Participants: | Participants:Hirata, Takahashi, Aso, Ishizaki, Tanaka, Okutomi, Sato, Shoda, Mark, Fabian, Akutsu, Fujii |
Line 19: | Line 19: |
* LVDT off load with fishing rod was done using the USB connection. * Tilt meter could not be installed because of the insufficient space. Will use the relative position of IM and IRM as a tilt sensor. |
|
Line 20: | Line 22: |
* Aso will send a stepper motor driver from Kamioka to Mitaka for test | |
Line 28: | Line 31: |
* Mark worked on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| JGW-D1503600 - BS Suspension Cabling]] - main thing we definitely don't have is stepper driver boxes (still being designed). | * Mark worked on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|JGW-D1503600 - BS Suspension Cabling]] - main thing we definitely don't have is stepper driver boxes (still being designed). * Ask Miyaka-san the status * Notify Miyakawa-san what and how many circuits are necessary by when (Mark) |
Line 32: | Line 37: |
* [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5108|Graceful shutdown mechanism]] * Check when is the next AEL meeting (Aso) |
|
Line 33: | Line 42: |
* #Electronics document tree for VIS by Mark ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4937| E1604937]]) * #Updated PR3 schematic with OpLev wiring ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4795| D1604795]]) |
* #Electronics document tree for VIS by Mark ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4937|E1604937]]) * #Updated PR3 schematic with OpLev wiring ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4795|D1604795]]) |
Line 47: | Line 56: |
* Policy of the screw types to be used (Mark, Fabian) [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5107| E1605107]] ([[https://onedrive.live.com/redir?resid=1447B05D5B571A84!346&authkey=!ABNrIarsklTd8Q0&ithint=file%2cdocx|draft]]) | * Policy of the screw types to be used (Mark, Fabian) [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5107|E1605107]] ([[https://onedrive.live.com/redir?resid=1447B05D5B571A84!346&authkey=!ABNrIarsklTd8Q0&ithint=file,docx|draft]]) |
Line 57: | Line 66: |
* Mark worked on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| JGW-D1503600 - BS Suspension Cabling]] | * Mark worked on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|JGW-D1503600 - BS Suspension Cabling]] |
Line 63: | Line 72: |
* Fabian finished analysis of wire thickness and wrote report: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5106| T1605106]] ([[https://onedrive.live.com/view.aspx?resid=1447B05D5B571A84!354&ithint=file%2cdocx&app=Word&authkey=!AO5CHNP3xlO5RjY|draft]]) * Fabian wrote up the policy on coating/venting of screws: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5107| E1605107 Fabian's screw policy]] ([[https://onedrive.live.com/redir?resid=1447B05D5B571A84!346&authkey=!ABNrIarsklTd8Q0&ithint=file%2cdocx|draft]]) |
* Fabian finished analysis of wire thickness and wrote report: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5106|T1605106]] ([[https://onedrive.live.com/view.aspx?resid=1447B05D5B571A84!354&ithint=file,docx&app=Word&authkey=!AO5CHNP3xlO5RjY|draft]]) * Fabian wrote up the policy on coating/venting of screws: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5107|E1605107 Fabian's screw policy]] ([[https://onedrive.live.com/redir?resid=1447B05D5B571A84!346&authkey=!ABNrIarsklTd8Q0&ithint=file,docx|draft]]) |
Line 66: | Line 75: |
* [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5106| Fabian's report T1605106]] ([[https://onedrive.live.com/view.aspx?resid=1447B05D5B571A84!354&ithint=file%2cdocx&app=Word&authkey=!AO5CHNP3xlO5RjY|draft]]) | * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5106|Fabian's report T1605106]] ([[https://onedrive.live.com/view.aspx?resid=1447B05D5B571A84!354&ithint=file,docx&app=Word&authkey=!AO5CHNP3xlO5RjY|draft]]) |
Line 71: | Line 80: |
