Differences between revisions 5 and 6
Revision 5 as of 2015-12-13 18:14:58
Size: 8681
Editor: YoichiAso
Comment:
Revision 6 as of 2015-12-13 18:25:48
Size: 8855
Editor: YoichiAso
Comment:
Deletions are marked like this. Additions are marked like this.
Line 8: Line 8:
==  Schedule ==
== Schedule ==
Line 11: Line 10:
  * Latest schedule chart   * [[attachment:05_VIS-20151211.pdf|Latest schedule chart]]
Line 23: Line 22:
   * Inspect the removed jacks.     * Inspect the removed jacks.
Line 38: Line 37:
    * Need to order spare flag bases: 6 of them (Takahashi)     * '''Need to order spare flag bases: 6 of them (Takahashi) '''
Line 41: Line 40:
  * Takahashi will tell Hirata the proper locations of the pillars.   * '''Takahashi will tell Hirata the proper locations of the pillars. '''
Line 48: Line 47:
  * Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi)
   * Balast mass design: Takahashi will check the design during the weekend and give (not give) an approval before Monday.
  * Fabian will give the design to Hirata-san on Monday.
  * '''Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi) '''
  * '''Balast mass design: Takahashi will check the design during the weekend and give (not give) an approval before Monday. '''
  * Fabian will give the design to Hirata-san on Monday.
Line 56: Line 55:
 * Traverser stop mechanism   * Traverser stop mechanism
Line 59: Line 58:
 * Clean work procedure 
  * Need to check with Miyoki-san when the clean suits will be delivered (Aso).
  * Ask Hirose-san about better wiping cloths (Aso).
  * Other clean supplies: masks, 
  * KAGRA should have a special meeting for clean requirements: Aso had a meeting with Saito-san and Hirose-san. But the meeting was interrupted by a car accident. Will propose another meeting.
 * Clean work procedure
  * '''Need to check with Miyoki-san when the clean suits will be delivered (Aso). '''
  * '''Ask Hirose-san about better wiping cloths (Aso). '''
  * Other clean supplies: masks,
  * KAGRA should have a special meeting for clean requirements: Aso had a meeting with Saito-san and Hirose-san. But the meeting was interrupted by a car accident. '''Will propose another meeting (Aso)'''.
Line 65: Line 64:
  
Line 67: Line 66:
  * Need to give the rotation angle of the traverser top plate (Aso)   * '''Need to give the rotation angle of the traverser top plate (Aso) '''
Line 73: Line 72:
  * Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table.   * Made a cable list -> Put a link to the excel file on Wiki. '''Takahashi will improve the table.  '''
Line 76: Line 75:
  * 70% done. 
  * One cable found to be broken. Will send it back to the company.
  * 70% done.
  * One cable found to be broken. '''Will send it back to the company (Takahashi)'''.
Line 90: Line 89:
   * Mark will ask LIGO people about the procedure
   * Contact manufacuturer (Tatsumi)
  
   * '''Mark will ask LIGO people about the procedure '''
   * '''Contact manufacuturer (Tatsumi) '''
Line 95: Line 94:
  * Hirata will order 20m more wires.   * '''Hirata will order 20m more wires. '''
Line 99: Line 98:
  *  Question from Akutsu-kun
  1. What is the weight each drum should support -> Shoda will calculate
  2. What is the wire diameter to be tested? -> 650um: Takahashi ordered 600um and 650um already. Will give 1m to ATC for the test. Takahashi will order some extra for 650um.
  * Question from Akutsu-kun
  * What is the weight each drum should support -> '''Shoda will calculate '''
  * What is the wire diameter to be tested? -> 650um: Takahashi ordered 600um and 650um already. Will give 1m to ATC for the test. '''Takahashi will order some extra for 650um. '''
Line 104: Line 103:
  * Design status (Fabian): Do it later.   * '''Design status (Fabian): Do it later. '''
Line 106: Line 105:
  * Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws.
 
  * Need to buy screws for fixing the compensation masses. '''Takahashi will check the lengths of screws.  '''
Line 120: Line 119:
   * Do we need to use longer ones ? -> Shoda will check with the actual test mass RM    * Do we need to use longer ones ? -> '''Shoda will check with the actual test mass RM'''
Line 123: Line 122:
  * What to do with the dirty RMs ?: Check with ATC if re-polishing the rough surface is possible or not (Takahashi)   * What to do with the dirty RMs ?: '''Check with ATC if re-polishing the rough surface is possible or not (Takahashi) '''
Line 131: Line 130:
   * Test of cleaning by blowing     * Test of cleaning by blowing
Line 142: Line 141:
 * Next week (from 12/14) plan   * Next week (from 12/14) plan
Line 150: Line 149:
  * PR2 
   * Mon: 
  * PR2
   * Mon:
Line 165: Line 164:
  * Hirata:    * Hirata:
Line 175: Line 174:
  * Ishizaki: 
  * Hirata: 
  * Ohishi: 
  * Ishizaki:
  * Hirata:
  * Ohishi:
Line 180: Line 179:
 
