Differences between revisions 3 and 4
Revision 3 as of 2016-01-15 01:42:10
Size: 8575
Editor: YoichiAso
Comment:
Revision 4 as of 2016-01-15 02:38:03
Size: 7100
Editor: YoichiAso
Comment:
Deletions are marked like this. Additions are marked like this.
Line 23: Line 23:
 * Mon: Sekiguchi PhD defense
 * Tue: Fix the traverser
 * Wed:
 * Thu:
 * Fri:
Line 30: Line 35:
 * Mon:
 * Tue:
 * Wed:
 * Thu:
 * Fri:
Line 35: Line 45:
 * Coil winding (Takahashi)
Line 38: Line 49:
 * Travel (Week of 1/18)
  * Takahashi:Tue-Fri
  * Shoda:Tue-Fri
  * Mark:
  * Fabian:
  * Okutomi:Tue-Fri
  * Fujii:Tue-Fri
  * Ishizaki:
  * Hirata:
  * Ohishi:Mon-Tue in Mitaka

 * Travel (Week of 1/25)
  * Takahashi:
  * Shoda:
  * Mark:
  * Fabian:
  * Okutomi:
  * Fujii:
  * Ishizaki:
  * Hirata:
  * Ohishi:

 * Joris: 1/11-1/29

 * 1/18 Sekiguchi-kun's PhD defense
Line 55: Line 91:
 * #Clean work procedure
  * Order clean wipes (Aso)
  * KAGRA should have a special meeting for clean requirements: Will propose another meeting. (Aso)
Line 62: Line 102:

== Electronics ==
 * #Digital System (Okutomi, Fujii)

 * LVDT Distributor problem
  * Connector for the coil driver input is D9 whereas the output from the HP coil driver is D15.

  * Discussed at the AEL meeting on 1/12
   * As a temporary measure, we will make a conversion cable from D15 to D9

   * For the long term measure, AEL is considering to order such cables to a company with a proper care of pin 5.

 * #Clean work procedure
  * Order clean wipes (Aso)
  * KAGRA should have a special meeting for clean requirements: Will propose another meeting. (Aso)

 * #Cable status (Takahashi)
  * Need to send more PTFE cable to finish the remaining two -> '''Will do it in the next week '''
  * Need to send the cables used for the test hanging once it is finished. -> '''Will send them once the test hanging is disassembled. '''

 * Cable check
  * Liu-kun came to work on it. -> Status ? (Takahashi)