* 6 prisms were ordered, to arrive just after Golden Week. Prisms will be polished and cut parallel to the c (rather than a) axis for strength. Size will be 5 mm for compatibility with SR. | * 6 prisms were ordered, to arrive just after Golden Week. Prisms will be polished and cut parallel to the c (rather than a) axis for strength. Size will be 5 mm for compatibility with SR. |
Line 103: | Line 112: |
* Mark, Hirata-san, Takahashi-san met with Mirapro 4/1 and presented [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5037| E1605037 BS Assembly Frame Requirements]] | * Mark, Hirata-san, Takahashi-san met with Mirapro 4/1 and presented [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5037|E1605037 BS Assembly Frame Requirements]] |
Line 105: | Line 114: |
* Clean bag * Needs to be ordered soon. Mark will make a design. Aso will contact the company. |
* Clean bag * Needs to be ordered soon. Mark will make a design. Aso will contact the company. |
Line 113: | Line 122: |
* Mark worked on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| JGW-D1503600 - BS Suspension Cabling]] adding rack cabling | * Mark worked on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|JGW-D1503600 - BS Suspension Cabling]] adding rack cabling |
Line 115: | Line 124: |
* Need to get status on design of stepper drive box (requested by Sekiguchi-san [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3385| T1503385]]) | * Need to get status on design of stepper drive box (requested by Sekiguchi-san [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3385|T1503385]]) |
VIS Meeting on 2016/4/8
2016/4/8 13:30 -
Room 210 & eZuce
Participants:Hirata, Takahashi, Aso, Ishizaki, Tanaka, Okutomi, Sato, Shoda, Mark, Fabian, Akutsu, Fujii
Schedule
- #Schedule status (Aso)
- #Will have a schedule meeting with Ando-san on April 15th in Kamioka (Takahashi, Mark, Shoda will come)
iKAGRA related activities
PR3
- PR3 Operation Status (Aso)
The fuse of the k1pr0 I/O chassis tripped again -> The power supply was replaced.
- BIO board was installed to k1pr0 taking this opportunity.
- Cabling was fixed
- PR3 commissioning (LVDT feedback off-load, tilt-meter (Shoda)
- LVDT off load with fishing rod was done using the USB connection.
- Tilt meter could not be installed because of the insufficient space. Will use the relative position of IM and IRM as a tilt sensor.
- Traverser and Stepper motor remote control (Shoda):
- Aso will send a stepper motor driver from Kamioka to Mitaka for test
iKAGRA ETM suspension
- Current status (Ohishi)
- Coil polarization
Double pass OpLev
Electronics
- What are necessary in the next few weeks ?
Mark worked on JGW-D1503600 - BS Suspension Cabling - main thing we definitely don't have is stepper driver boxes (still being designed).
- Ask Miyaka-san the status
- Notify Miyakawa-san what and how many circuits are necessary by when (Mark)
- Watch dog system (Tanaka)
- Check when is the next AEL meeting (Aso)
- #Electronics diagram and review
#Electronics document tree for VIS by Mark (E1604937)
- #Who will manage the electronics of each suspension
- Type-Bp will be controlled by Shoda but the diagram update will be done by Mark
- Type-A may be maintained by a new engineer. Sould be discussed with the person before April .
- #We need to count electronics and cables needed for the tests, such as temporary sensors and so on.
bKAGRA preparation
- Three big categories of the tasks
- Type-A: Leader = Takahashi, Okutomi, Ishizaki, a new engineer
- Type-B (BS and SRC): Leader = Mark, Fabian, Hirata
- Type-Bp modification: Leader = Shoda, Fujii, A new technician (?)
Common Issues
Policy of the screw types to be used (Mark, Fabian) E1605107 (draft)
- Reflection type local sensor (Akutsu)
- OSEM assembly (Akutsu)
- Schedule for each suspension is necessary
Each leader must tell Akutsu-kun when and how many OSEMs they need by the next meeting -> Done for Type-Bp and Type-B. No OSEM for Type-A.
