2015/12/18 13:30 - Kamioka NAOJ Room + SeeVogh Participants: == Schedule == |
2015/12/18 13:30 - Kamioka TV conference room + SeeVogh Participants: Joris, Fabian, Hirata, Mark, Fujii, Shoda, Okutomi, Akutsu, Tatsumi, Raffaele, Takahashi == Schedule == |
Line 12: | Line 11: |
* PR2 preparation may take much longer * Need to consider a possibility of installing an ETM first. |
|
Line 16: | Line 17: |
* Removed the galled jacks. Used the crane to gently sit the suspension on the frame. * Two IM OSEM flags were broken. Taken out. * Now the suspension is freely hanging. |
|
Line 17: | Line 21: |
* Suspension was fine. * The interface plate was not easily accessible with the air gun. |
|
Line 18: | Line 24: |
* Lowest resonance ~ 15Hz * '''ATC people wants to have the results and the test condition (Takahashi) ''' |
|
Line 19: | Line 27: |
* All the cables are connected. Checked the connection except for the traverser. * Used cable ties to fix the cables on the ceiling of the clean booth. * Connecting the picomotor driver to the network for remote control |
|
Line 20: | Line 31: |
* Leveled the IM * BF tilt seems to be fine * OpLev for PR3 * Pillars were set up. * View ports are there. * QPD preparation is the remaining thing. Will try next week. |
|
Line 22: | Line 40: |
* Collected screws * RM carriage assembled * RM assembled * IM is on the frame. Started alignment. |
|
Line 25: | Line 47: |
* Sand the Ni-plating on the magnets before gluing to increase the adhesion ? -> Preparation Status * Need to order spare flag bases: 6 of them (Takahashi) -> Status |
* Sand the Ni-plating on the magnets in Mitaka on Monday (Fabian) * Glue the flags on Tue * __'''Need to order spare flag bases: 6 of them (Takahashi) -> Status ? '''__ * We need to secure things for water using Sunoko (duckboard). |
Line 29: | Line 54: |
* Takahashi will tell Hirata the proper locations of the pillars. | * __'''Takahashi will tell Hirata the proper locations of the pillars. -> status ? *Urgent* '''__ |
Line 32: | Line 57: |
* Created a copy of PR3 model for PR2. | |
Line 34: | Line 60: |
* Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi) * Balast mass design |
* Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. __'''Arrange with ATC people (Takahashi) -> Status ? '''__ * Balast mass design: '''Fabian will talk with Hirata on Monday. ''' |
Line 38: | Line 64: |
* Now we may move the traverser in the air a little bit. * Will test it at some point. * Traverser stop mechanism * Procurement status (Takahashi) * Clean work procedure |
* Need to check the condition of the traverser. '''Shoda will call Uraguchi-san from the site on Mon. and ask for his instruction on how to check the traverser. ''' * Cabling is now done. We can test it. * Traverser stop mechanism * Procurement status (Takahashi): Parts were delivered. '''Clean the parts on Monday (Hirata). ''' * Clean work procedure |
Line 46: | Line 72: |
* Ask Hirose-san about better wiping cloths (Aso): Texwipe Vectra Alpha 10 or TX8410. Asking if he has enough or we should order them. * KAGRA should have a special meeting for clean requirements: Aso had a meeting with Saito-san and Hirose-san. But the meeting was interrupted by a car accident. Will propose another meeting. |
* Ask Hirose-san about better wiping cloths (Aso): Texwipe Vectra Alpha 10 or TX8410. Asking if he has enough or we should order them -> Yes we can use them. '''Will order more (Aso)''' * KAGRA should have a special meeting for clean requirements: Aso had a meeting with Saito-san and Hirose-san. But the meeting was interrupted by a car accident. '''Will propose another meeting. ''' |
Line 50: | Line 76: |
* Need to give the rotation angle of the traverser top plate (Aso) | * '''Need to give the rotation angle of the traverser top plate (Aso) ''' |
Line 54: | Line 80: |
* Need to send more PTFE cable to finish the remaining two -> status | * __'''Need to send more PTFE cable to finish the remaining two -> status '''__ |
Line 56: | Line 82: |
* Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table. | * __'''Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table. '''__ |
Line 59: | Line 85: |
* 70% done. * One cable found to be broken. Will send it back to the company -> status |
* 70% done. * One cable found to be broken. __'''Will send it back to the company -> status '''__ |
Line 63: | Line 89: |