  * #One cable found to be broken. Will send it back to the company -> not yet. Send it together with the other cable related items.
Line 106: Line 122:
  * Picomotor drivers (Takahashi)''' ''' -> Delivered
  * Signal generators for LVDTs (Aso)''' ''' -> Ordered. Will be delivered very soon.
  * Serial-Ethernet converter: 7 more (Shoda)''' ''' -> Ishizaki-san ordered them. Delivery 1/14.
  * #Picomotor drivers (Takahashi)''' ''' -> Delivered
  * #Signal generators for LVDTs (Aso)''' ''' -> Ordered. Will be delivered very soon.
  * #Serial-Ethernet converter: 7 more (Shoda)''' ''' -> Ishizaki-san ordered them. Delivery 1/14.
Line 110: Line 126:
  * Turn backles (bigger and eye). Smaller shackles. (Aso)''' '''-> Ishizaki-san ordered. Delivery may be 1/18   * #Turn backles (bigger and eye). Smaller shackles. (Aso)''' '''-> Ishizaki-san ordered. Delivery may be 1/18
Line 112: Line 128:
 * Next week (from 1/12) plan
  * Test hanging
   * Mon: holiday
   * Tue:Pull out, Remove the EQ stop around the mirror.
   * Wed: Move PR3 to the spare mirror container. Take out the RM and the spare mirror
   * Thu: Remove the BF from the traverser
   * Fri:Continue
== Electronics ==
 * What are necessary in the next few weeks ?
Line 120: Line 131:
  * PR2
   * Mon:holiday
   * Tue:
   * Wed:Covering up the assembly set up
   * Thu: Covering up the assembly set up
   * Fri:
 * Electronics diagram and review
  * [[attachment:20151225_081424000_iOS.png|A diagram from Shoda]]
  * '''Mark will make overview diagrams of VIS electronics'''
Line 127: Line 135:
 * Travel (Week of 1/12)
  * Takahashi:Tue-Fri
  * Shoda:Tue-Fri
  * Mark:Tue-Thu
  * Fabian:Tue-Thu
  * Okutomi:Tue-Fri
  * Fujii:Tue-Fri
  * Ishizaki:
  * Hirata:
  * Ohishi:in Mitaka
 * LVDT Distributor problem
  * Connector for the coil driver input is D9 whereas the output from the HP coil driver is D15.
Line 138: Line 138:
 * Travel (Week of 1/18)
  * Takahashi:Tue-Fri
  * Shoda: Tue-Fri
  * Mark:
  * Fabian:
  * Okutomi: Tue-Fri
  * Fujii: Tue-Fri
  * Ishizaki:
  * Hirata:
  * Ohishi:
  * Discussed at the AEL meeting on 1/12
   * As a temporary measure, we will make a conversion cable from D15 to D9
   * For the long term measure, AEL is considering to order such cables to a company with a proper care of pin 5.
Line 149: Line 142:
* Joris: 1/11-1/29  * #Digital System (Okutomi, Fujii)
Line 151: Line 144:
* 1/18 Sekiguchi-kun's PhD defense  * #Cable status (Takahashi)
  * Need to send more PTFE cable to finish the remaining two -> '''Will do it in the next week '''
  * Need to send the cables used for the test hanging once it is finished. -> '''Will send them once the test hanging is disassembled. '''
Line 153: Line 148:
== BS ==  * Cable check
  * Liu-kun came to work on it. -> Status ? (Takahashi)

  * #One cable found to be broken. Will send it back to the company -> not yet. Send it together with the other cable related items.

== #BS and SR ==
Line 169: Line 169:
== ETM ==
 * Preparation tasks
  * Prepare missing parts
   * Check what are missing: Tasumi
   * Get quotation: Tasumi
    * http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4741
   * Order the missing parts: Takahashi
   * Wind coil wires: Takahashi+Some student (from Ando-lab ?)
   * Check coils: The above student
  * Disassemble the suspensions at Mitaka: Ohishi, Torii,
  * Wash the suspension part: Ohishi + Hirata
  * Send the parts to Kamioka: Hirata
  * Assemble the suspensions at Kamioka: Ohishi, Tomaru, Uchiyama
   * Transfer function check
   * Transportation to the end: we need to consider the actual method carefully
  * Send PRMs to Kamioka: Ask Tatsumi-san (Aso)
   * Drag wipe at Mitaka
   * First contact ?
   * Container ?

== Other ==
 * Fishing rod production stauts (Takahashi)
  * We may not be able to buy blades in this FY. '''WIll check with the company (Takahashi) '''
== Type A ==
 * Fishing rod production status (Takahashi)
  * We may not be able to buy blades in this FY. -> WIll check with the company (Takahashi)
Line 193: Line 173:
 * bKAGRA preparation
  * [[attachment:Task for bKAGRA.xls|Task list]] (Takahashi)
  * Roughly divide the task to three categories
   * Preparation of Type-B suspensions (BS and SR)
   * Modification of PR suspensions
   * Type-A

 * Electronics
  * Electronics diagram and review
   * [[attachment:20151225_081424000_iOS.png|A diagram from Shoda]]
   * '''Mark will make overview diagrams of VIS electronics'''
  * What are necessary in the next few weeks ?
 * Installation procedure document
  * Many people need to contribute to the document. However, we need one person responsible for the consistency of the document.
  * BS installation document: Mark will be the editor.

