Differences between revisions 9 and 10
Revision 9 as of 2016-04-08 10:54:06
Size: 12960
Editor: MarkBarton
Comment:
Revision 10 as of 2016-04-08 11:15:11
Size: 13113
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 47: Line 47:
 * Policy of the screw types to be used (Mark, Fabian) -> Will upload the document by Tuesday next week.-> s  * Policy of the screw types to be used (Mark, Fabian) [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5107| E1605107]] ([[https://onedrive.live.com/redir?resid=1447B05D5B571A84!346&authkey=!ABNrIarsklTd8Q0&ithint=file%2cdocx|draft]])

VIS Meeting on 2016/4/8

2016/4/8 13:30 -

Room 210 & eZuce

Participants:

Schedule

  • #Schedule status (Aso)
  • #Will have a schedule meeting with Ando-san on April 15th in Kamioka (Takahashi, Mark, Shoda will come)

PR3

  • PR3 Operation Status (Aso)
    • The fuse of the k1pr0 I/O chassis tripped again -> The power supply was replaced.

      • BIO board was installed to k1pr0 taking this opportunity.
      • Cabling was fixed
    • PR3 commissioning (LVDT feedback off-load, tilt-meter (Shoda)
  • Traverser and Stepper motor remote control (Shoda):

iKAGRA ETM suspension

  • Current status (Ohishi)
    • Coil polarization
    • Double pass OpLev

Electronics

  • What are necessary in the next few weeks ?
  • Watch dog system (Tanaka)
  • #Electronics diagram and review
    • #Electronics document tree for VIS by Mark (E1604937)

    • #Updated PR3 schematic with OpLev wiring (D1604795)

    • #Who will manage the electronics of each suspension
      • Type-Bp will be controlled by Shoda but the diagram update will be done by Mark
      • Type-A may be maintained by a new engineer. Sould be discussed with the person before April .
    • #We need to count electronics and cables needed for the tests, such as temporary sensors and so on.

bKAGRA preparation

  • Three big categories of the tasks
    • Type-A: Leader = Takahashi, Okutomi, Ishizaki, a new engineer
    • Type-B (BS and SRC): Leader = Mark, Fabian, Hirata
    • Type-Bp modification: Leader = Shoda, Fujii, A new technician (?)

Common Issues

  • Policy of the screw types to be used (Mark, Fabian) E1605107 (draft)

  • Reflection type local sensor (Akutsu)
  • OSEM assembly (Akutsu)
    • Schedule for each suspension is necessary
    • Each leader must tell Akutsu-kun when and how many OSEMs they need by the next meeting -> Done for Type-Bp and Type-B. No OSEM for Type-A.

Type-B

  • KAGRA/Subgroups/VIS/TypeB

  • Task list/schedule

  • Past Week Summary
  • Wires
  • Fabian's report T1605106 (draft)

    • Rahul pointed out that 200 µm wire was not enough for BS (chosen for PR, not rethought).
    • Fabian checked and recommends 300 µm piano wire (available from Nilaco, 3.4 safety factor)
  • BS prism preparation
    • 6 prisms were ordered, to arrive just after Golden Week. Prisms will be polished and cut parallel to the c (rather than a) axis for strength. Size will be 5 mm for compatibility with SR.
  • Can we make SR wire breakers bigger ?
    • Fukushima-san preparing test: 3/4/2016 + 1 month = ≈4/1/2016 -> No update as of 4/1 morning - will ask.

  • Flag design
    • BS Flag Redesign on OneDrive

    • Drawings done (but not posted): D1503487, D1605087, D1605088, ??)

    • Takahashi-san ordering
    • Widen the OSEM opening (Akutsu)
    • A new local length sensing
      • Need to decide the strategy for BS: three choices
        • Use OSEMs as originally planned
        • Use OpLev, No OSEM flag

        • Use reflection type sensors, No OSEM flag
      • Decide later!
  • BS dummy optic
  • BS dummy and secondary prisms
    • Dummy prisms will be 5 mm to match SR - need to adjust BS clamp blocks.
    • Mark trying to find out from Tatsumi-san what height of prism is assumed by current jig.
  • EQ stop screws, extensions and lock nuts (in manufacture - promised for 4/22)
  • BS Clamp Mods
    • Hirata-san finalized details with IJECT. Order pending, promised for 4/22.
  • Ballast masses for payload
    • Hirata-san created drawings DropBox link