Type-B
- Past Week Summary
Mark worked on JGW-D1503600 - BS Suspension Cabling
Mark wrote assembly frame requirements doc for Mirapro: E1605037
- Mark checked Hirata-san's assembly drawings and re-checked again after corrections; Hirata-san is now working on obtaining fasteners:
Takahashi-san checked Hirata-san's drawings for BS and IM flags (two designs each) and is ordering them: D1503487, D1605087, D1605088, ?? - not yet posted)
- Hirata-san got quote on BS clamp modifications - being ordered to arrive 4/22.
Fabian finished analysis of wire thickness and wrote report: T1605106 (draft)
Fabian wrote up the policy on coating/venting of screws: E1605107 Fabian's screw policy (draft)
- Wires
- Rahul pointed out that 200 µm wire was not enough for BS (chosen for PR, not rethought).
- Fabian checked and recommends 300 µm piano wire (available from Nilaco, 4.5 safety factor)
- See document for more on RM wires for BS and PR/SR
- BS prism preparation
- 6 prisms were ordered, to arrive just after Golden Week. Prisms will be polished and cut parallel to the c (rather than a) axis for strength. Size will be 5 mm for compatibility with SR.
- Can we make SR wire breakers bigger?
Fukushima-san preparing test: 3/4/2016 + 1 month = ≈4/1/2016 -> Hirata-san and Takahashi-san talking to ATC 4/8 morning.
- Flag design
Drawings done (but not posted): D1503487, D1605087, D1605088, ??)
- Takahashi-san ordering
- Widen the OSEM opening (Akutsu)
- A new local length sensing
- Need to decide the strategy for BS: three choices
- Use OSEMs as originally planned
Use OpLev, No OSEM flag
- Use reflection type sensors, No OSEM flag
- Decide later!
- Need to decide the strategy for BS: three choices
- BS dummy optic
- Ordered, expected ≈4/22
- BS dummy and secondary prisms
- Dummy prisms will be 5 mm to match SR - need to adjust BS clamp blocks.
- Mark trying to find out from Tatsumi-san what height of prism is assumed by current jig.
- EQ stop screws, extensions and lock nuts (in manufacture - promised for 4/22)
- BS Clamp Mods
- Hirata-san finalized details with IJECT. Order pending, promised for 4/22.
- Ballast masses for payload
Hirata-san created drawings DropBox link
- Drawings were checked by Mark, not yet ordered.
- Lower breadboard stuff
- Breadboard spring bases and associated cable clamps (in manufacture, expected 4/15)
- Breadboard springs (in manufacture)
- Damper ring mods (in manufacture, expected 4/28)
- Nail-head parts: quote from Mirapro received, not yet ordered
- BS Assembly Frame Design (Mark, Hirata)
Mark, Hirata-san, Takahashi-san met with Mirapro 4/1 and presented E1605037 BS Assembly Frame Requirements
- Quote received
- Clean bag
- Needs to be ordered soon. Mark will make a design. Aso will contact the company.
- No action since last week
- 2D and 3D CAD
- Individual mass assemblies for payload all done.
- BS 3D Assembly
- Needs updates for BF and SF blade spring configuration.
- Electronics
Mark worked on JGW-D1503600 - BS Suspension Cabling adding rack cabling
- Need to inform Miyakawa-san of requirements and schedule
Need to get status on design of stepper drive box (requested by Sekiguchi-san T1503385)
- Procedure documents
- No action since last week
- Mirror box (Tatsumi)
- Mirror box exists but Tatsumi-san has a list of modifications he'd like to make.
- Need to get clarity on secondary prism size - 5 mm or 1.28.
- Mirror box base will need holes to interface to hanging frame trolley. Tatsumi-san has agreed to do the mirror box trolley plate so that it will match the mirror box base plate. Hirata-san will design the rest of the hanging system and ask Mirapro to make it along with the assembly frame.
