* Put a report here | * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA|Minutes of Type-A Meeting]] * Vacuum compatibility of the release sensor was checked by Saito-san.''' |
Line 13: | Line 14: |
* Put a report here |
* Type B Past Week Summary * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more. * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]). * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san re-greased them with vacuum grease. * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it. * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber. * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working. * Fabian did more pre-assembly of the RM/IM/IRM. * Fabian designed modifications for the brackets on the security structure for immobilizing the IM, and Hirata-san did 2D drawings from them. * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags. * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank. * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well. * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18. * Hirata-san measured another filter and cleaned parts for Fabian * Type B ongoing issues * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts - RECEIVED. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Apply grease to jacks for assembly frame (Takahashi) * Finish assembly of BS IM, RM and IRM (Fabian). * Weigh IM/RM/IRM (Fabian, Hirata) * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Mark, Shoda) * Remove glue from dummy BS face (Fabian) * Remove prism from dummy BS (Hirose, Fabian?) * Reglue flags and prisms (Tatsumi, Fabian) * Buy wire for BS and RM (Hirata) * Clean wire for BS and RM (Hirata) * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
Line 28: | Line 77: |
* LVDT for BF damping (Shoda, Raffaele) * The next meeting on July 11th * Check if the current design of Virgo LVDT will fit to our systems * If so, we will produce them in Japan * Two sample LVDTs will be sent to Japan |
|
Line 35: | Line 79: |
* What to do with the SR preparation * Call for shifts ? |
Agenda/Minutes of the VIS Meeting on 2016/7/8
2016/7/8 13:30 - @ Room 210
Participants:
Progress report
Type-A (Takahashi)
Vacuum compatibility of the release sensor was checked by Saito-san.
Type-B (Mark)
- Type B Past Week Summary
- Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more.
Mark and Hirata-san helped Mirapro construct the assembly frame (photos).
- Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san re-greased them with vacuum grease.
- Mark and Hirata-san wiped down the assembly frame and put the clean bag on it.
- Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber.
- Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working.
- Fabian did more pre-assembly of the RM/IM/IRM.
- Fabian designed modifications for the brackets on the security structure for immobilizing the IM, and Hirata-san did 2D drawings from them.
- Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags.
- Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank.
- Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well.
Tatsumi-san ordered modifications to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18.
- Hirata-san measured another filter and cleaned parts for Fabian
- Type B ongoing issues
- OSEMs
- Akutsu-san is working to get wide-mouth OSEMs
Longer cables for BF->PI and SF->PI.
- Connectors RECEIVED, cables being made.
- SR machining test ongoing.
- Lower breadboard stuff
- Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
- Breadboard springs (in manufacture, expected end of July)
- Nail-head parts - RECEIVED.
- Documents
BS Assembly Procedure E1504235, E1504235 draft
- OSEMs
- To-do list during Mark's vacation
- Apply grease to jacks for assembly frame (Takahashi)
- Finish assembly of BS IM, RM and IRM (Fabian).
- Weigh IM/RM/IRM (Fabian, Hirata)
- Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
- Analyze geophone data (Mark, Shoda)
- Remove glue from dummy BS face (Fabian)
- Remove prism from dummy BS (Hirose, Fabian?)
- Reglue flags and prisms (Tatsumi, Fabian)
- Buy wire for BS and RM (Hirata)
- Clean wire for BS and RM (Hirata)
- Do fit/function test of winches (Fabian/Hirata)
- Ship winches to Kamioka (Hirata/Fabian)
- Work on BS simulation (Fabian)
- Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
- Write more of payload assembly procedure (Fabian)
- Write more of main assembly procedure (Mark)
- Longer term to-do list
- Do BS Simulink model (Mark, Kokeyama)
- Do 2D drawings of SR2 parts (Hirata)
- Redesign SRx IM wire clamps for larger prisms, remachined RMs.
- Order SRM/PRM parts (Hirata/Shoda)
- Order SRx fasteners (Hirata)
- Check SR RM machining test progress (Hirata)
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- Put a report here
Safety
- Any issue ?
Discussion
- Inertial Sensors for Type-B (Mark, Fujii)
- Geophone performance results (Fabian)
- What to do with the SR preparation
- Call for shifts ?
Site work plan for the next week
- Mon: Takahshi (witness/supervise the installation of a cross-tube)
- Tue:
- Wed:
- Thu:
- Fri:
Travel Plans
- Travel (Week of 7/11):
Takahashi:11 (Cross tube installation)
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
- Travel (Week of 7/18):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
Mark is away: July 8-20
Next meeting
2016/7/15(Fri) 13:30 - (Aso will be absent)