 * Watch dog system (Tanaka)
  * Will present at an AEL meeting on 1/12

 * GAS blade inspection by Virgo (Takahashi)
  * Shipped the blades. Will get results in 1-2 months.
Line 216: Line 175:
  * If we can get help from ATC to measure the optimal load in Mitaka, it will be good.
* Takahashi will make a plan for the optimal load check and ask ATC.-> '''Will make one in the next week. '''
  * How to manufacture the long maraging wires ?
  * Takahashi will make a plan for the optimal load check and ask ATC.-> Will make one in the next week.
  * #How to manufacture the long maraging wires ?
Line 224: Line 182:
 * Safety at the site (Takahashi, Ishizaki)
  * The heavy side flange was difficult to put it back.
== #Type-Bp modification ==
== Other ==
 * #Installation procedure document
  * Many people need to contribute to the document. However, we need one person responsible for the consistency of the document.
  * BS installation document: Mark will be the editor.

 * Watch dog system (Tanaka)
  * Presentation at the next AEL meeting

 * #GAS blade inspection by Virgo (Takahashi)
  * Shipped the blades. Will get results in 1-2 months.

 * Safety
Line 228: Line 197:
2015/1/15 (Fri) 13:30 - 2015/1/22 (Fri) 13:30 -

VIS Meeting on 2016/1/15

2015/1/15 13:30 -

Kamioka TV conference room + SeeVogh

Participants:

bKAGRA preparation

  • Three big categories of the tasks
    • Type-A
    • Type-B (BS and SRC)
    • Type-Bp modification

Schedule

  • Schedule status (Aso)

PR3

  • Test Hanging Status (Takahashi)
  • PR3 Installation Status (Takahashi)
  • #The frame for the clean bag is bent. We cannot remove the nut. Probably we need to cut the rod once we take the suspension out of the chamber. Need to prepare a replacement rod (Aso)

Plan for the next week

  • Mon: Sekiguchi PhD defense
  • Tue: Fix the traverser
  • Wed:
  • Thu:
  • Fri:

PR2

  • PR2 status (Mark, Fabian)
  • IOO wants the optical bench back (Aso)
  • #OpLev interference check (Akutsu)

Plan for the next week

  • Mon:
  • Tue:
  • Wed:
  • Thu:
  • Fri:

iKAGRA ETM suspension

  • Disassembly (and cleaning) of the suspensions (Ohishi)
  • Procurement of missing parts (Tatsumi)
  • PRM transportation (Tatsumi)
  • Coil winding (Takahashi)

Plan for the next week

Travel Plans

  • Travel (Week of 1/18)
    • Takahashi:Tue-Fri

    • Shoda:Tue-Fri

    • Mark:
    • Fabian:
    • Okutomi:Tue-Fri

    • Fujii:Tue-Fri

    • Ishizaki:
    • Hirata:
    • Ohishi:Mon-Tue in Mitaka

  • Travel (Week of 1/25)
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:
  • Joris: 1/11-1/29
  • 1/18 Sekiguchi-kun's PhD defense

Other Mechanical Issues

  • BF Optimal Weight (Takahashi)
    • Inscription of the number on the BF #2 and BS BF should be done before the transportation to Kamioka on Thursday. Will ask Saito-san of ATC for his availability (Takahashi)
    • Balast mass design: Will ask for quotation to companies now (Hirata)
  • Traverser actuation check (Shoda)
  • Traverser stop mechanism
    • Parts were sent to Kamioka.
    • Takahashi-san will find where these are stored
  • #PR CAD model and assembly drawings (Hirata)
    • Aso calculated the rotation angle
      • PR3: 0.786deg counter clockwise from the line connecting the centers of the PR3 and BS chambers.
      • Will make a report soon.
  • #Clean work procedure
    • Order clean wipes (Aso)
    • KAGRA should have a special meeting for clean requirements: Will propose another meeting. (Aso)
  • PR2 wire breaker problem (Mark, Tatsumi)
    • Prism removal status (Mark)
    • #SUS wire breaker order status (Takahashi) -> Expected delivery date is 1/22. Waiting for more concrete answer from the company.

