Differences between revisions 4 and 5
Revision 4 as of 2015-12-11 13:06:04
Size: 4961
Editor: YoichiAso
Comment:
Revision 5 as of 2015-12-13 18:14:58
Size: 8681
Editor: YoichiAso
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
2015/12/11 13:30 - 2015/12/11 13:30 -  16:30
Line 6: Line 6:
Participants:

== Schedule ==
Participants: Shoda, Fabian, Fujii, Mark, Ohishi, Joris, Takahashi, Aso, Hirata, Tatsumi, Raffaele, Okutomi

== Schedule ==
Line 10: Line 11:
  * [[attachment:05_VIS-20151211.pdf|Latest schedule chart]]   * Latest schedule chart
Line 14: Line 15:
  * LVDT driver
  * Picomotor connection
  * Fishing rod motor
   * Will use a non-vacuum compatible D-SUB for the hanging test. -> Status
  * Suspension was dumped into the chamber: the hook of a turn backle came off while slowly sitting the suspension into the chamber. The entire chain dropped by about 1cm. With this shock, at least 1 OSEM flag in IM was broken.
  * LVDT driver: The one used at first had a broken IC. Replaced with a new board and it worked. Need to set the gains properly. Will put information into the corresponding DCC documents.
  * Picomotor connection: Worked fine.
  * Fishing rod motor: Worked fine. Pin-extracter was delivered. So the damaged vacuum compatible cable can be fixed.
  * While lowering the jacks on the inner frame, some of them seemed to have galled.

 * How to sit the suspension to the inner frame ?
  * Lift up the suspension. Remove the galled jacks.
   * Inspect the removed jacks.
  * Put new jacks.
  * Try to sit the suspension usign turn backles.
   * Use 4 slings instead of 2.
   * Carefully level the top plate.
Line 20: Line 30:
  * Finding screws and parts.
  * Cleaned some parts.

  * What can we do before the PR2 arrives
   * RM assembly
   * Traverser assembly
   * Preparation of the flags
    * Sand the Ni-plating on the magnets before gluing to increase the adhesion ?
    * Need to order spare flag bases: 6 of them (Takahashi)
Line 22: Line 41:
  * Takahashi will tell Hirata the proper locations of the pillars.
Line 24: Line 44:
  * The model is almost completed.
  * Now the digital system is working. We were able to measure transfer functions.
Line 26: Line 48:
  * Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi)
  * Balast mass design
  * Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi)
   * Balast mass design: Takahashi will check the design during the weekend and give (not give) an approval before Monday.
   * Fabian will give the design to Hirata-san on Monday.
Line 30: Line 53:

 * Traverser stop mechanism (Shoda)
  * Procurement status (Takahashi): Told Uraguchi-san about our decision. Will order the parts soon. -> Status

 * Clean work procedure
  * KAGRA should have a special meeting for clean requirements (Aso will propose to Saito-san)
  * Now we may move the traverser in the air a little bit.
  * Will test it at some point.

 * Traverser stop mechanism
  * Procurement status (Takahashi): Parts were ordered. Should arrive in one week.

 * Clean work procedure
  * Need to check with Miyoki-san when the clean suits will be delivered (Aso).
  * Ask Hirose-san about better wiping cloths (Aso).
  * Other clean supplies: masks,
  * KAGRA should have a special meeting for clean requirements: Aso had a meeting with Saito-san and Hirose-san. But the meeting was interrupted by a car accident. Will propose another meeting.
  * Blowing the suspension in the assembly frame -> Need to pre-arrange the schedule with other groups.
  
Line 41: Line 70:
  * Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table.   * All the cables except for two cables were delivered.
   * Need to send more PTFE cable to finish the remaining two.
   * Need to send the cables used for the test hanging once it is finshed.
  * Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table.

 * Cable check
  * 70% done.
  * One cable found to be broken. Will send it back to the company.
Line 45: Line 81:
  * No application so far
Line 48: Line 85:
  * PR3 was transported to Kamioka
  * PR3 ones have no crack. PR3 was transported to Kamioka
  * Use SUS wire breakers for iKAGRA mirrors ?
   * PRC mirrors will not suffer from the thermal noise
   * For SRC mirrors, we should test the sapphire wire breakers more carefully
  * Removal of the wire breakers
   * Mark will ask LIGO people about the procedure
   * Contact manufacuturer (Tatsumi)
  
Line 52: Line 95:
  * Hirata will order 20m more wires.
  * Will wash Tungsten wires too, but not yet delivered.
Line 54: Line 99:
  * Most of the parts were delivered.
  * ATC engineers is test assembling the winches (mostly complete)
  * Question from Akutsu-kun
  1. What is the weight each drum should support -> Shoda will calculate
  2. What is the wire diameter to be tested? -> 650um: Takahashi ordered 600um and 650um already. Will give 1m to ATC for the test. Takahashi will order some extra for 650um.
Line 59: Line 105:
  * Order status (Takahashi): Placed an order. Will check the delivery date -> confirm (Takahashi)
  * Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws
  * For the RM assembly in the test hanging, SUS screws were fine (no gulling). So we will use SUS screws.
  * Order status (Takahashi): Delivered. Hirata washed and sent them to Kamioka.
  * Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws.
 
