Line 76: Line 76:
   * Make a list with ranges of numbers for uncertain things by the next VIS meeting. Then talk to AEL.
  * '''SRx will probably not have geophones, so Mark will need to do a revision too.'''
   * Make a list with ranges of numbers for uncertain things by the next VIS meeting (Takahashi). Then talk to AEL.
Line 80: Line 79:
  . [[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0051/E1605194/001/Project%20WDS%20Experiment%20%202016_05_13.pdf|Document(pdf)]]

VIS Meeting on 2016/5/20

2016/5/20 13:30 -

Room 210

Participants:

Overall Schedule

  • The current overall schedule chart.

iKAGRA related activities

PR3

  • PR3 post-run work status (Shoda)
    • Planned works
      • 5/16: measurement of PR3 mirror position relative to the vacuum tank
      • 5/17: OpLev wind shield test?, Inner frame status check.

      • 5/18: Extended chief meeting
      • 5/19, 20: Evacuation

IP tests in Kamioka

  • Status report (Fujii)
  • Control test may be performed with the hanging test of BS
    • Ask Joris what is his intention and schedule (Raffaele)
    • Ask if we can perform the control test remotely (Aso)

bKAGRA preparation

Important Issues

  • Suspended bread board
    • #Many critical components will be installed on it (baffles, steering mirrors for the green injection etc)
    • We have to make sure that the bread board suspension is properly damped
      • Takahashi checked Sekiguchi thesis
      • Looks like we can estimate the damping force from his experimental results. Takahashi will calculate the necessary number of magnets.-> by the next VIS meeting

  • Accelerometers for IP
    • Geophone is too noisy for innertial damping in Kamioka
    • TAMA SAS accelerometers for Type-A
    • NIKHEF accelerometers for BS ?
    • Which accelerometers for SR ?
      • Buy from NIKHEF ? How much is the cost ?
      • Get the design from NIKHEF and produce them in Japan (ATC) ?
  • Pre-isolator assembly and tests
    • What is the plan for SR Type-B
    • Takahashi and Mark will start the discussion on, where, who, when.
  • Bottom filter local sensor for Type-A
    • Tell SEO about the wider cross tube -> Wider tube is not possible

    • Fix EQ stop at the bottom ? -> This is possible

    • #EQ stop design should take into account of the sensor/actuator mounts.
    • #Use the same sensor/actuator as Type-Bp ?
    • #Sato-san is responsible for this part.
  • #Dummy payload design for Type-A
    • Okutomi-kun is assigned.

Common Issues

  • Wide OSEM production (Akutsu)
    • For BS test hanging, we need the wider version by mid-to-late June.
    • Got cost estimates for the small parts. Will order for 20 OSEMs.

  • Length sensing OpLev

    • #In order to test this with the BS test haning, we want to have wide OSEMs as witness sensors on the mirror.
    • #Stab-flag and tipped flag are both in quotation. We will order both. The gluing jigs will be the same.
    • #Who will design and prepare the BS length sensing OpLev ? -> Ask Simon (Aso) -> in progress

  • #What shall we do with PR2
    • PR2 chamber has only one viewport avaibale at 45deg. angle for OpLev

    • Original idea: Put a reflecting mirror on the bread board and monitor the rotation of the bread board with another OpLev.

      • No length sensing
      • Two OpLevs needed

    • Another idea: Introduce the light with a fiber into the vacuum chamber to form a one-way 45deg. OpLev for length sensing.

      • Length sensing possible
      • Affected by the vacuum chamber tilt (if we mount the fiber collimator to the inner frame, the tilt will be less).
      • Need to find a place to mount the fiber collimator inside the vacuum chamber
        • See if we can find any mounting point on the inner frame (Akutsu) by the next next VIS meeting.

Electronics

  • What are necessary in the next few weeks ?
    • We need to count the number of necessary circuits for Type-A and Type-Bp, so that we can tell AEL the total number necessary for VIS.
    • Make a list by the end of May (Shoda, Takahashi)List

      • There are some uncertainties in the number of necessary circuits.
      • Make a list with ranges of numbers for uncertain things by the next VIS meeting (Takahashi). Then talk to AEL.
  • Watch dog system (Tanaka)
    • photo-MOS relay switch resistance fluctuation
      • Noise requirement for the resistance fluctuation is necessary (Aso)

      • Tanaka measured the photo-MOS relay resistance fluctuation-> 37mOhm RMS upper limit

        • Will make spectrum of the resistance fluctuation.
    • DC-DC convertor noise check: quiter than a battery ?