    • For BS prisms, should we ask the company which made LIGO prisms ?
      • Contact the company LIGO used for the possibility of buying sapphire prisms (Mark)
      • Can we make SR wire breakers bigger ? Hirata-san's report.

  • #Wire cleaning (Hirata)
    • Hirata will order 20m more wires. -> Delivered. Will wipe in the next week. -> Finished. Will send to Kamioka soon.

    • Will wash Tungsten wire delivery status -> Delivered. Will wipe in the next week -> Finished. Will send to Kamioka soon.

  • #Production of additional PR winches (Akutsu)
    • Shipping status (Takahashi, Hirata) -> Wrapped. Will be shipped with IP in the next week.

  • #OSEM assembly status (Akutsu)
  • RM production (Takahashi)
    • Which RMs are really clean ?
    • Ask Fukushima-san if machining the slit part is possible or not (Takahashi)
  • List of what should be changed for PR3 hanging
  • Missing items(to be purchased soon)
    • #Picomotor drivers (Takahashi) -> Delivered

    • #Signal generators for LVDTs (Aso) -> Ordered. Will be delivered very soon.

    • #Serial-Ethernet converter: 7 more (Shoda) -> Ishizaki-san ordered them. Delivery 1/14.

    • Traverser motor driver (Shoda) -> Will discuss Uraguchi-san. Need a box for stepping motor driver. -> These are for PR2. Will be ordered sometime.

    • #Turn backles (bigger and eye). Smaller shackles. (Aso) -> Ishizaki-san ordered. Delivery may be 1/18

Electronics

  • What are necessary in the next few weeks ?
  • Electronics diagram and review
  • LVDT Distributor problem
    • Connector for the coil driver input is D9 whereas the output from the HP coil driver is D15.
    • Discussed at the AEL meeting on 1/12
      • As a temporary measure, we will make a conversion cable from D15 to D9
      • For the long term measure, AEL is considering to order such cables to a company with a proper care of pin 5.
  • #Digital System (Okutomi, Fujii)
  • #Cable status (Takahashi)
    • Need to send more PTFE cable to finish the remaining two -> Will do it in the next week

    • Need to send the cables used for the test hanging once it is finished. -> Will send them once the test hanging is disassembled.

  • Cable check
    • Liu-kun came to work on it. -> Status ? (Takahashi)

    • #One cable found to be broken. Will send it back to the company -> not yet. Send it together with the other cable related items.

#BS and SR

  • BS Assembly Frame Design (Aso, Hirata)
  • BS flag design (Mark, Fabian)
  • BS gluing jigs (Tatsumi)
  • Not enough crane height problem (Hirata, Saito)
  • IP base clamp (Fabian)
  • Bread board spring (Takahashi)
    • Need a review: Show the design at the next F2F VIS meeting (Takahashi)
  • BS clean bag (Aso)

Type A

  • Fishing rod production status (Takahashi)
    • We may not be able to buy blades in this FY. -> WIll check with the company (Takahashi)

    • Stepping motors and other components can be purchased within this FY.
  • Type-A Filters Optimal Load Measurements
    • Takahashi will make a plan for the optimal load check and ask ATC.-> Will make one in the next week.

    • #How to manufacture the long maraging wires ?
      • One prototype was machined by Ojima
      • Aoshima can do the heat treatment for the long rod. Will ask them soon (Takahashi) -> Still waiting for a quotation.

      • How to test it ?
        • We can use the prototype assembly frame in TAMA.

#Type-Bp modification

Other

  • #Installation procedure document
    • Many people need to contribute to the document. However, we need one person responsible for the consistency of the document.
    • BS installation document: Mark will be the editor.
  • Watch dog system (Tanaka)
    • Presentation at the next AEL meeting
  • #GAS blade inspection by Virgo (Takahashi)
    • Shipped the blades. Will get results in 1-2 months.
  • Safety

Next meeting

2015/1/22 (Fri) 13:30 -

KAGRA/Subgroups/VIS/VISMinutes20160115 (last edited 2016-01-18 05:45:37 by YoichiAso)