    • Drawings were checked by Mark, not yet ordered.
  • Lower breadboard stuff
    • Breadboard spring bases and associated cable clamps (in manufacture, expected 4/15)
    • Breadboard springs (in manufacture)
    • Damper ring mods (in manufacture, expected 4/28)
    • Nail-head parts: quote from Mirapro received, not yet ordered
  • BS Assembly Frame Design (Mark, Hirata)
  • Clean bag
    • Needs to be ordered soon. Mark will make a design. Aso will contact the company.
    • No action since last week
  • 2D and 3D CAD
    • Individual mass assemblies for payload all done.
    • BS 3D Assembly
      • Needs updates for BF and SF blade spring configuration.
  • Electronics
  • Procedure documents
    • No action since last week
  • Mirror box (Tatsumi)
    • Mirror box exists but Tatsumi-san has a list of modifications he'd like to make.
    • Need to get clarity on secondary prism size - 5 mm or 1.28.
    • Mirror box base will need holes to interface to hanging frame trolley. Tatsumi-san has agreed to do the mirror box trolley plate so that it will match the mirror box base plate. Hirata-san will design the rest of the hanging system and ask Mirapro to make it along with the assembly frame.
  • Not enough crane height problem (Hirata, Saito)

Type A

  • Task list (Takahashi)

  • Thinking about a possibility of testing the long filter chain using the prototype EQ stop in Kashiwa.
    • The prototype EQ stop was transported from Kashiwa to Kamioka on 31th March.
    • Pre-assembly of the EQ stop prototypr on 6-7 April. Near the SR chambers
    • Demonstration of installation procedure using prototype filters (SFx1 + BFx2) from May.-> No clean booth on the 2F now. Need to consider where to do the test.

  • The kick-off meeting was held on 31th March.
  • The test of prototype long maraging rod was started. Detail is here: http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=1185

    • Load dependence was measured using a laser position sensor. Extension of 2.84mm was observed for the load of 272.8kg. The extension is consistent with the calculation (2.75mm).
  • Care on the humidity should be taken to store maraging steel to avoid cracking noise.
  • Type-A Filters Optimal Load Measurements
    • SFs will be transported to Mitaka on April 4th to start the measurement
  • Simultion (Okutomi)
    • Reported a draft simulation results in the Type-A kick-off meeting.
    • Simulation with a dummy mass: Send a report to people before the VIS meeting in the next week.

Type-Bp modification

  • Traverser motor driver (Shoda)
    • Need a box for stepping motor driver. Miyakawa-san is thinking about ordering chassis and boxes for motors. We discussed and agreed that the design of the boxes will be unified. The boxes will be designed and ordered together with those. (16/03/10)
    • Miyakawa-san wants to have a driver and a motor to test
      • Will give them to MIyakawa-san when Shoda-san come to Kamioka for the shifts
        • -> Done (3/28)

        • Shoda is also asking Uraguchi-san to provide one more Traverser motor driver for the test.
  • #PR2 Wire breaker problem
    • Prism removal from PR2 (Hirose, Mark)
      • Spare mirror is now back to Kashiwa
  • #CLIO suspension
    • Ishizaki-san will come to pick it up
  • Modification for bKAGRA
    • wiki

      • Uraguchi-san proposed us the new IP plan
      • Shoda updated the proposal(concerns?) for the BF active damping plan
    • Will have a brainstorming after the JSPS meeting -> Done (3/23)

      • We also discussed with Uraguchi-san, and tell him our concerns raised in our brainstorming discussion. (3/25)
    • Action items for Type-Bp modification
      • Calculate the upper limit of the resonant fequency for IP (Fujii): MeetingMemo

      • Check if we need the magnetic damper for the bottom filter (Fujii): MeetingMemo

        • Either the MD is used or the resonant frequency of the IP should be matched with the whole chain resonance.
      • Check the mass of the bottom plate and the cap of the standard filter -> Send Uraguchi-san (Shoda)

        • -> Done (3/31)

      • Check structure analysis of the EQ stop for active damping on BF (Shoda)
      • Check the minimam weight we need for the BFRM in order to damp the resonance enough (Shoda)
      • Check the capability to modify the BF cap (Shoda)
        • We want the correct CAD model for the original Type-Bp

        • The BF and SF designs are the same for Bp and B except for the blades. So the effort to make correct CAD models for those filters can be unified between the two teams. Hirata-san with help from Shoda-san will work to make correct CAD models.
    • Will have a meeting with Virgo people sometime soon. Then have a review for Type-Bp

Site work plan for the next week

  • Mon:
  • Tue:
  • Wed:
  • Thu:
  • Fri:

Travel Plans

  • Travel (Week of 4/11)
    • Takahashi:15

    • Shoda:15

    • Mark:15

    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:
  • Travel (Week of 4/18)
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:

Other

  • Safety
    • Safety campaign is on going in the tunnel to fix dangerous cablings
  • #GAS blade inspection by Virgo (Takahashi)
    • Shipped the blades. Will get results in 1-2 months.

Next meeting

2016/4/15 (Fri) 13:30 -

KAGRA/Subgroups/VIS/VISMinutes20160408 (last edited 2016-04-10 05:06:56 by YoichiAso)