Differences between revisions 1 and 9 (spanning 8 versions)
Revision 1 as of 2016-07-27 13:51:45
Size: 6072
Editor: YoichiAso
Comment:
Revision 9 as of 2016-07-29 11:37:56
Size: 1781
Editor: YoichiAso
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
Schedule Chart ([[https://www.dropbox.com/s/in8snejffra66as/VIS%20Overall%20Schedule%2020160720.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/byl5lkwhp0p25kb/VIS%20Overall%20Schedule-160720.mpp?dl=0|MPP]]) -> Something wrong with the Project Server. Aso will try to fix it. Schedule Chart ([[https://www.dropbox.com/s/xnwas3z51u821md/VIS%20Overall%20Schedule%2020160727.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/ys1u5r4wqb2b3ol/VIS%20Overall%20Schedule-160727.mpp?dl=0|MPP]])
Line 11: Line 11:
 * Simulation (Okutomi)
  * Will calculate the requirements for the sensor noise
  * Will calculate the requirements for the actuator coupling and coil driver noise
 * Type-A installation procedure review in the second week of August.
 * Type-A installation procedure review on the 10th in August.
Line 17: Line 14:
[[KAGRA/Subgroups/VIS/MeetingNAOJ]]

 * Discussion
  * Next week, Type-B team will stay in Tokyo to finish remaining tasks
 * Type B Past Week Summary
  * Hirata-san wiped one set each of wires for the BS and RM (additional sets pending).
  * Hirata-san washed remachined locking parts for the IM and screws for jacks.
  * Hirata-san liaised with Ikenoue-san of ATC to get new winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking.
  * Hirata-san worked on the Inventor 3D assembly of the SR2.
  * The scale for checking the masses of the IM parts arrived.
  * Fabian and Hirata-san assembled the IRM and identified an issue with the Teflon-coated lock screws between the IM and IRM. The screws were slightly too large, and correcting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order SDC-coated screws from Misumi and have additional machining done on them.
  * Fabian tracked down the calibration factors for the geophones and generated a calibrated [[attachment:Geophone_Kamioka.png|plot]].
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
  * Longer cables for BF->PI and SF->PI ORDERED.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
 * Put a report here
Line 62: Line 17:
 * Basic Design Review [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeBp/meeting160721|minute]]
 * Contacted with some companies. (Cost estimate will be done by ATC.)
 * Put a report here
Line 66: Line 20:
 * In negotiation with a company for CAD modeling  * Put a report here
Line 69: Line 23:
 * Working on the software  * Materials to use in meeting.[[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0054/E1605412/001/Soft_Shutdown-WDS_Experiment_report-160729.pdf|PDF]]
Line 72: Line 26:
 * No issue  * Any issue ?
Line 75: Line 29:
 * Inertial Sensors for Type-B (Fabian)
  * Fabian's plot https://dl.dropboxusercontent.com/u/99018438/Geophone_Kamioka.png
  * Plot the theoretical noise of geophone
 * Wide OSEM production and test plan (Akutsu, Aso)
  * Steps
   * Test assemble a few (Akutsu)
   * Noise check (Type-B team)
    * Change the supply current of a satellite amplifier (find the optimal value for the wide OSEM).
    * Calibration
    * Noise measurements
    * Deadline for the noise check: by the end of September
    * Wide OSEM noise should be checked in Kamioka using the digital system. Type-B team will do it when they come to Kamioka.
    * Akutsu will give Type-B team a wide OSEM and test setup.
   * Mass production of wide OSEMs (Akutsu)
    * Assembly (call for shift)
    * Wash (Hirata ?)
    * Calibration and simple noise check(call for shift)
    * A/I: Akutsu will write an assembly procedure document. Make a call for shift to start the mass production asap.
   * Ship to Kamioka
   * Change the supply current of the satellite amplifiers (talk to AEL: Aso)
 * LVDT test
  * Takahashi and Shoda will discuss about this
  * Points to be clarified: purpose of the test (what kind of information we want to obtain to design the new LVDTs ?)
  * Deadline for the new LVDTs: the end of August.
 * Inertial sensor selection for Type-B update (Fabian)
  * [[https://dl.dropboxusercontent.com/u/99018438/Geophone_Kamioka.png|Plot1]], [[https://dl.dropboxusercontent.com/u/99018438/Geophone_Kamioka_noise_ratio.png|Plot2]]
 * Wide OSEM
  * Mass production status (Akutsu)
 * Document Tree
  * [[https://www.dropbox.com/s/c688de3olu9l1vx/bKAGRA_Input.dxf?dl=0|VIS Document Tree]]
Line 108: Line 44:
 * Travel (Week of 7/25):  * Travel (Week of 8/1):
Line 111: Line 47:
  * Mark: Kashiwa on some day
  * Fabian: Kashiwa on some day
  * Mark:
  * Fabian:
Line 120: Line 56:
 * Travel (Week of 8/1):  * Travel (Week of 8/8):
Line 122: Line 58:
  * Shoda:
  * Mark: 1 - 5 ?
  * Fabian: 1 - 5 ?
  * Shoda:8-10 (check existing parts)
  * Mark:
  * Fabian:
Line 133: Line 69:
2016/7/29(Fri) 13:30 - 2016/8/5(Fri) 13:30 -

Agenda/Minutes of the VIS Meeting on 2016/7/29

2016/7/29 13:30 - @ Room 210

Participants:

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

Type-B (Mark)

  • Put a report here

Type-Bp (Shoda)

  • Put a report here

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Materials to use in meeting.PDF

Safety

  • Any issue ?

Discussion

  • Inertial sensor selection for Type-B update (Fabian)
  • Wide OSEM
    • Mass production status (Akutsu)
  • Document Tree

Site work plan for the next week

  • Mon:
  • Tue:
  • Wed:
  • Thu:
  • Fri:

Travel Plans

  • Travel (Week of 8/1):
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:
  • Travel (Week of 8/8):
    • Takahashi:
    • Shoda:8-10 (check existing parts)

    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:

Next meeting

2016/8/5(Fri) 13:30 -

KAGRA/Subgroups/VIS/VISMinutes20160729 (last edited 2016-07-29 15:50:31 by YoichiAso)