Line 6: Line 6:
Participants:  Participants:
Line 10: Line 10:
  * Latest schedule chart   * [[attachment:05_VIS-20151224.pdf|Latest schedule chart]]
Line 55: Line 55:
  * One cable found to be broken. Will send it back to the company -> status    * One cable found to be broken. Will send it back to the company -> status
Line 73: Line 73:
  * Need to buy screws for fixing the compensation masses.    * Need to buy screws for fixing the compensation masses.
Line 84: Line 84:
  * What to do with the dirty RMs ?: Check with ATC if re-polishing the rough surface is possible or not (Takahashi) -> status ?    * What to do with the dirty RMs ?: Check with ATC if re-polishing the rough surface is possible or not (Takahashi) -> status ?
Line 100: Line 100:
   * Mon: 
   * Tue: 
   * Mon:
   * Tue:
Line 103: Line 103:
   * Thu:     * Thu:
Line 107: Line 107:
   * Mon: 
   * Tue: 
   * Mon:
   * Tue:
Line 110: Line 110:
   * Thu:     * Thu:
Line 119: Line 119:
  * Fujii:    * Fujii:
Line 125: Line 125:
  * Takahashi: 
  * Shoda: 
  * Mark: 
  * Fabian: 
  * Okutomi: 
  * Takahashi:
  * Shoda:
  * Mark:
  * Fabian:
  * Okutomi:
Line 169: Line 169:
  * If we can get help from ATC to measure the optimal load in Mitaka, it will be good.
   * Takahashi will make a plan for the optimal load check and ask ATC.-> Status ?
  * If we can get help from ATC to measure the optimal load in Mitaka, it will be good.
  * Takahashi will make a plan for the optimal load check and ask ATC.-> Status ?

VIS Meeting on 2015/12/25

2015/12/25 13:30 -

Kamioka TV conference room + SeeVogh

Participants:

Schedule

PR

  • Test Hanging Status (Takahashi)
    • Transfer function measurements (Shoda)
    • OpLev (Shoda)

    • Mirror orientation confirmation (Shoda)
  • PR2 Status (Mark, Fabian)
    • Flag preparation status (Fabian)
    • Spare flag order status (Takahashi)
  • We need to secure things for water using Sunoko (duckboard).
  • Location of the EQ stop pillars (Takahashi)
    • Locations were reported by Takahashi
      • Interference with OpLev (Akutsu)

  • Digital System (Okutomi, Fujii)
  • BF Optimal Weight (Takahashi)
    • Check the optimal load for the ETM BFs at the ATC: Need to be done before the end of Jan. Arrange with ATC people (Takahashi) -> Status

    • Balast mass design: Fabian will talk with Hirata on Monday. -> Status

  • Traverser actuation check (Shoda)
    • Need to check the condition of the traverser. -> Status (Shoda)

  • Traverser stop mechanism
    • Procurement status (Takahashi): Parts were delivered. Clean the parts on Monday (Hirata). -> Status

  • Clean work procedure
    • Order clean wipes (Aso)
    • KAGRA should have a special meeting for clean requirements: Will propose another meeting. (Aso)

  • PR CAD model and assembly drawings (Hirata)
    • Need to give the rotation angle of the traverser top plate (Aso)

  • Cable status (Takahashi)
    • All the cables except for two cables were delivered.
      • Need to send more PTFE cable to finish the remaining two -> status

      • Need to send the cables used for the test hanging once it is finshed.
    • Made a cable list -> Put a link to the excel file on Wiki. Takahashi will improve the table.

  • Cable check
    • 70% done.
    • One cable found to be broken. Will send it back to the company -> status

  • Call for shift for assembly help (Takahashi)
    • Made a call for shift for helping the installation works -> status

  • PR2 wire breaker problem (Mark, Tatsumi)
    • Removal of the wire breakers (Mark)
    • SUS wire breaker order status (Takahashi)
  • Wire cleaning (Hirata)
    • Hirata will order 20m more wires. -> Delivered. Will wipe in the next week. -> Status

    • Will wash Tungsten wire delivery status -> Delivered. Will wipe in the next week -> Status

  • Production of additional PR winches (Akutsu)
    • 650um Tungsten wire test with 9.2kg is fine
    • Will test with 200um wires on Monday (7.2kg) with improved mass clamps (Hirata). -> Status

  • RM compensation mass
    • Need to buy screws for fixing the compensation masses.
      • M6-16mm and M6-20mm are necessary. -> are these available ?

  • PR Optical Bench (Akutsu)
    • For PR2, we do need to raise the optical bench.
      • Delivery date for the screws: Dec. 21
      • PR2 vacuum installation will be Jan. 19
  • OSEM assembly status (Akutsu)
  • RM production (Takahashi)
    • What to do with the dirty RMs ?: Check with ATC if re-polishing the rough surface is possible or not (Takahashi) -> status ?

  • List of what should be changed for PR3 hanging
  • Missing items(to be purchased soon)

    • Picomotor drivers (Takahashi)

    • Signal generators for LVDTs (Aso) -> Asking for quotation

    • Serial-Ethernet converter: 7 more (Shoda) -> Asked Ishizaki-san to buy them

    • Traverser motor driver (Shoda)

    • Turn backles (bigger and eye). Smaller shackles. (Aso) -> TBD

  • Next week (from 1/4) plan
    • Test hanging
      • Mon:
      • Tue:
      • Wed:
      • Thu:
      • Fri: F2F@Mitaka
    • PR2
      • Mon:
      • Tue:
      • Wed:
      • Thu:
      • Fri: F2F@Mitaka
  • Travel (Week of 1/4)
    • Takahashi: Mon-Thu
    • Shoda: Mon-Thu
    • Mark: Mon-Thu
    • Fabian: Tue-Thu
    • Okutomi: Mon-Tue (available)
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:
  • Travel (Week of 1/11)
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii: -
    • Ishizaki:
    • Hirata:
    • Ohishi:

* Joris: 1/11-1/29

* 1/18 Sekiguchi-kun's PhD defense

BS

  • BS Assembly Frame Design (Aso, Hirata)
  • BS flag design (Mark, Fabian)
  • BS gluing jigs (Tatsumi)
  • Not enough crane height problem (Hirata, Saito)
  • IP base clamp (Fabian)
  • Bread board spring (Takahashi)
  • BS clean bag (Aso)

ETM

  • ETM assembly frame (Aso)
    • Ordering in progress

Other

  • bKAGRA preparation
    • List of tasks for: BS, Type-A, Type-Bp modification, IMMT (Takahashi) by the end of the next week. Set up a Wiki page (Aso)

  • Watch dog system (Tanaka)
    • Will present at an AEL meeting.
  • GAS blade inspection by Virgo (Takahashi)
    • To be shipped soon: Check the deadline for Virgo (Takahashi) -> Status

  • Type-A Filters Optimal Load Measurements
    • If we can get help from ATC to measure the optimal load in Mitaka, it will be good.
    • Takahashi will make a plan for the optimal load check and ask ATC.-> Status ?

    • How to manufacture the long maraging wires ?
      • One prototype was machined by Ojima
      • Aoshima can do the heat treatment for the long rod. Will ask them soon (Takahashi) -> Status

      • How to test it ?
        • Use the unused assembly frame for Type-B ?
  • Safety at the site (Takahashi, Ishizaki)

Next meeting

2015/1/8 (Fri) 13:30 - F2F@Mitaka