Line 40: Line 40:
 * Bottom Filter LVDT
  * Virgo people wants to produce ones for us.

VIS Meeting on 2016/5/27

2016/5/27 13:30 -

Room 210

Participants:

Overall Schedule

  • The current overall schedule chart.

iKAGRA related activities

PR3

  • PR3 post-run work status (Fujii)

bKAGRA preparation

Important Issues

  • Suspended bread board
    • #Many critical components will be installed on it (baffles, steering mirrors for the green injection etc)
    • We have to make sure that the bread board suspension is properly damped
      • Takahashi checked Sekiguchi thesis
      • Damping effect depends on the ratio of mass and resonant frequency. Estimated effect was 0.45 for the experiments. The number of magnets needed in the same condition is about half.
      • 30 magnets necessary for the gap of 5mm -> need to update the calculation for the double pendulum case (Takahashi)

  • Accelerometers for IP

    • Is Geophone too noisy for innertial damping in Kamioka ? (Shoda)
    • NIKHEF accelerometers for BS
      • Test status (Fujii)
    • #Which accelerometers for SR ?
      • Buy from NIKHEF ? How much is the cost ?
      • Get the design from NIKHEF and produce them in Japan (ATC) ?
  • Pre-isolator assembly and tests

    • What is the plan for SR Type-B
    • Takahashi and Mark will start the discussion on, where, who, when -> continue.

  • Bottom filter local sensor/actuator for Type-A
    • Any progress ?
      • What is the space available for the sensors/actuators ?
    • Fix EQ stop at the bottom: modify the design of the bottom part of the EQ stop to be tightly fit into the tube.
  • Dummy payload design for Type-A
    • Okutomi-kun is assigned.
    • Okutomi will make schematic design. One of the engineers will make drawings. Report more detailed plan by the next week (Takahashi).

  • Bottom Filter LVDT
    • Virgo people wants to produce ones for us.

Common Issues

  • Wide OSEM production (Akutsu)
    • For BS test hanging, we need the wider version by mid-to-late June.
    • Got cost estimates for the small parts. Will order for 20 OSEMs.
  • Length sensing OpLev

    • Optical design will be discussed in Optics Meeting.
  • What shall we do with PR2
    • Fixing an OpLev component on the inner frame seems possible (Akutsu)

Electronics

  • What are necessary in the next few weeks ?

    • Make a list of VIS electronics by the end of May (Shoda, Takahashi) -> List

      • Presented the list to AEL. Miyakawa-san agreed.
      • Need to update the list to include IMMT
      • Discuss how many spares to make at the next AEL meeting
  • Watch dog system (Tanaka)
    • Wants to do tests with the existing PR3 sometime in fall ? Need coordination.
    • photo-MOS relay switch resistance fluctuation
      • Noise requirement for the resistance fluctuation is necessary (Aso)
        • If we require the resistance noise to be smaller than DAC noise, the allowed fluctuation is 10^-7 Ohm/sqrt(Hz)@10Hz.
        • Asking Michimua-kun to calculate the requirements from the suspension response.
      • Tanaka measured the photo-MOS relay resistance fluctuation-> 37mOhm RMS upper limit

        • Will make spectrum of the resistance fluctuation.
    • #The next step: Make a prototype with slow shutdown mechanism

Type-B

  • KAGRA/Subgroups/VIS/TypeB

  • Task list/schedule

  • Past Week Summary
    • Fabian did inventory of parts/fasteners for dummy BS, RM, IM and IRM - almost all at Mitaka. A handful (picos, pico drivers) will be brought back from Kamioka.
    • Fabian continued work on Mathematica and Matlab models of the BS and control system. He now gets much better agreement after correcting discrepancies between the parameter sets.
    • Hirata-san worked on:
      • Checking Mirapro assembly frame drawings
      • Ordering missing screws and small items (screws for dummy mass, fine pitch M8 for RM)
      • Work platforms and clean booth second floor arrangement.
      • Load gauge adapter and associated parts

      • Possible fall-back plans for the rods connecting the security structure to the PI.
      • Design for additional IM trim masses (existing design had one mass per corner and no provision for adding/removing).
    • Mark worked more on E1504235 BS Assembly Procedure (Draft on OneDrive)

    • Mark designed a guide part to help place the PI accurately onto the security structure.

