= Agenda/Minutes of the VIS Meeting on 2016/6/24 = 2016/6/24 13:30 - 15:00 @ Room 210 Participants:Fabian, Mark, Ohishi, Aso, Sato, Ishizaki, Tanaka, Hirata, Shoda, Raffaele, Akutsu == Progress report == Schedule Chart ([[https://www.dropbox.com/s/jcjn7pladconq3n/VIS%20Overall%20Schedule%2020160617.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/aymck60fpnqgj2x/VIS%20Overall%20Schedule%2020160617.mpp?dl=0|MPP]]) === Type-A (Takahashi) === * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA|Minutes of Type-A Meeting]] * Simulation * '''Deadline is the end of June (Okutomi)''' * 5 blades for BF -> "The filters in Virgo are different from the GAS filters (no compression). 3 + 2 combination is no problem." (by E. Majorana) === Type-B (Mark) === * Type B Past Week Summary * Mark and Fabian worked at Kamioka: * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added. * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction. * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area. * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction. * Hirata-san shipped 7 SFs and some parts to Kamioka. * Hirata-san made assembly drawings of the damper rings and cable clamps for SR. * Hirata-san liaised with Mirapro about the frame assembly. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco. * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables. * Feedthrough Adapters * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Installation stuff * Crane scale - RECEIVED * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] === Type-Bp (Shoda) === * Designed the additional masses for the IM [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5301|JGWdoc]](Shoda) * Created the 3D model of the vacuum tank with the PR suspensions also for PR2, 3, and M. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5309|Sectional View of PRs]](Shoda) * Checked if the suspension parts clip any beams. Found the POX and POY beams are clipped at the RM. (Shoda) * Ckecked also the OpLev beam path inside the chamber except for PR2. Found that we cannot have the OpLev beam spot at the center of the PR3 optic. [[https://granite.phys.s.u-tokyo.ac.jp/svn/LCGT/trunk/VIS/CAD/|SVN]](Shoda) * Summarized the information of iKAGRA PR3 measurement. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5316|Report]](Fujii) * Now comparing the simulation and the measurement. * Design for the modification of the optical bench suspension points is on going. (Shoda) * We need the additional machining at the intermediate stage of the optical bench. * Design for the installation jigs for the optical bench is on going. (Shoda) * Detailed simulation for the modified Type-Bp is on going. (Fujii) * Created the Type-Bp model in both the SUMCON and simulink. * Checked the almost all the modes are damped within 1 min. * Design for the control filters are on going. * I asked Kasuya-san @ Somiya group to join the Type-Bp installation. And she agrees. How far she will be involved is under discussion. === IMMT (Ohishi) === * No report === Watchdog system (Tanaka) === * I'm working on experiment for stability of PhotoMos Relay. . (I will be reported at the next meeting(Maybe..). * Above 10Hz, the resistance fluctuation seems small (1e-7 Ohm/rtHz level) * In the 20min time scale, the resistance is fluctuating with the amplitude of 0.5mOhm or so. * '''We will get more detailed report in the next week''' === Safety === * No issue == Issues == * LVDT for BF damping (Shoda, Raffaele) * Will have a meeting with Virgo on 6/27 from 4PM * '''Shoda will give an overall presentation ''' * Show the fit check drawings * Discussion about the electronics. '''Ask Virgo people if they can give a short presentation on electronics (Raffaele)''' * Available size around the BFs (Shoda, Sato) * Type-Bp: 6 of them will fit if we rotate the vertical ones around the wire axis. * Type-A: We need to use the openings for the flanges in the cross-tube * Length to pitch coupling simulation (Okutomi) * Dummy payloads for Type-A (Takahashi, Aso) * Dummy payload interferometer: unlikely to happen * Need to think about how to test the Type-A performance without Michelson. == Site work plan for the next week == * Mon:Mark and Fabian for BS preparation, Fujii for accelerometer, Akutsu and Simon for BS length sensing OpLev * Tue: Mark and Fabian for BS preparation, Fujii for accelerometer, Akutsu and Simon for BS length sensing OpLev * Wed: Mark and Fabian for BS preparation, Fujii for accelerometer * Thu: Mark and Fabian for BS preparation. * Fri: Mark and Fabian for BS preparation. == Travel Plans == * Travel (Week of 6/27) * Takahashi: * Shoda: * Mark:27 - 7/1 * Fabian: 27 - 7/1 * Okutomi: * Fujii: 27-29 * Ishizaki: * Hirata: * Ohishi: * Sato: * Akutsu: 27-28 * Simon: 27-28 * Travel (Week of 7/4): * Takahashi: 4-7 (extended chief meeting, site check for the installation of Type-A) * Shoda: 4 (extended chief meeting) * Mark:4-6 (preparation for BS installation) * Fabian: * Okutomi: * Fujii: * Ishizaki:5-7 (site check for the installation of Type-A) * Hirata:4-6 (preparation for BS installation) * Sato: 5-7 (site check for the installation of Type-A) * Ohishi: Mark is away: July 8-20 == Next meeting == 2016/7/1(Fri) 13:30 - Next F2F 7/8