= VIS Meeting on 2016/2/12 = 2015/2/12 13:30 -15:30 Kamioka TV conference room + !SeeVogh Participants:Takahashi, Mark, Hirata, Fabian, Shoda, Fujii, Aso, Sekiguchi, Akutsu, Okutomi == Schedule == * Schedule status (Aso) ([[https://www.dropbox.com/s/y586flgsr0usmvx/05_VIS-20160212.pdf?dl=0|Chart]]) == PR3 == * PR3 Installation Status (Takahashi) * Wire breaker groove problem * Wrong surface was glued on the mirror side. So no groove is present where the wires touch. * Put alminum foil between the prism and the wires * Current status (http://klog.icrr.u-tokyo.ac.jp/osl/?r=756) * IM and the bottom filter is connected. * Adjusting the weight of the IM * #Traverser repair: Repair of the broken ones at Mitaka -> Uraguchi-san is working on it. * #Screws to fix the front and back rings the RM were too long, or the tapping in the holes were too short. Couldn't use M5x40. Ordered M5x35 with vent holes. -> Delivered. '''Remember to replace them''' * The frame for the clean bag is bent. * Reinformcement design by Mirapro * [[https://www.dropbox.com/s/l8er09c3d7lmsgr/VP5904-A_Bag%20Frame%20Assy.pdf?dl=0|2D Drawing]] * [[https://www.dropbox.com/s/j8rcpvytin0qft6/Bag%20Frame.stp?dl=0|STEP]] * [[https://www.dropbox.com/s/llu99rjj0gnesz2/Bag%20Assy.png?dl=0|Assembly image]] * [[https://www.dropbox.com/s/zsrizfnzx9xuovp/Bag%20Assy.stp?dl=0|Assembly STEP]] * Tell Mirapro to go ahead (Aso) * Mirapro will come on 22nd to make changes. * Crane will be not available on 2/25 for the crane upgrade to remote control. We need to coordinate with Uchiyama-san if we want to do the vacuum installation on 25th. === Plan for the next week === * Mon: IM hanging * Tue: IMRM hanging * Wed: IM alignment * Thu: OSEM setup * Fri: == iKAGRA ETM suspension == * Assembly of the suspension (Ohishi) * Missing parts (Tatsumi, Takahashi) * Insulation tubes for picomotor connectors * Tubes were delivered on Wed. * Cable ties are not yet delivered -> check the delivery date (Takahashi) * Suspension Test (Ohishi) * Coil winding (Takahashi) * Made 13 coils in total. * Need to send 3 bobins to the coil winding company * TAMA PRM transportation (Tatsumi) -> done today. === Plan for the next week === == Travel Plans == * Travel (Week of 2/15) * Takahashi:Mon-Thu * Shoda:Mon-Thu * Mark: * Fabian: * Okutomi:Mon-Thu * Fujii:Mon-Thu * Ishizaki: * Hirata: * Ohishi: * Sekiguchi: Mon-Thu VIS F2F 2/19 KAGRA F2F 2/21 - 23 * Travel (Week of 2/22) * Takahashi:Wed - Thu (Fri: Akeno for the acceptance of IP from NIKHEF) * Shoda:Wed - Fri * Mark: * Fabian: * Okutomi:Wed - Fri * Fujii:Wed - Fri * Ishizaki: * Hirata: * Ohishi: == Other Mechanical Issues == * Rotation angle of the PR3 mirror * 0.786deg counter clockwise from the line connecting the centers of the PR3 and BS chambers. * 0.619deg counter clockwise with respect to the chamber ([[https://www.dropbox.com/s/073wcbz652i016a/VM5920_KAGRA真空容器PR3_Type-Bp.pdf?dl=0|schematic]]) * Currently the mirror is rotated by 0.65deg (measured at the time of the test hanging). * This is well within the actuation range of the traverser. -> Will not make any further adjustment. * #Wire winches * Now in the ATC clean room. * Asked Ikenue-san to repair it (Takahashi) * #Clean work procedure * Will be discussed at F2F. * #BF Optimal Weight (Takahashi) * #Balast masses: Delivered to Mitaka. Will send them to Kamioka (Hirata) * #IM wire clamps * #Need to send the wire clamps used for the test hanging to I-ject: it was sent to I-ject (Takahashi) * #Traverser actuation check (Shoda) * #Wire cleaning (Hirata) * Hirata will order 20m more wires. -> Delivered. Will wipe in the next week. -> Finished. Will send to Kamioka soon. * Will wash Tungsten wire delivery status -> Delivered. Will wipe in the next week -> Finished. Will send to Kamioka soon. * #Production of additional PR winches (Akutsu) * Shipping status (Takahashi, Hirata) -> Wrapped. Will be shipped with IP in the next week. * #OSEM assembly status (Akutsu) * #List of what should be changed for PR3 hanging * People should share ideas whenever they come up with missing thigns. * Shoda made a spread sheet for keep tracking the ideas * https://docs.google.com/spreadsheets/d/1zZaLObWjDSEOTrr85Hz0ApXxEUChK3xJ_chk0f7r5nY/edit?usp=sharing * All the items are now done or being taken care of * #Missing items(to be purchased soon) * #Traverser motor driver (Shoda)''' ''' -> Will discuss Uraguchi-san. Need a box for stepping motor driver. -> These