Line 64: Line 109:
  * Out sourcing: Need to send the plates to the company -> Sent 6 sets on Tue. One set remaining at the site.   * Out sourcing: 6 sets delivered washed and sent to Kamioka. Now we have all needed.
Line 74: Line 119:
   * We have a lot of M5x20 BUMAX screws
   * Do we need to use longer ones ? -> Shoda will check with the actual test mass RM
Line 76: Line 123:
  * Confirmation of the surface finish   * What to do with the dirty RMs ?: Check with ATC if re-polishing the rough surface is possible or not (Takahashi)
Line 80: Line 127:
   * Peel off the first contact first -> Done
   * Cabling
   * OpLev preparation
   * Hammering test
   * Test of cleaning by blowing
Line 82: Line 134:
   * Do we need OpLev -> Yes
Line 85: Line 136:
   * Peel off the first contact first -> Done
   * Practice of the suspension cleaning using the air gun
   * Inner frame modal analysis with the suspension (Takahashi)
Line 90: Line 138:
  * some OSEM screws (to BUMAX)

 * Next week (from 12/7) plan
  * People should share ideas whenever they come up with missing thigns.
  * Shoda made a spread sheet for keep tracking the ideas
   * https://docs.google.com/spreadsheets/d/1zZaLObWjDSEOTrr85Hz0ApXxEUChK3xJ_chk0f7r5nY/edit?usp=sharing

 * Next week (from 12/14) plan
Line 94: Line 144:
   * Mon:
   * Tue:
   * Wed:
   * Thu:
   * Fri:
  * PR2
   * Mon:
   * Tue:
   * Wed:
   * Thu:
   * Fri:
   * Mon: Replace the jacks
   * Tue: Replace the jacks
   * Wed: Cleaning test, Hammering Test
   * Thu: Cabling
   * Fri: Release the EQ stops

  * PR2
   * Mon:
   * Tue: Assemble RM
   * Wed: Put IM
   * Thu: Assemble RM carrage
   * Fri: Preparation for traverser assembly
Line 110: Line 161:
  * Fabian: Tue-Fri
  * Okutomi: Tue-Fri
  * Fujii: Mon(aft)-Fri
  * Ishizaki: Tue-Fri
  * Hirata:
  * Ohishi: Tue-Fri

 * Travel (Week of 12/21)
  * Takahashi: Thu-Fri
  * Shoda: Mon-Fri
  * Mark: Mon-Tue
Line 111: Line 173:
  * Okutomi: Tue-Fri
  * Fujii:
  * Ishizaki: Tue-Fri
  * Hirata:
  * Ohishi:

 * Travel (Week of 12/21)
  * Takahashi:
  * Shoda:
  * Mark:
  * Fabian:
  * Okutomi:
  * Fujii:
  * Ishizaki:
  * Hirata:
  * Ohishi:
  * Okutomi: Mon-Fri
  * Fujii: Mon-Fri
  * Ishizaki:
  * Hirata:
  * Ohishi:
Line 129: Line 180:
 
Line 131: Line 182:
Line 132: Line 184:
  * We need to decide on the plan by the end of Dec.
  * We will do the BS first
 
Line 149: Line 201:
 
Line 155: Line 208:
  * Roadmap discussion with Ando-san ([[attachment:bKAGRA15summer-VIS-20151211.pdf|Schedule Chart]])   * Roadmap discussion with Ando-san (Schedule Chart)
Line 157: Line 210:
  * List of tasks for: BS, Type-A, Type-Bp modification, IMMT   * List of tasks for: BS, Type-A, Type-Bp modification, IMMT (Takahashi) Set up a Wiki page (Aso)
Line 160: Line 213:
  * Will present at an AEL meeting.
Line 162: Line 216:
  * Waiting for shipping information:   * Waiting for shipping information: Go the shipping address. To be shipped soon.
Line 165: Line 219:
  * Production of the blades of the Type-A BF: We should check the consistency of the optimal load at the TAMA prototype experiment and G&M measurements (SF and TF) (Takahashi) -> Status   * Production of the blades of the Type-A BF: We should check the consistency of the optimal load at the TAMA prototype experiment and G&M measurements (SF and TF) (Takahashi) -
   *
SF: G&M 164.7kg, TAMA: 165.3kg
   * TF: G&M 276kg, TAMA: 278kg
  * No obvious reason to distrust G&M's measurements
  * Should consider in-situ measurement procedure of the optimal load during the installation of Type-A
Line 168: Line 226:
  * A big near miss during the suspension installation into the chamber
Line 170: Line 229:
2015/12/18 (Fri) 13:30 -