    • #The next step: Make a prototype with slow shutdown mechanism

Type-B

  • KAGRA/Subgroups/VIS/TypeB

  • Task list/schedule

  • Past Week Summary
    • Flags and metal prisms ordered; expected 5/31.
    • New assembly drawing D1605179 focussing on items not part of main chain (and associated screws):

      • Crane adapter
      • Lower breadboard blade module (with cable clamps)
      • IM-RM safety bar (D1605127 from last week now obsolete)

    • 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram)
    • Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist: Crane Frame.pdf)

    • Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: BS Cleanbooth.pdf)

    • Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro.
    • Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later).
    • Lots of work by Fabian on E1604817 BS Payload Assembly Procedure ( Draft on OneDrive; (IM and RM assembly sections now finished)

    • Lots of work by Mark on E1504235 BS Assembly Procedure (Draft on OneDrive)

    • Hirata-san measured another SF.
  • Discussions

    • Need more realistic schedule
    • Take into account the preparation of SR suspensions
    • SRM and PRM payloads need to be ordered.
  • IM assembly
    • Planning to do it in ATC. Use the clean room used for the SF assembly.
    • Fabian will start the preparation from the next week.
  • Wires
  • Can we make SR wire breakers bigger?
    • Fukushima-san preparing test: 3/4/2016 + "1 month" = ≈4/1/2016, not ready as of 4/8.-> Takahashi will ask the status.

  • Flags, Prisms
  • BS dummy optic
    • Ordered, expected ≈4/22 (T1604811)

    • Decided to have it shipped to Mitaka for initial assembly and give it to Tatsumi-san for prisms/flags.
  • Mirror box (Tatsumi)
    • Tatsumi-san has ordered modifications to mirror box for final flags and prisms.
  • An extra structure attached to the EQ stop to prevent tipping over of the BS.
    • Will consider if we can make it to the test hanging. But not critical for the test hanging.
    • No action since last week.
  • Not enough crane height problem (Hirata, Saito)
    • No action since last week
  • EQ stop screws, extensions and lock nuts (in manufacture - promised for 4/22)
  • Ballast masses for payload
    • Hirata-san created drawings DropBox link

    • Drawings were checked by Mark, not yet ordered.
  • Lower breadboard stuff
    • Breadboard spring bases and associated cable clamps (in manufacture, expected 4/15)
    • Breadboard springs (in manufacture)
    • Damper ring mods (in manufacture, expected 4/28)
    • Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  • BS Assembly Frame Design (Mark, Hirata)
    • Hirata-san did new Inventor assembly with Mirapro's initial design plus various improvements including clean bag supports.
  • Clean bag
    • Ordered - expected 6/8.
  • 2D and 3D CAD
  • Electronics
    • JGW-D1503600 - BS Suspension Cabling

    • E1605111 BS Suspension Electronic Items List

    • D1503901 In-Vacuum Cable Detail

    • Item list and timetable was given to Miyakawa-san - some corrections received and added to schematic but not yet posted.
    • Status on AEL boxes OK according to Miyakawa-san.
    • Need to order LVDT oscillator cards from NIKHEF (Takahashi) and have a signal generator and cable in the meantime (Mark).
    • Need to get new longer versions of some previously ordered BF-PI and SF-PI cables (Takahashi).
    • Need to check previously ordered TM-BF and IM-BF OSEM cables have been flipped (Takahashi).
    • Decided to hand-make cables for geophones because previously ordered cables have no conductor on pin 5.
    • Stepper drive box (requested by Sekiguchi-san T1503385) is being designed, should be ready in time.

  • Procedure documents

Type A

  • Task list (Takahashi)

  • Where to perform the TF+IP assembly ?
    • The large access door to the ATC clean room is not available until Octorber or November. Doing the assembly work in Mitaka is next to impossible.
  • Prototype testof the EQ stop

    • Purpose of the test needs to be clarified to decide on where to perform the test.
  • The test of prototype long maraging rod was finished
    • Will order them with maraging rods for the cryogenic payload early July. The lead time is 2 months.
  • Type-B Standard Filters preparation
  • Type-A SF preparation
    • Needs to cut more finshing rod blades.
  • The next Type-A meeting will be on 5/26.
  • #Simultion (Okutomi)
  • #Local sensors for BF

Type-Bp modification

  • Modification for bKAGRA
    • wiki
    • Discussing with ATC people for the mechanical modification.
      • Got some comments
    • Estimating the noise requirements for the BF sensor/actuator
    • Full CAD model of the original Type-Bp needs to be created

Site work plan for the next week

  • Mon:PR3 measurements, IP

  • Tue: PR3 measurements, IP
  • Wed: Extended Chief Meeting
  • Thu: PR3 measurements, IP
  • Fri: PR3 vacuum evacuation, IP

Travel Plans

  • Travel (Week of 5/16)
    • Takahashi: 17-20 (chief meeting and IP)
    • Shoda:16-20 (PR3)

    • Mark:
    • Fabian:
    • Okutomi:15-18 (PR3)

    • Fujii:17-20 (IP)

    • Ishizaki:
    • Hirata:
    • Ohishi:
  • Travel (Week of 5/23):
    • Takahashi:
    • Shoda: Elba
    • Mark:
    • Fabian:
    • Okutomi: Elba
    • Fujii:23-27 (Accelerometer, PR3)

    • Ishizaki:
    • Hirata:
    • Ohishi:

Mark is away: July 8-20

Other

  • Safety:no incident

  • #GAS blade inspection by Virgo (Takahashi)
    • Shipped the blades. Will get results in 1-2 months.

Next meeting

2016/5/20(Fri) 13:30 -