* Made a call for shift for helping the installation works -> status | * __'''Made a call for shift for helping the installation works -> status '''__ |
Line 67: | Line 93: |
* SUS wire breaker order status (Takahashi) | * __'''SUS wire breaker order status (Takahashi) '''__ * '''Propose to have a special meeting to Hirose-san (Aso) ''' |
Line 70: | Line 97: |
* Hirata will order 20m more wires. -> status * Will wash Tungsten wire delivery status |
* Hirata will order 20m more wires. -> Delivered. '''Will wipe in the next week. ''' * Will wash Tungsten wire delivery status -> Delivered. '''Will wipe in the next week. ''' |
Line 74: | Line 101: |
* 650um Tungsten wire test with 9.2kg is fine * '''Will test with 200um wires on Monday (7.2kg) with improved mass clamps (Hirata). ''' |
|
Line 76: | Line 105: |
* Design status (Fabian): Do it later. * Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws. |
* Design status (Fabian): Now done. * Need to buy screws for fixing the compensation masses. '''__Takahashi will check the lengths of screws. -> Status ? __''' |
Line 90: | Line 119: |
* What to do with the dirty RMs ?: Check with ATC if re-polishing the rough surface is possible or not (Takahashi) -> status | * What to do with the dirty RMs ?: __'''Check with ATC if re-polishing the rough surface is possible or not (Takahashi) -> status ? '''__ |
Line 104: | Line 133: |
* Next week (from 12/21) plan | * Missing items(to be purchased soon)<<BR>> * '''Picomotor drivers (Takahashi) ''' * '''Signal generators for LVDTs (Aso) ''' * '''Serial-Ethernet converter: 7 more (Shoda) ''' * '''Traverser motor driver (Shoda) ''' * '''Turn backles (bigger and eye). Smaller shackles. (Aso) ''' * LVDT(Joris) * Fixing LVDTs * Next week (from 12/21) plan |
Line 106: | Line 145: |
* Mon: * Tue: * Wed: * Thu: * Fri: * PR2 * Mon: * Tue: * Wed: * Thu: * Fri: |
* Mon: Traverser check. QPD preparation. * Tue: Transfer function measurements * Wed: * Thu: Orientation and height check * Fri: Orientation and height check * PR2 * Mon: Fabian will sand the magnets in Mitaka. Mark will align the IM * Tue: Preparation of the clean booth, bring in electronics to the tunnel. * Wed: * Thu: Traverser assembly preparation * Fri: Traverser assembly preparation |
Line 120: | Line 159: |
* Takahashi: Thu-Fri | * Takahashi: Mon-Tue |
Line 123: | Line 162: |
* Fabian: Mon-Fri * Okutomi: Mon-Fri |
* Fabian: Thu-Fri * Okutomi: Mon-Tue |
Line 126: | Line 165: |
* Ishizaki: * Hirata: * Ohishi: |
* Ishizaki: * Hirata: * Ohishi: |
Line 131: | Line 170: |
* Takahashi: * Shoda: * Mark: * Fabian: * Okutomi: * Fujii: * Ishizaki: * Hirata: * Ohishi: * Joris: 12/7 - 12/18 |
* Takahashi: Mon-Thu * Shoda: Mon-Thu * Mark: Mon-Thu * Fabian: Tue-Thu * Okutomi: Mon-Tue (available) * Fujii: - * Ishizaki: * Hirata: * Ohishi: * Joris: 1/11-1/29 * 1/18 Sekiguchi-kun's PhD defense |
Line 144: | Line 185: |
Line 160: | Line 200: |
Line 163: | Line 202: |
* Need to include a clean bag frame | * Need to include a clean bag frame. PR one was too weak. Make it stronger |
Line 167: | Line 206: |
* List of tasks for: BS, Type-A, Type-Bp modification, IMMT (Takahashi) Set up a Wiki page (Aso) | * __'''List of tasks for: BS, Type-A, Type-Bp modification, IMMT (Takahashi) by the end of the next week.'''__ Set up a Wiki page (Aso) |
Line 173: | Line 212: |
* To be shipped soon -> status | * To be shipped soon: '''Check the deadline for Virgo (Takahashi) ''' |
Line 180: | Line 219: |
* Should consider in-situ measurement procedure of the optimal load during the installation of Type-A | * If we can get help from ATC to measure the optimal load in Mitaka, it will be good. * '''Takahashi will make a plan for the optimal load check and ask ATC.''' The start of the Type-A install will be Oct. 2016 * How to manufacture the long maraging wires ? * One prototype was machined by Ojima * Aoshima can do the heat treatment for the long rod. '''Will ask them soon (Takahashi) ''' * How to test it ? * Use the unused assembly frame for Type-B ? |
Line 183: | Line 229: |
* Steps and clean belts will be ordered very soon. | |
Line 185: | Line 232: |
2015/12/25 (Fri) 13:30 - |
VIS Meeting on 2015/12/18
2015/12/18 13:30 -
Kamioka TV conference room + SeeVogh
Participants: Joris, Fabian, Hirata, Mark, Fujii, Shoda, Okutomi, Akutsu, Tatsumi, Raffaele, Takahashi
Schedule
- Schedule status (Aso)
- Latest schedule chart
- PR2 preparation may take much longer
- Need to consider a possibility of installing an ETM first.
