Size: 6230
Comment:
|
Size: 6239
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 82: | Line 82: |
Measurement with tape measure shows the chamber center is (x, y) = (0mm, +2mm) based on the floor points. | Measurement with tape measure shows that now the chamber center is (x, y) = (0mm, +2mm) based on the floor points. |
Agenda/Minutes of the VIS Meeting on 2016/7/8
2016/7/8 13:30 - @ Room 210
Participants:
Progress report
Type-A (Takahashi)
- Vacuum compatibility of the release sensor was checked by Saito-san.
Type-B (Mark)
- Type B Past Week Summary
- Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more.
Mark and Hirata-san helped Mirapro construct the assembly frame (photos).
- Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san re-greased them with vacuum grease.
- Mark and Hirata-san wiped down the assembly frame and put the clean bag on it.
- Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber.
- Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working.
- Fabian did more pre-assembly of the RM/IM/IRM.
- Fabian designed modifications for the brackets on the security structure for immobilizing the IM, and Hirata-san did 2D drawings from them.
- Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags.
- Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank.
- Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well.
Tatsumi-san ordered modifications to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18.
- Hirata-san measured another filter and cleaned parts for Fabian
- Type B ongoing issues
- OSEMs
- Akutsu-san is working to get wide-mouth OSEMs
Longer cables for BF->PI and SF->PI.
- Connectors RECEIVED, cables being made.
- SR machining test ongoing.
- Lower breadboard stuff
- Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
- Breadboard springs (in manufacture, expected end of July)
- Nail-head parts - RECEIVED.
- Documents
BS Assembly Procedure E1504235, E1504235 draft
- OSEMs
- To-do list during Mark's vacation
- Apply grease to jacks for assembly frame (Takahashi)
- Finish assembly of BS IM, RM and IRM (Fabian).
- Weigh IM/RM/IRM (Fabian, Hirata)
- Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
- Analyze geophone data (Mark, Shoda)
- Remove glue from dummy BS face (Fabian)
- Remove prism from dummy BS (Hirose, Fabian?)
- Reglue flags and prisms (Tatsumi, Fabian)
- Buy wire for BS and RM (Hirata)
- Clean wire for BS and RM (Hirata)
- Do fit/function test of winches (Fabian/Hirata)
- Ship winches to Kamioka (Hirata/Fabian)
- Work on BS simulation (Fabian)
- Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
- Write more of payload assembly procedure (Fabian)
- Write more of main assembly procedure (Mark)
- Longer term to-do list
- Do BS Simulink model (Mark, Kokeyama)
- Do 2D drawings of SR2 parts (Hirata)
- Redesign SRx IM wire clamps for larger prisms, remachined RMs.
- Order SRM/PRM parts (Hirata/Shoda)
- Order SRx fasteners (Hirata)
- Check SR RM machining test progress (Hirata)
Type-Bp (Shoda)
- Type-Bp modification 3D Drawings
- Saito-san implemented the Virgo design into the Type-Bp design. (I asked him a little more updates.)
- We have some questions about F7 LVDTs.
- Coil specification
- Its design (Slits on the coils. The place where the wires suppose to come out.)
[A/I] Structual analysis
- Installation related issue
- Technical document is written by Shoda.
- Does the Type-B team use the hanging frame for iKAGRA PR2?
[A/I] Shoda will decide the meeting date will Mirapro.
IMMT (Ohishi)
- Schedule
- Finally succeeded in installing Windows and Microsoft Project.
- Asking a company to make a quotation for writing 3D CAD drawing of IMMT suspensions from 2D parts plans.
- BS chamber was relocated (6th and 7th July).
- Measurement with tape measure shows that now the chamber center is (x, y) = (0mm, +2mm) based on the floor points.
Watchdog system (Tanaka)
Safety
- Any issue ?
Discussion
- Inertial Sensors for Type-B (Mark, Fujii)
- Geophone performance results (Fabian)
- What to do with the SR preparation
- Call for shifts ?
Site work plan for the next week
- Mon: Takahshi (witness/supervise the installation of a cross-tube)
- Tue:
- Wed:
- Thu:
- Fri:
Travel Plans
- Travel (Week of 7/11):
Takahashi:11 (Cross tube installation)
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
- Travel (Week of 7/18):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
Mark is away: July 8-20
Next meeting
2016/7/15(Fri) 13:30 - (Aso will be absent)