Next F2F Meeting ?
2015/12/18 (Fri) 13:30 - 

Next F2F Meeting: Jan 8

VIS Meeting on 2015/12/11

2015/12/11 13:30 - 16:30

Kamioka NAOJ Room + SeeVogh

Participants: Shoda, Fabian, Fujii, Mark, Ohishi, Joris, Takahashi, Aso, Hirata, Tatsumi, Raffaele, Okutomi

Schedule

  • Schedule status (Aso)
    • Latest schedule chart

PR

  • Test Hanging Status (Takahashi)
    • Suspension was dumped into the chamber: the hook of a turn backle came off while slowly sitting the suspension into the chamber. The entire chain dropped by about 1cm. With this shock, at least 1 OSEM flag in IM was broken.
    • LVDT driver: The one used at first had a broken IC. Replaced with a new board and it worked. Need to set the gains properly. Will put information into the corresponding DCC documents.
    • Picomotor connection: Worked fine.
    • Fishing rod motor: Worked fine. Pin-extracter was delivered. So the damaged vacuum compatible cable can be fixed.
    • While lowering the jacks on the inner frame, some of them seemed to have galled.
  • How to sit the suspension to the inner frame ?
    • Lift up the suspension. Remove the galled jacks.
      • Inspect the removed jacks.
    • Put new jacks.
    • Try to sit the suspension usign turn backles.
      • Use 4 slings instead of 2.
      • Carefully level the top plate.
  • PR2 Status (Mark, Fabian)
    • Finding screws and parts.
    • Cleaned some parts.
    • What can we do before the PR2 arrives
      • RM assembly
      • Traverser assembly
      • Preparation of the flags
        • Sand the Ni-plating on the magnets before gluing to increase the adhesion ?
        • Need to order spare flag bases: 6 of them (Takahashi)
  • Location of the EQ stop pillars (Takahashi)
    • Takahashi will tell Hirata the proper locations of the pillars.
  • Digital System (Okutomi, Fujii)
    • The model is almost completed.
    • Now the digital system is working. We were able to measure transfer functions.
  • BF Optimal Weight (Takahashi)
    • Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi)
    • Balast mass design: Takahashi will check the design during the weekend and give (not give) an approval before Monday.
    • Fabian will give the design to Hirata-san on Monday.
  • Traverser actuation check (Shoda)
    • Now we may move the traverser in the air a little bit.
    • Will test it at some point.
  • Traverser stop mechanism
    • Procurement status (Takahashi): Parts were ordered. Should arrive in one week.
  • Clean work procedure
    • Need to check with Miyoki-san when the clean suits will be delivered (Aso).
    • Ask Hirose-san about better wiping cloths (Aso).
    • Other clean supplies: masks,
    • KAGRA should have a special meeting for clean requirements: Aso had a meeting with Saito-san and Hirose-san. But the meeting was interrupted by a car accident. Will propose another meeting.
    • Blowing the suspension in the assembly frame -> Need to pre-arrange the schedule with other groups.

  • PR CAD model and assembly drawings (Hirata)
    • Need to give the rotation angle of the traverser top plate (Aso)
  • Cable status (Takahashi)
    • All the cables except for two cables were delivered.
      • Need to send more PTFE cable to finish the remaining two.
      • Need to send the cables used for the test hanging once it is finshed.
    • Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table.

  • Cable check
    • 70% done.
    • One cable found to be broken. Will send it back to the company.
  • Call for shift for assembly help (Takahashi)
    • Made a call for shift for helping the installation works
    • No application so far
  • PR2 gluing schedule (Tatsumi)
    • PR2 wire breakers have cracks
    • PR3 ones have no crack. PR3 was transported to Kamioka
    • Use SUS wire breakers for iKAGRA mirrors ?
      • PRC mirrors will not suffer from the thermal noise
      • For SRC mirrors, we should test the sapphire wire breakers more carefully
    • Removal of the wire breakers
      • Mark will ask LIGO people about the procedure
      • Contact manufacuturer (Tatsumi)
  • Wire cleaning
    • Damaged one wire
    • Hirata will order 20m more wires.
    • Will wash Tungsten wires too, but not yet delivered.
  • Production of additional PR winches (Akutsu)
    • Question from Akutsu-kun
    • What is the weight each drum should support -> Shoda will calculate

    • What is the wire diameter to be tested? -> 650um: Takahashi ordered 600um and 650um already. Will give 1m to ATC for the test. Takahashi will order some extra for 650um.