PR
- Test Hanging Status (Takahashi)
- Installation into vacuum
- Removed the galled jacks. Used the crane to gently sit the suspension on the frame.
- Two IM OSEM flags were broken. Taken out.
- Now the suspension is freely hanging.
- Blowing test
- Suspension was fine.
- The interface plate was not easily accessible with the air gun.
- Hammering test
- Lowest resonance ~ 15Hz
ATC people wants to have the results and the test condition (Takahashi)
- Cabling
- All the cables are connected. Checked the connection except for the traverser.
- Used cable ties to fix the cables on the ceiling of the clean booth.
- Connecting the picomotor driver to the network for remote control
- EQ stop release
- Leveled the IM
- BF tilt seems to be fine
- Installation into vacuum
OpLev for PR3
- Pillars were set up.
- View ports are there.
- QPD preparation is the remaining thing. Will try next week.
- PR2 Status (Mark, Fabian)
- Collected screws
- RM carriage assembled
- RM assembled
- IM is on the frame. Started alignment.
- What can we do before the PR2 arrives
- Preparation of the flags
- Sand the Ni-plating on the magnets in Mitaka on Monday (Fabian)
- Glue the flags on Tue
Need to order spare flag bases: 6 of them (Takahashi) -> Status ?
- Preparation of the flags
- We need to secure things for water using Sunoko (duckboard).
- Location of the EQ stop pillars (Takahashi)
Takahashi will tell Hirata the proper locations of the pillars. -> status ? *Urgent*
- Digital System (Okutomi, Fujii)
- Created a copy of PR3 model for PR2.
- BF Optimal Weight (Takahashi)
Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi) -> Status ?
Balast mass design: Fabian will talk with Hirata on Monday.
- Traverser actuation check (Shoda)
Need to check the condition of the traverser. Shoda will call Uraguchi-san from the site on Mon. and ask for his instruction on how to check the traverser.
- Cabling is now done. We can test it.
- Traverser stop mechanism
Procurement status (Takahashi): Parts were delivered. Clean the parts on Monday (Hirata).
- Clean work procedure
Need to check with Miyoki-san when the clean suits will be delivered (Aso) -> 1/15
Ask Hirose-san about better wiping cloths (Aso): Texwipe Vectra Alpha 10 or TX8410. Asking if he has enough or we should order them -> Yes we can use them. Will order more (Aso)
KAGRA should have a special meeting for clean requirements: Aso had a meeting with Saito-san and Hirose-san. But the meeting was interrupted by a car accident. Will propose another meeting.
- PR CAD model and assembly drawings (Hirata)
Need to give the rotation angle of the traverser top plate (Aso)
- Cable status (Takahashi)
- All the cables except for two cables were delivered.
Need to send more PTFE cable to finish the remaining two -> status
- Need to send the cables used for the test hanging once it is finshed.
Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table.
- All the cables except for two cables were delivered.
- Cable check
- 70% done.
One cable found to be broken. Will send it back to the company -> status
- Call for shift for assembly help (Takahashi)
Made a call for shift for helping the installation works -> status
- PR2 wire breaker problem (Tatsumi)
- Removal of the wire breakers
SUS wire breaker order status (Takahashi)
Propose to have a special meeting to Hirose-san (Aso)
- Wire cleaning (Hirata)
Hirata will order 20m more wires. -> Delivered. Will wipe in the next week.
Will wash Tungsten wire delivery status -> Delivered. Will wipe in the next week.
- Production of additional PR winches (Akutsu)
- 650um Tungsten wire test with 9.2kg is fine
Will test with 200um wires on Monday (7.2kg) with improved mass clamps (Hirata).
- RM compensation mass
- Design status (Fabian): Now done.
