2016/6/10 13:30 - 15:00 @ Room 210 Participants: 2016/6/10 13:30 - 15:00 @ Room 210

Participants:Takahashi, Ishizaki, Sato, Tanaka, Fabian, Mark, Fujii, Hirata, Shoda, Akutsu
Line 8: Line 10:
 * Put a report here  * Simulation: '''Ask Okutomi the status (Takahashi) '''
 * Structural analysis of the frame lock was done.
 * EQ stop test
  * '''Confirm what needs to be done with Ishizaki-san<<BR>>'''
  * '''Hurry up the production of the frame lock (Takahashi) '''
 * Accelerometers check
  * Dismounted them from 3 of the TAMA SAS
  * Will work on the remaining 1 soon.
 * Standard filer
  * Measuring the optimal loads
 * Bottom Filter
  * Calculated the size of the blades
  * Finish the cutting by the end of July
 * Release sensor
  * Waiting for the samples to test
Line 13: Line 29:
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]    * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815|klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
Line 15: Line 31:
  * Hirata-san measured another filter.   * Hirata-san moved in another filter for testing (but didn't get to measure it).
Line 18: Line 34:
  * Hirata-san worked on work platforms for the installation.
  * Hirata-san looked for
a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
  * Hirata-san researched and ordered a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
Line 21: Line 36:
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.    * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
Line 23: Line 38:
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week.   * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. Some issues with constructing pico adapters cables.
Line 34: Line 49:
   * Crane scale - quote received
   * Work platforms - quote received
   * Crane scale - ORDERED.
   * Work platforms - RECEIVED.
   * PI G
uide parts - in manufacture at ATC.
Line 44: Line 60:
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]    * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * Site work plan
  * '''Start the preparation work from the week of 6/20 '''
Line 49: Line 67:
 * Rough LVDT model -> DONE: under discussion with Saito-san@ATC  * Rough LVDT model -> DONE: under discussion
Line 53: Line 71:
 * Put a report here  * Nothing
Line 56: Line 74:
 * Put a report here  * Report of the experimental results and analysis(Resistance stability of PhotoMos Relay).[[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0052/E1605270/002/Project%20WDS%20Experiment%202016_06_10.pdf|http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0052/E1605270/002/Project%20WDS%20Experiment%202016_06_10.pdf]]
Line 61: Line 79:
  * NIKHEF accelerometer measurement results (Fujii)
  * Geophone noise (Takahashi)
  * NIKHEF accelerometer measurement results (Fujii) [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5271|Slides]]
   * The LVDT driver had wrong power supply voltages -> need to perform the measurements again
   * Type-B team will continue the noise measurements as well as the geophones
   * Fujii and Shoda will go to Kamioka on 27-29 June to transfer the information to the Type-B team
Line 64: Line 84:
  * Any news from Virgo ? (Raffaele)   * If we get the design from Virgo within this month, we will use the design
  * If not, we should make a design from scratch
Line 66: Line 87:
  * Shoda is working on the new fixture design for PR: by mid-July
  * '''Need to check if there is a similar problem in SR (Mark)'''
Line 90: Line 113:
  * Takahashi:   * Takahashi:19-21 (Acceptance of SFs, check items, move things around and so on)
Line 92: Line 115:
  * Mark:
  * Fabian:
  * Mark:20-24 (preparation for BS installation)
  * Fabian:20-24 (preparation for BS installation)
Line 97: Line 120:
  * Hirata:   * Hirata:20-24(not yet decided)
Line 99: Line 122:

June 27-29: Fujii, Shoda

July 4 - 8: Takahashi, Ishizaki, Sato (site check for the installation of Type-A)

Minutes of the VIS Meeting on 2016/6/10

2016/6/10 13:30 - 15:00 @ Room 210

Participants:Takahashi, Ishizaki, Sato, Tanaka, Fabian, Mark, Fujii, Hirata, Shoda, Akutsu

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

  • Simulation: Ask Okutomi the status (Takahashi)