  • Discussions

  • IM assembly
    • Planning to do it in ATC. Use the clean room used for the SF assembly.
    • Fabian made an inventory. Most parts are ready.
  • Wires
  • Can we make SR wire breakers bigger?
    • Fukushima-san preparing test: 3/4/2016 + "1 month" = ≈4/1/2016, not ready as of 4/8.-> Takahashi will ask the status.

  • Flags, Metal Prisms
    • IM and BS flags and metal prisms ordered; expected 5/31
  • Sapphire Prisms - expected 6/5
  • Mirror box (Tatsumi)
    • Tatsumi-san has ordered modifications to mirror box for final flags and prisms.
  • An extra structure attached to the EQ stop to prevent tipping over of the BS.
    • Will consider if we can make it to the test hanging. But not critical for the test hanging.
    • No action since last week.
  • Not enough crane height problem (Hirata, Saito)
    • No action since last week
  • EQ stop screws, extensions and lock nuts (in manufacture - promised for 4/22)
  • Ballast masses for payload
    • Initial batch received - need to design and order smaller ones to allow for adjustments
  • Lower breadboard stuff
    • Assembly procedure ?

    • Breadboard spring bases and associated cable clamps RECEIVED
    • Breadboard springs (in manufacture)
    • Damper ring mods RECEIVED
    • Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  • BS Assembly Frame Design (Mark, Hirata)
    • Hirata-san did new Inventor assembly with Mirapro's initial design plus various improvements including clean bag supports.
  • Clean bag
    • Ordered - expected 6/8.
  • 2D and 3D CAD
  • Electronics
    • JGW-D1503600 - BS Suspension Cabling

    • E1605111 BS Suspension Electronic Items List

    • D1503901 In-Vacuum Cable Detail

    • Item list and timetable was given to Miyakawa-san - some corrections received and added to schematic but not yet posted.
    • Status on AEL boxes OK according to Miyakawa-san.
    • Signal generator and cable to be used for BS test. May order NIKHEF cards later if concern about AC-driven units in racks.
    • Need to get new longer versions of some previously ordered BF-PI and SF-PI cables (Takahashi).
    • Need to check previously ordered TM-BF and IM-BF OSEM cables have been flipped (Takahashi).
    • Decided to hand-make cables for geophones because previously ordered cables have no conductor on pin 5.
    • Stepper drive box (requested by Sekiguchi-san T1503385) is being designed, should be ready in time.

  • Procedure documents

Type A

  • Task list (Takahashi)

  • Clean booth design for 2F https://www.dropbox.com/s/8bi9ij91radmpt5/IXYV160512.pdf?dl=0

    • Ask Miyoki-san to add cable racks
  • Prototype test of the EQ stop
    • Will do the test in ATC
    • EQ stop and assembly frame prototype were shipped to Mitaka
    • Will start the preparation from the next
  • Sensors to monitor the release of the SFs from the EQ stop.
    • Now considering to use some touch sensors
    • Will test this sensor in the prototype test
  • #The test of prototype long maraging rod was finished
    • Will order them with maraging rods for the cryogenic payload early July. The lead time is 2 months.
  • Type-B Standard Filters preparation
    • 6th SF measurements were done ?
    • Shipped the SF for BS to Mitaka.
    • Ship the measured SFs to Kamioka at an apropriate time
  • Type-A SF preparation
    • Needs to cut more finshing rod blades -> ATC is working on it now.

  • The next Type-A meeting will be on 5/26.
  • Simultion (Okutomi)
  • #Local sensors for BF

Type-Bp modification

  • Modification for bKAGRA
    • wiki
    • Discussing with Saito-san of ATC
      • Specified what can be modified
      • Asked to fix the EQ stop to the traverser
    • Asked Fujii-kun to work on the noise requirements for the BF sensor/actuator
    • Still waiting for the LVDT design from Virgo
    • Full CAD model of the original Type-Bp needs to be created

Site work plan for the next week

  • Mon:
  • Tue:
  • Wed:
  • Thu:
  • Fri:

Travel Plans

  • Travel (Week of 5/30)
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:
    • Sato:
  • Travel (Week of 6/6):
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:

Mark is away: July 8-20

Other

  • Safety:no incident

  • #GAS blade inspection by Virgo (Takahashi)
    • Shipped the blades. Will get results in 1-2 months.

Next meeting

2016/6/3(Fri) 13:30 -

Next VIS F2F 6/10 ?

KAGRA/Subgroups/VIS/VISMinutes20160527 (last edited 2016-05-28 15:09:32 by MarkBarton)