Line 182: Line 181:
Line 185: Line 183:
 
Line 201: Line 199:
 
Line 210: Line 207:
  * List of tasks for: BS, Type-A, Type-Bp modification, IMMT (Takahashi) Set up a Wiki page (Aso)   * List of tasks for: BS, Type-A, Type-Bp modification, IMMT. '''Make a draft list (Takahashi). Set up a Wiki page (Aso)'''
Line 229: Line 226:
2015/12/18 (Fri) 13:30 -  2015/12/18 (Fri) 13:30 -

VIS Meeting on 2015/12/11

2015/12/11 13:30 - 16:30

Kamioka NAOJ Room + SeeVogh

Participants: Shoda, Fabian, Fujii, Mark, Ohishi, Joris, Takahashi, Aso, Hirata, Tatsumi, Raffaele, Okutomi

Schedule

PR

  • Test Hanging Status (Takahashi)
    • Suspension was dumped into the chamber: the hook of a turn backle came off while slowly sitting the suspension into the chamber. The entire chain dropped by about 1cm. With this shock, at least 1 OSEM flag in IM was broken.
    • LVDT driver: The one used at first had a broken IC. Replaced with a new board and it worked. Need to set the gains properly. Will put information into the corresponding DCC documents.
    • Picomotor connection: Worked fine.
    • Fishing rod motor: Worked fine. Pin-extracter was delivered. So the damaged vacuum compatible cable can be fixed.
    • While lowering the jacks on the inner frame, some of them seemed to have galled.
  • How to sit the suspension to the inner frame ?
    • Lift up the suspension. Remove the galled jacks.
      • Inspect the removed jacks.
    • Put new jacks.
    • Try to sit the suspension usign turn backles.
      • Use 4 slings instead of 2.
      • Carefully level the top plate.
  • PR2 Status (Mark, Fabian)
    • Finding screws and parts.
    • Cleaned some parts.
    • What can we do before the PR2 arrives
      • RM assembly
      • Traverser assembly
      • Preparation of the flags
        • Sand the Ni-plating on the magnets before gluing to increase the adhesion ?
        • Need to order spare flag bases: 6 of them (Takahashi)

  • Location of the EQ stop pillars (Takahashi)
    • Takahashi will tell Hirata the proper locations of the pillars.

  • Digital System (Okutomi, Fujii)
    • The model is almost completed.
    • Now the digital system is working. We were able to measure transfer functions.
  • BF Optimal Weight (Takahashi)
    • Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi)

    • Balast mass design: Takahashi will check the design during the weekend and give (not give) an approval before Monday.

    • Fabian will give the design to Hirata-san on Monday.
  • Traverser actuation check (Shoda)
    • Now we may move the traverser in the air a little bit.
    • Will test it at some point.
  • Traverser stop mechanism
    • Procurement status (Takahashi): Parts were ordered. Should arrive in one week.
  • Clean work procedure
    • Need to check with Miyoki-san when the clean suits will be delivered (Aso).

    • Ask Hirose-san about better wiping cloths (Aso).

    • Other clean supplies: masks,
    • KAGRA should have a special meeting for clean requirements: Aso had a meeting with Saito-san and Hirose-san. But the meeting was interrupted by a car accident. Will propose another meeting (Aso).

    • Blowing the suspension in the assembly frame -> Need to pre-arrange the schedule with other groups.

  • PR CAD model and assembly drawings (Hirata)
    • Need to give the rotation angle of the traverser top plate (Aso)

  • Cable status (Takahashi)
    • All the cables except for two cables were delivered.
      • Need to send more PTFE cable to finish the remaining two.
      • Need to send the cables used for the test hanging once it is finshed.
    • Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table.

  • Cable check
    • 70% done.
    • One cable found to be broken. Will send it back to the company (Takahashi).

  • Call for shift for assembly help (Takahashi)
    • Made a call for shift for helping the installation works
    • No application so far
  • PR2 gluing schedule (Tatsumi)
    • PR2 wire breakers have cracks
    • PR3 ones have no crack. PR3 was transported to Kamioka
    • Use SUS wire breakers for iKAGRA mirrors ?
      • PRC mirrors will not suffer from the thermal noise
      • For SRC mirrors, we should test the sapphire wire breakers more carefully
    • Removal of the wire breakers
      • Mark will ask LIGO people about the procedure

      • Contact manufacuturer (Tatsumi)

  • Wire cleaning
    • Damaged one wire
    • Hirata will order 20m more wires.