- Not enough crane height problem (Hirata, Saito)
Type A
Task list (Takahashi)
- Thinking about a possibility of testing the long filter chain using the prototype EQ stop in Kashiwa.
- The prototype EQ stop was transported from Kashiwa to Kamioka on 31th March.
- Pre-assembly of the EQ stop prototypr on 6-7 April. Near the SR chambers
Demonstration of installation procedure using prototype filters (SFx1 + BFx2) from May.-> No clean booth on the 2F now. Need to consider where to do the test.
- The kick-off meeting was held on 31th March.
The test of prototype long maraging rod was started. Detail is here: http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=1185
- Load dependence was measured using a laser position sensor. Extension of 2.84mm was observed for the load of 272.8kg. The extension is consistent with the calculation (2.75mm).
- Care on the humidity should be taken to store maraging steel to avoid cracking noise.
- Type-A Filters Optimal Load Measurements
- SFs will be transported to Mitaka on April 4th to start the measurement
- Simultion (Okutomi)
- Reported a draft simulation results in the Type-A kick-off meeting.
- Simulation with a dummy mass: Send a report to people before the VIS meeting in the next week.
Type-Bp modification
- Traverser motor driver (Shoda)
- Need a box for stepping motor driver. Miyakawa-san is thinking about ordering chassis and boxes for motors. We discussed and agreed that the design of the boxes will be unified. The boxes will be designed and ordered together with those. (16/03/10)
- Miyakawa-san wants to have a driver and a motor to test
- Will give them to MIyakawa-san when Shoda-san come to Kamioka for the shifts
-> Done (3/28)
- Shoda is also asking Uraguchi-san to provide one more Traverser motor driver for the test.
- Will give them to MIyakawa-san when Shoda-san come to Kamioka for the shifts
- #PR2 Wire breaker problem
- Prism removal from PR2 (Hirose, Mark)
- Spare mirror is now back to Kashiwa
- Prism removal from PR2 (Hirose, Mark)
- #CLIO suspension
- Ishizaki-san will come to pick it up
- Modification for bKAGRA
- Uraguchi-san proposed us the new IP plan
- Shoda updated the proposal(concerns?) for the BF active damping plan
Will have a brainstorming after the JSPS meeting -> Done (3/23)
- We also discussed with Uraguchi-san, and tell him our concerns raised in our brainstorming discussion. (3/25)
- Action items for Type-Bp modification
Calculate the upper limit of the resonant fequency for IP (Fujii): MeetingMemo
Check if we need the magnetic damper for the bottom filter (Fujii): MeetingMemo
- Either the MD is used or the resonant frequency of the IP should be matched with the whole chain resonance.
Check the mass of the bottom plate and the cap of the standard filter -> Send Uraguchi-san (Shoda)
-> Done (3/31)
- Check structure analysis of the EQ stop for active damping on BF (Shoda)
- Check the minimam weight we need for the BFRM in order to damp the resonance enough (Shoda)
- Check the capability to modify the BF cap (Shoda)
We want the correct CAD model for the original Type-Bp
- The BF and SF designs are the same for Bp and B except for the blades. So the effort to make correct CAD models for those filters can be unified between the two teams. Hirata-san with help from Shoda-san will work to make correct CAD models.
- Will have a meeting with Virgo people sometime soon. Then have a review for Type-Bp
Site work plan for the next week
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
Travel Plans
- Travel (Week of 4/11)
Takahashi:15
Shoda:15
Mark:15
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
- Travel (Week of 4/18)
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
Other
- Safety
- Safety campaign is on going in the tunnel to fix dangerous cablings
- #GAS blade inspection by Virgo (Takahashi)
- Shipped the blades. Will get results in 1-2 months.
Next meeting
2016/4/15 (Fri) 13:30 -