Need to buy screws for fixing the compensation masses. Takahashi will check the lengths of screws. -> Status ?
- PR Optical Bench (Akutsu)
- For PR2, we do need to raise the optical bench.
- Delivery date for the screws: Dec. 21
- PR2 vacuum installation will be Jan. 19
- For PR2, we do need to raise the optical bench.
- OSEM assembly status (Akutsu)
- OSEM screw length issue
- We have a lot of M5x20 BUMAX screws
Do we need to use longer ones ? -> Shoda will check with the actual test mass RM -> Seems OK (5mm spare length)
- OSEM screw length issue
- RM production (Takahashi)
What to do with the dirty RMs ?: Check with ATC if re-polishing the rough surface is possible or not (Takahashi) -> status ?
- Test hanging vacuum installation
- What needs to be done when the suspension is inside the chamber ?
- Transfer function measurement
- Spectrum
- Check the orientation of the mirror
- Check the height with laser marker
- What needs to be done when the suspension is inside the chamber ?
- List of what should be changed for PR3 hanging
- People should share ideas whenever they come up with missing thigns.
- Shoda made a spread sheet for keep tracking the ideas
Missing items(to be purchased soon)
Picomotor drivers (Takahashi)
Signal generators for LVDTs (Aso)
Serial-Ethernet converter: 7 more (Shoda)
Traverser motor driver (Shoda)
Turn backles (bigger and eye). Smaller shackles. (Aso)
- LVDT(Joris)
- Fixing LVDTs
- Next week (from 12/21) plan
- Test hanging
- Mon: Traverser check. QPD preparation.
- Tue: Transfer function measurements
- Wed:
- Thu: Orientation and height check
- Fri: Orientation and height check
- PR2
- Mon: Fabian will sand the magnets in Mitaka. Mark will align the IM
- Tue: Preparation of the clean booth, bring in electronics to the tunnel.
- Wed:
- Thu: Traverser assembly preparation
- Fri: Traverser assembly preparation
- Test hanging
- Travel (Week of 12/21)
- Takahashi: Mon-Tue
- Shoda: Mon-Fri
- Mark: Mon-Tue
- Fabian: Thu-Fri
- Okutomi: Mon-Tue
- Fujii: Mon-Fri
- Ishizaki:
- Hirata:
- Ohishi:
- Travel (Week of 1/4)
- Takahashi: Mon-Thu
- Shoda: Mon-Thu
- Mark: Mon-Thu
- Fabian: Tue-Thu
- Okutomi: Mon-Tue (available)
- Fujii: -
- Ishizaki:
- Hirata:
- Ohishi:
* Joris: 1/11-1/29
* 1/18 Sekiguchi-kun's PhD defense
BS
- BS Assembly Frame Design (Aso, Hirata)
- BS flag design (Mark, Fabian)
- BS gluing jigs (Tatsumi)
- Not enough crane height problem (Hirata, Saito)
- IP base clamp (Fabian)
- Bread board spring (Takahashi)
- BS clean bag (Aso)
ETM
- ETM assembly frame (Aso)
- Got a quotation
- Need to include a clean bag frame. PR one was too weak. Make it stronger
Other
- bKAGRA preparation
List of tasks for: BS, Type-A, Type-Bp modification, IMMT (Takahashi) by the end of the next week. Set up a Wiki page (Aso)
- Watch dog system (Tanaka)
- Will present at an AEL meeting.
- GAS blade inspection by Virgo (Takahashi)
To be shipped soon: Check the deadline for Virgo (Takahashi)
- Request to the ATC for the next year
Production of the blades of the Type-A BF: We should check the consistency of the optimal load at the TAMA prototype experiment and G&M measurements (SF and TF) (Takahashi) -
SF: G&M 164.7kg, TAMA: 165.3kg
TF: G&M 276kg, TAMA: 278kg
No obvious reason to distrust G&M's measurements
- If we can get help from ATC to measure the optimal load in Mitaka, it will be good.
Takahashi will make a plan for the optimal load check and ask ATC. The start of the Type-A install will be Oct. 2016
- How to manufacture the long maraging wires ?
- One prototype was machined by Ojima
Aoshima can do the heat treatment for the long rod. Will ask them soon (Takahashi)
- How to test it ?
- Use the unused assembly frame for Type-B ?
- Safety at the site (Takahashi, Ishizaki)
- Steps and clean belts will be ordered very soon.
Next meeting
2015/12/25 (Fri) 13:30 -
2015/1/8 (Fri) 13:30 - F2F@Mitaka