    • Will wash Tungsten wires too, but not yet delivered.
  • Production of additional PR winches (Akutsu)
    • Question from Akutsu-kun
    • What is the weight each drum should support -> Shoda will calculate

    • What is the wire diameter to be tested? -> 650um: Takahashi ordered 600um and 650um already. Will give 1m to ATC for the test. Takahashi will order some extra for 650um.

  • RM compensation mass
    • Design status (Fabian): Do it later.

    • Order status (Takahashi): Delivered. Hirata washed and sent them to Kamioka.
    • Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws.

  • RM EQ stop screw position (Takahashi)
    • Out sourcing: 6 sets delivered washed and sent to Kamioka. Now we have all needed.
  • PR Optical Bench (Akutsu)
    • For PR2, we do need to raise the optical bench.
      • Delivery date for the screws: Dec. 21
      • PR2 vacuum installation will be Jan. 19
  • OSEM assembly status (Akutsu)
    • 7 OSEMs sent to Kamioka http://klog.icrr.u-tokyo.ac.jp/osl/?r=431

    • OSEM screw length issue
      • We have a lot of M5x20 BUMAX screws
      • Do we need to use longer ones ? -> Shoda will check with the actual test mass RM

  • RM production (Takahashi)
    • What to do with the dirty RMs ?: Check with ATC if re-polishing the rough surface is possible or not (Takahashi)

  • Test hanging vacuum installation
    • What needs to be done when the suspension is inside the chamber ?
      • Peel off the first contact first -> Done

      • Cabling
      • OpLev preparation

      • Hammering test
      • Test of cleaning by blowing
      • Transfer function measurement
      • Spectrum
      • Check the orientation of the mirror
      • Check the height with laser marker
  • List of what should be changed for PR3 hanging
  • Next week (from 12/14) plan
    • Test hanging
      • Mon: Replace the jacks
      • Tue: Replace the jacks
      • Wed: Cleaning test, Hammering Test
      • Thu: Cabling
      • Fri: Release the EQ stops
    • PR2
      • Mon:
      • Tue: Assemble RM
      • Wed: Put IM
      • Thu: Assemble RM carrage
      • Fri: Preparation for traverser assembly
  • Travel (Week of 12/14)
    • Takahashi: Mon-Thu
    • Shoda: Mon-Fri
    • Mark: Tue-Thu(AM)
    • Fabian: Tue-Fri
    • Okutomi: Tue-Fri
    • Fujii: Mon(aft)-Fri
    • Ishizaki: Tue-Fri
    • Hirata:
    • Ohishi: Tue-Fri
  • Travel (Week of 12/21)
    • Takahashi: Thu-Fri
    • Shoda: Mon-Fri
    • Mark: Mon-Tue
    • Fabian: Mon-Fri
    • Okutomi: Mon-Fri
    • Fujii: Mon-Fri
    • Ishizaki:
    • Hirata:
    • Ohishi:

* Joris: 12/7 - 12/18

BS

  • What to do with BS after iKAGRA (Aso)
    • We will do the BS first
  • BS Assembly Frame Design (Aso, Hirata)
  • BS flag design (Mark, Fabian)
  • BS gluing jigs (Tatsumi)
  • Not enough crane height problem (Hirata, Saito)
  • IP base clamp (Fabian)
  • Bread board spring (Takahashi)
  • BS clean bag (Aso)

ETM

  • ETM assembly frame (Aso)
    • Waiting for quotation from Mirapro (sent a reminder)
    • Optical table was ordered: delivery date 1/19

Other

  • bKAGRA preparation
    • Roadmap discussion with Ando-san (Schedule Chart)
      • DGS request. They need 3 weeks of preparation time before suspension installation.
    • List of tasks for: BS, Type-A, Type-Bp modification, IMMT. Make a draft list (Takahashi). Set up a Wiki page (Aso)

  • Watch dog system (Tanaka)
    • Will present at an AEL meeting.
  • GAS blade inspection by Virgo (Takahashi)
    • Waiting for shipping information: Go the shipping address. To be shipped soon.
  • Request to the ATC for the next year
    • Production of the blades of the Type-A BF: We should check the consistency of the optimal load at the TAMA prototype experiment and G&M measurements (SF and TF) (Takahashi) -

      • SF: G&M 164.7kg, TAMA: 165.3kg

      • TF: G&M 276kg, TAMA: 278kg

    • No obvious reason to distrust G&M's measurements

    • Should consider in-situ measurement procedure of the optimal load during the installation of Type-A
  • Safety at the site (Takahashi, Ishizaki)
    • A big near miss during the suspension installation into the chamber

Next meeting

2015/12/18 (Fri) 13:30 -

Next F2F Meeting: Jan 8

KAGRA/Subgroups/VIS/VISMinutes20151211 (last edited 2015-12-13 18:25:48 by YoichiAso)