VIS Meeting on 2015/12/18
2015/12/18 13:30 -
Kamioka TV conference room + SeeVogh
Participants:
Schedule
- Schedule status (Aso)
- Latest schedule chart
PR
- Test Hanging Status (Takahashi)
- Installation into vacuum
- Blowing test
- Hammering test
- Cabling
- EQ stop release
- PR2 Status (Mark, Fabian)
- What can we do before the PR2 arrives
- Preparation of the flags
Sand the Ni-plating on the magnets before gluing to increase the adhesion ? -> Preparation Status
Need to order spare flag bases: 6 of them (Takahashi) -> Status
- Preparation of the flags
- What can we do before the PR2 arrives
- Location of the EQ stop pillars (Takahashi)
- Takahashi will tell Hirata the proper locations of the pillars.
- Digital System (Okutomi, Fujii)
- BF Optimal Weight (Takahashi)
- Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi)
- Balast mass design
- Traverser actuation check (Shoda)
- Now we may move the traverser in the air a little bit.
- Will test it at some point.
- Traverser stop mechanism
- Procurement status (Takahashi)
- Clean work procedure
Need to check with Miyoki-san when the clean suits will be delivered (Aso) -> 1/15
- Ask Hirose-san about better wiping cloths (Aso): Texwipe Vectra Alpha 10 or TX8410. Asking if he has enough or we should order them.
- KAGRA should have a special meeting for clean requirements: Aso had a meeting with Saito-san and Hirose-san. But the meeting was interrupted by a car accident. Will propose another meeting.
- PR CAD model and assembly drawings (Hirata)
- Need to give the rotation angle of the traverser top plate (Aso)
- Cable status (Takahashi)
- All the cables except for two cables were delivered.
Need to send more PTFE cable to finish the remaining two -> status
- Need to send the cables used for the test hanging once it is finshed.
Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table.
- All the cables except for two cables were delivered.
- Cable check
- 70% done.
One cable found to be broken. Will send it back to the company -> status
- Call for shift for assembly help (Takahashi)
Made a call for shift for helping the installation works -> status
- PR2 wire breaker problem (Tatsumi)
- Removal of the wire breakers
- SUS wire breaker order status (Takahashi)
- Wire cleaning (Hirata)
Hirata will order 20m more wires. -> status
- Will wash Tungsten wire delivery status
- Production of additional PR winches (Akutsu)
- RM compensation mass
- Design status (Fabian): Do it later.
- Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws.
- PR Optical Bench (Akutsu)
- For PR2, we do need to raise the optical bench.
- Delivery date for the screws: Dec. 21
- PR2 vacuum installation will be Jan. 19
- For PR2, we do need to raise the optical bench.
- OSEM assembly status (Akutsu)
- OSEM screw length issue
- We have a lot of M5x20 BUMAX screws
Do we need to use longer ones ? -> Shoda will check with the actual test mass RM -> Seems OK (5mm spare length)
- OSEM screw length issue
- RM production (Takahashi)
What to do with the dirty RMs ?: Check with ATC if re-polishing the rough surface is possible or not (Takahashi) -> status
- Test hanging vacuum installation
- What needs to be done when the suspension is inside the chamber ?
- Transfer function measurement
- Spectrum
- Check the orientation of the mirror
- Check the height with laser marker
- What needs to be done when the suspension is inside the chamber ?
- List of what should be changed for PR3 hanging
- People should share ideas whenever they come up with missing thigns.
- Shoda made a spread sheet for keep tracking the ideas
- Next week (from 12/21) plan
- Test hanging
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
- PR2
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
- Test hanging
- Travel (Week of 12/21)
- Takahashi: Thu-Fri
- Shoda: Mon-Fri
- Mark: Mon-Tue
- Fabian: Mon-Fri
- Okutomi: Mon-Fri
- Fujii: Mon-Fri
- Ishizaki:
- Hirata:
- Ohishi:
- Travel (Week of 1/4)
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
* Joris: 12/7 - 12/18
BS
- BS Assembly Frame Design (Aso, Hirata)
- BS flag design (Mark, Fabian)
- BS gluing jigs (Tatsumi)
- Not enough crane height problem (Hirata, Saito)
- IP base clamp (Fabian)
- Bread board spring (Takahashi)
- BS clean bag (Aso)
ETM
- ETM assembly frame (Aso)
- Got a quotation
- Need to include a clean bag frame
Other
- bKAGRA preparation
- List of tasks for: BS, Type-A, Type-Bp modification, IMMT (Takahashi) Set up a Wiki page (Aso)
- Watch dog system (Tanaka)
- Will present at an AEL meeting.
- GAS blade inspection by Virgo (Takahashi)
To be shipped soon -> status
- Request to the ATC for the next year
Production of the blades of the Type-A BF: We should check the consistency of the optimal load at the TAMA prototype experiment and G&M measurements (SF and TF) (Takahashi) -
SF: G&M 164.7kg, TAMA: 165.3kg
TF: G&M 276kg, TAMA: 278kg
No obvious reason to distrust G&M's measurements
- Should consider in-situ measurement procedure of the optimal load during the installation of Type-A
- Safety at the site (Takahashi, Ishizaki)
Next meeting
2015/1/8 (Fri) 13:30 - F2F@Mitaka