are for PR2. Will be ordered sometime. == Electronics == * What are necessary in the next few weeks ? * Nothing * Electronics diagram and review * Mark: detailed schematics nearly ready to post - [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3615|D1503615 (full PR3)]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4795|D1604795 (iKAGRA PR3)]] * Mark: started overview schematic [[attachment:Cabling Overview.graffle.pdf|diagram]], * Need to make Guradian script for PR3. Shoda + Fujii and Okutomi will write one after the mechanical installation is finished. * Watch dog system (Tanaka) * #LVDT distributor connector problem * Miyakawa-san circulated a design of the conversion cable (D9-D15): [[attachment:ESB-K003-G004-01A.pdf|drawing]] * #Digital System (Okutomi, Fujii) * #Cable status (Takahashi) * Need to send more PTFE cable to finish the remaining two -> '''Will do it in the next week ''' * Need to send the cables used for the test hanging once it is finished. -> '''Will send them once the test hanging is disassembled. ''' * #Cable check * Liu-kun Zhao-kun finished checking all the cables. They found another broken cable. * Will send the broken cables together with the other cable related items (Takahashi). == bKAGRA preparation == * Three big categories of the tasks * Type-A: Leader = Takahashi: Task list, team members * Type-B (BS and SRC): Leader = Mark: Task list, team members * Type-Bp modification: Continue discussion (Aso, Raffaele) == Common Issues == == Type-B == * Task list[[KAGRA/Subgroups/VIS/TypeB/TaskList]] * Kick off meeting within February (Mark) * BS prism preparation (Mark) * 5mm prism [[attachment:JGW-D1604796.pdf|drawing]] * Confirmed with Hirata-san that BS can use same 5 mm prism as SR (grooves, wire clearance all OK). * Confirmed with Tatsumi-san that not a big deal to use smaller BS prism as long as secondary position not changed. * Submitted 5 mm prism drawing to company that did LIGO HSTS prism (except grooves), waiting on response. * Second company that did LIGO groove cutting not interested in quoting - exploring other US companies. * Should contact Shinko-sha again (Takahashi) * Can we make SR wire breakers bigger ? * Check what happens if we widen the slit by 3.75mm and make a new M5 (Hirata) -> [[https://www.dropbox.com/sh/f5lnexvb6k9bovo/AABEYf4_C19GXYEuJZZiy7cqa?dl=0|Result]] * Two concerns * The rework may bend the wing shaped parts. * The P.C.D. of the new screw holes may not coincide exactly with the other existing holes * Consult with Fukushima-san again. Takahashi will contact Fukushima-san * Do we need to widen the slits for PRC RMs ? -> Depends on how difficult it is to rework the RM. * Wider cuts will break the horizontal balance. Need to check how much compensation mass is reduced (Hirata) -> 2mm reduction will be necessary. We can do this. * Flag design (Mark) * Shorter flag is desirable ? * Mark will sort out the ideas and organize a specialized meeting.-> will present an updated version in the next meeting. * IP base clamp (Fabian): [[attachment:image.png|Picture]] -> Reduce the number of clamps-> Hirata-san finished 2D drawings. Trying to get quotation now. * Bread board spring (Takahashi): Hirata-san is getting quotations. * #BS Assembly Frame Design (Aso, Hirata) * #BS gluing jigs (Tatsumi) * #Not enough crane height problem (Hirata, Saito) * #BS clean bag (Aso) == Type A == * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4792|Task list]] (Takahashi) * #Type-A Filters Optimal Load Measurements * #Takahashi will make a plan for the optimal load check and ask ATC.-> Check two filters per month from April 2016. -> Will be presented to the ATC steering committee. * #How to manufacture the long maraging wires ? * One prototype was machined by Ojima * Aoshima can do the heat treatment for the long rod. Will ask them soon (Takahashi) -> Still waiting for a quotation. * How to test it ? * We can use the prototype assembly frame in TAMA. == Type-Bp modification == * PRM traverser * Postpone the production to the next FY until we know the details of the modification. * Tell Uraguchi-san about the above plan (Takahashi) -> done * #PR2 Wire breaker problem * Prism removal from PR2 (Hirose, Mark) * Not yet ready == Other == * Safety * No incident * #GAS blade inspection by Virgo (Takahashi) * Shipped the blades. Will get results in 1-2 months. == Next meeting == 2015/2/19 (Fri) 13:30 - @ Mitaka