashi)
- LVDT driver
- Picomotor connection
- Fishing rod motor
Will use a non-vacuum compatible D-SUB for the hanging test. -> Status
- PR2 Status (Mark, Fabian)
- Location of the EQ stop pillars (Takahashi)
- Digital System (Okutomi, Fujii)
- BF Optimal Weight (Takahashi)
- Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi)
- Balast mass design
- Traverser actuation check (Shoda)
- Traverser stop mechanism (Shoda)
Procurement status (Takahashi): Told Uraguchi-san about our decision. Will order the parts soon. -> Status
- Clean work procedure
- KAGRA should have a special meeting for clean requirements (Aso will propose to Saito-san)
- PR CAD model and assembly drawings (Hirata)
- Need to give the rotation angle of the traverser top plate (Aso)
- Cable status (Takahashi)
Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table.
- Call for shift for assembly help (Takahashi)
- Made a call for shift for helping the installation works
- PR2 gluing schedule (Tatsumi)
- PR2 wire breakers have cracks
- PR3 was transported to Kamioka
- Wire cleaning
- Damaged one wire
- Production of additional PR winches (Akutsu)
- Most of the parts were delivered.
- ATC engineers is test assembling the winches (mostly complete)
- RM compensation mass
- Design status (Fabian): Do it later.
Order status (Takahashi): Placed an order. Will check the delivery date -> confirm (Takahashi)
- Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws
- For the RM assembly in the test hanging, SUS screws were fine (no gulling). So we will use SUS screws.
- RM EQ stop screw position (Takahashi)
Out sourcing: Need to send the plates to the company -> Sent 6 sets on Tue. One set remaining at the site.
- PR Optical Bench (Akutsu)
- For PR2, we do need to raise the optical bench.
- Delivery date for the screws: Dec. 21
- PR2 vacuum installation will be Jan. 19
- For PR2, we do need to raise the optical bench.
- OSEM assembly status (Akutsu)
7 OSEMs sent to Kamioka http://klog.icrr.u-tokyo.ac.jp/osl/?r=431
- OSEM screw length issue
- RM production (Takahashi)
- Confirmation of the surface finish
- Test hanging vacuum installation
- What needs to be done when the suspension is inside the chamber ?
- Transfer function measurement
- Spectrum
Do we need OpLev -> Yes
- Check the orientation of the mirror
- Check the height with laser marker
Peel off the first contact first -> Done
- Practice of the suspension cleaning using the air gun
- Inner frame modal analysis with the suspension (Takahashi)
- What needs to be done when the suspension is inside the chamber ?
- List of what should be changed for PR3 hanging
- some OSEM screws (to BUMAX)
- Next week (from 12/7) plan
- Test hanging
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
- PR2
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
- Test hanging
- Travel (Week of 12/14)
- Takahashi: Mon-Thu
- Shoda: Mon-Fri
- Mark: Tue-Thu(AM)
- Fabian: Mon-Fri
- Okutomi: Tue-Fri
- Fujii:
- Ishizaki: Tue-Fri
- Hirata:
- Ohishi:
- Travel (Week of 12/21)
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
* Joris: 12/7 - 12/18
BS
- What to do with BS after iKAGRA (Aso)
- We need to decide on the plan by the end of Dec.
- BS Assembly Frame Design (Aso, Hirata)
- BS flag design (Mark, Fabian)
- BS gluing jigs (Tatsumi)
- Not enough crane height problem (Hirata, Saito)
- IP base clamp (Fabian)
- Bread board spring (Takahashi)
- BS clean bag (Aso)
ETM
- ETM assembly frame (Aso)
- Waiting for quotation from Mirapro (sent a reminder)
- Optical table was ordered: delivery date 1/19
Other
- bKAGRA preparation
Roadmap discussion with Ando-san (Schedule Chart)
- DGS request. They need 3 weeks of preparation time before suspension installation.
- List of tasks for: BS, Type-A, Type-Bp modification, IMMT
- Watch dog system (Tanaka)
- GAS blade inspection by Virgo (Takahashi)
- Waiting for shipping information:
- Request to the ATC for the next year
Production of the blades of the Type-A BF: We should check the consistency of the optimal load at the TAMA prototype experiment and G&M measurements (SF and TF) (Takahashi) -> Status
- Safety at the site (Takahashi, Ishizaki)
Next meeting
2015/12/18 (Fri) 13:30 -
Next F2F Meeting ?