  • Structural analysis of the frame lock was done.
  • EQ stop test
    • Confirm what needs to be done with Ishizaki-san

    • Hurry up the production of the frame lock (Takahashi)

  • Accelerometers check
    • Dismounted them from 3 of the TAMA SAS
    • Will work on the remaining 1 soon.
  • Standard filer
    • Measuring the optimal loads
  • Bottom Filter
    • Calculated the size of the blades
    • Finish the cutting by the end of July
  • Release sensor
    • Waiting for the samples to test

Type-B (Mark)

  • Type B Past Week Summary
    • Fabian finished dummy BS assembly.
    • Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. klog Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. klog

    • Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. klog We will check status on Mon 6/13.

    • Hirata-san moved in another filter for testing (but didn't get to measure it).
    • Hirata-san washed a batch of parts.
    • Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement.
    • Hirata-san researched and ordered a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
    • Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
    • We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
    • Mark worked on list of items for purchase in FY2016 and on the schedule.
    • Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. Some issues with constructing pico adapters cables.
  • Type B ongoing issues
    • Wires
      • Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
    • OSEMs
    • Feedthrough Adapters
      • Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
    • Can we make SR wire breakers bigger?
      • Fukushima-san will start on machining test soon (as of 5/27).
    • Not enough crane height problem (Hirata, Saito) - no action since last week
    • Installation stuff
      • Crane scale - ORDERED.
      • Work platforms - RECEIVED.
      • PI Guide parts - in manufacture at ATC.
    • Ballast masses for payload
      • Initial batch received - ordered extra smaller ones to allow for adjustments.
    • Lower breadboard stuff
      • Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
      • Breadboard springs (in manufacture, expected end of July)
      • Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
    • Clean bag - expected 6/8.
    • Documents
  • Site work plan
    • Start the preparation work from the week of 6/20

Type-Bp (Shoda)

  • 3D CAD model (Original & Latest modified version) -> DONE: Uploaded to ROOM214 (Shoda)

  • 1st draft of the installation procedure for modified parts -> Ongoing (Fujii+Shoda)

  • Rough LVDT model -> DONE: under discussion

  • We found that the suspension points of the optical bench are required to be shifted -> Shoda will design new adapters. (Deadline: Mid July)

IMMT (Ohishi)

  • Nothing

Watchdog system (Tanaka)

Safety

Issues

  • Accelerometers for IP
    • NIKHEF accelerometer measurement results (Fujii) Slides

      • The LVDT driver had wrong power supply voltages -> need to perform the measurements again

      • Type-B team will continue the noise measurements as well as the geophones
      • Fujii and Shoda will go to Kamioka on 27-29 June to transfer the information to the Type-B team
  • LVDT for BF damping
    • If we get the design from Virgo within this month, we will use the design
    • If not, we should make a design from scratch
  • Interference of the interferometer beams with VIS structure
    • Shoda is working on the new fixture design for PR: by mid-July
    • Need to check if there is a similar problem in SR (Mark)

Site work plan for the next week

  • Mon:
  • Tue:
  • Wed:
  • Thu:
  • Fri:

BS crane will not be available: 13th -14th of June

Travel Plans

  • Travel (Week of 6/13)
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Ohishi:
    • Sato:
  • Travel (Week of 6/20):
    • Takahashi:19-21 (Acceptance of SFs, check items, move things around and so on)

    • Shoda:
    • Mark:20-24 (preparation for BS installation)

    • Fabian:20-24 (preparation for BS installation)

    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:20-24(not yet decided)

    • Ohishi:

June 27-29: Fujii, Shoda

July 4 - 8: Takahashi, Ishizaki, Sato (site check for the installation of Type-A)

Mark is away: July 8-20

Next meeting

2016/6/17(Fri) 13:30 -

Next VIS F2F 6/17

Next next F2F 7/8

KAGRA/Subgroups/VIS/VISMinutes20160610 (last edited 2016-06-10 15:45:46 by YoichiAso)