Line 22: Line 22:
 * Put a report here  * Type-Bp modification
  * Saito-san made the 1st version of the 2D drawing. Though we still have small modification, we can start cost estimate.
 * F7 LVDT
  * Virgo LVDT test is ongoing. The measured calibration factor and noise level is worse than expected. More tuning is required.
 * Installation related issues
  * BF weight is lighter than the 3D model. (CAD: 50 kg, measured: 45 kg.) Shoda has not been able to find any reason yet. Further investigation will be done in next week.
  * Mirapro sent us the design of the optical bench installation jigs. We sent them some request for the update.
  * The design of the assembly frame is almost fixed.
 * Simulation and others
  * None

 * '''A/I'''
  * Investigate the BF weight inconsistency (Shoda)
  * Some 2D drawings not related to the modification (additional masses, OB wire hook, OB wires,,,) (Hirata)
  * Assembly drawing (Shoda)
  * Optical bench additional parts design
  * Organize the mirror preparation

Agenda/Minutes of the VIS Meeting on 2016/8/19

2016/8/19 13:30 - @ Room 210

Participants:

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Task list was updated.
  • No type-A meeting in this week.
  • EQ stop, release sensor, dummy payload: The specification document and drawings were fixed. The bidding was announced on the 17th.
  • Installation procedure: The review was held on the 10th.
  • Standard filters: Cheking of 6 sets were finished and shipped to Kamioka.
  • BF damper: LVDT sample is under testing. The measured noise is too large (10^-6 m/rtHz).

Type-B (Mark)

  • Put a report here

Type-Bp (Shoda)

  • Type-Bp modification
    • Saito-san made the 1st version of the 2D drawing. Though we still have small modification, we can start cost estimate.
  • F7 LVDT
    • Virgo LVDT test is ongoing. The measured calibration factor and noise level is worse than expected. More tuning is required.
  • Installation related issues
    • BF weight is lighter than the 3D model. (CAD: 50 kg, measured: 45 kg.) Shoda has not been able to find any reason yet. Further investigation will be done in next week.
    • Mirapro sent us the design of the optical bench installation jigs. We sent them some request for the update.
    • The design of the assembly frame is almost fixed.
  • Simulation and others
    • None
  • A/I

    • Investigate the BF weight inconsistency (Shoda)
    • Some 2D drawings not related to the modification (additional masses, OB wire hook, OB wires,,,) (Hirata)
    • Assembly drawing (Shoda)
    • Optical bench additional parts design
    • Organize the mirror preparation

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Put a report here

Safety

  • Any issue ?

Discussion

  • Installation order for Type-B and Type-Bp

Site work plan for the next week

  • Mon: BS test hanging (Mark, Fabian, Zhao)
  • Tue: BS test hanging (Mark, Fabian, Zhao)
  • Wed: BS test hanging (Mark, Fabian, Zhao)
  • Thu: F2F
  • Fri: F2F

Travel Plans

  • Travel (Week of 8/22):
    • Takahashi:
    • Shoda:
    • Mark: 22-26 ?
    • Fabian: 22-26 ?
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:
  • Travel (Week of 8/29):
    • Takahashi: 30 - 9/2 ?
    • Shoda:
    • Mark: 29 - 9/2 ?
    • Fabian: 29 - 9/2 ?
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato: 30 - 9/2 ?
    • Ohishi:

Next meeting

2016/9/2(Fri) 13:30 -