  • RM compensation mass
    • Design status (Fabian): Do it later.
    • Order status (Takahashi): Delivered. Hirata washed and sent them to Kamioka.
    • Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws.
  • RM EQ stop screw position (Takahashi)
    • Out sourcing: 6 sets delivered washed and sent to Kamioka. Now we have all needed.
  • PR Optical Bench (Akutsu)
    • For PR2, we do need to raise the optical bench.
      • Delivery date for the screws: Dec. 21
      • PR2 vacuum installation will be Jan. 19
  • OSEM assembly status (Akutsu)
    • 7 OSEMs sent to Kamioka http://klog.icrr.u-tokyo.ac.jp/osl/?r=431

    • OSEM screw length issue
      • We have a lot of M5x20 BUMAX screws
      • Do we need to use longer ones ? -> Shoda will check with the actual test mass RM

  • RM production (Takahashi)
    • What to do with the dirty RMs ?: Check with ATC if re-polishing the rough surface is possible or not (Takahashi)
  • Test hanging vacuum installation
    • What needs to be done when the suspension is inside the chamber ?
      • Peel off the first contact first -> Done

      • Cabling
      • OpLev preparation

      • Hammering test
      • Test of cleaning by blowing
      • Transfer function measurement
      • Spectrum
      • Check the orientation of the mirror
      • Check the height with laser marker
  • List of what should be changed for PR3 hanging
  • Next week (from 12/14) plan
    • Test hanging
      • Mon: Replace the jacks
      • Tue: Replace the jacks
      • Wed: Cleaning test, Hammering Test
      • Thu: Cabling
      • Fri: Release the EQ stops
    • PR2
      • Mon:
      • Tue: Assemble RM
      • Wed: Put IM
      • Thu: Assemble RM carrage
      • Fri: Preparation for traverser assembly
  • Travel (Week of 12/14)
    • Takahashi: Mon-Thu
    • Shoda: Mon-Fri
    • Mark: Tue-Thu(AM)
    • Fabian: Tue-Fri
    • Okutomi: Tue-Fri
    • Fujii: Mon(aft)-Fri
    • Ishizaki: Tue-Fri
    • Hirata:
    • Ohishi: Tue-Fri
  • Travel (Week of 12/21)
    • Takahashi: Thu-Fri
    • Shoda: Mon-Fri
    • Mark: Mon-Tue
    • Fabian: Mon-Fri
    • Okutomi: Mon-Fri
    • Fujii: Mon-Fri
    • Ishizaki:
    • Hirata:
    • Ohishi:

* Joris: 12/7 - 12/18

BS

  • What to do with BS after iKAGRA (Aso)
    • We will do the BS first
  • BS Assembly Frame Design (Aso, Hirata)
  • BS flag design (Mark, Fabian)
  • BS gluing jigs (Tatsumi)
  • Not enough crane height problem (Hirata, Saito)
  • IP base clamp (Fabian)
  • Bread board spring (Takahashi)
  • BS clean bag (Aso)

ETM

  • ETM assembly frame (Aso)
    • Waiting for quotation from Mirapro (sent a reminder)
    • Optical table was ordered: delivery date 1/19

Other

  • bKAGRA preparation
    • Roadmap discussion with Ando-san (Schedule Chart)
      • DGS request. They need 3 weeks of preparation time before suspension installation.
    • List of tasks for: BS, Type-A, Type-Bp modification, IMMT (Takahashi) Set up a Wiki page (Aso)
  • Watch dog system (Tanaka)
    • Will present at an AEL meeting.
  • GAS blade inspection by Virgo (Takahashi)
    • Waiting for shipping information: Go the shipping address. To be shipped soon.
  • Request to the ATC for the next year
    • Production of the blades of the Type-A BF: We should check the consistency of the optimal load at the TAMA prototype experiment and G&M measurements (SF and TF) (Takahashi) -

      • SF: G&M 164.7kg, TAMA: 165.3kg

      • TF: G&M 276kg, TAMA: 278kg

    • No obvious reason to distrust G&M's measurements

    • Should consider in-situ measurement procedure of the optimal load during the installation of Type-A
  • Safety at the site (Takahashi, Ishizaki)
    • A big near miss during the suspension installation into the chamber

Next meeting

2015/12/18 (Fri) 13:30 -

Next F2F Meeting: Jan 8

KAGRA/Subgroups/VIS/VISMinutes20151211 (last edited 2015-12-13 18:25:48 by YoichiAso)