Schedule Chart ([[https://www.dropbox.com/s/g1t88ygow3iub84/VIS%20Overall%20Schedule-20160817.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/nn349ssjnu8aegh/VIS%20Overall%20Schedule-20160817.mpp?dl=0|MPP]]) | Schedule Chart ([[https://www.dropbox.com/s/mecu9tgoua7jutt/VIS%20Overall%20Schedule-20160831.mpp?dl=0|PDF]],[[https://www.dropbox.com/s/mecu9tgoua7jutt/VIS%20Overall%20Schedule-20160831.mpp?dl=0|MPP]]) |
Line 28: | Line 28: |
* Installation order for Type-B and Type-Bp * BS(1-3) -> SR3(3-7) -> SR2(7-11) -> SRM (11-) * PR3 (12-3) -> PRM(3-5) -> PR2(5-7) * We need to coordinate the BS area usage with PI assembly work and the transportation of the assembly frame. * Aso, Mark, Takahashi will discuss it F2F. |
* Insufficient strength of the maraging rods ? * Local sensor to monitor the TM motion during assembly |
Line 38: | Line 35: |
* Thu: F2F * Fri: F2F |
* Thu: BS test hanging (Mark, Fabian, Zhao) * Fri: BS test hanging (Mark, Fabian, Zhao) |
Line 42: | Line 39: |
* Travel (Week of 8/22): * Takahashi:25 - 27 * Shoda:22 - 27 * Mark: 22 - 27 * Fabian: 22 or 23 - 27 * Okutomi: 25 - 27 |
* Travel (Week of 9/5): * Takahashi: * Shoda: * Mark: 5 - 8 * Fabian: 5 - 8 * Okutomi: |
Line 54: | Line 51: |
* Travel (Week of 8/29): | * Travel (Week of 9/12): |
Line 57: | Line 54: |
* Mark: 29 - 9/2 * Fabian: 29 - 9/2 |
* Mark: 12 - 15 * Fabian: 12 - 15 |
Line 67: | Line 64: |
2016/9/2(Fri) 13:30 - Next F2F 2016/9/9 |
2016/9/9(Fri) 13:30 - in Mitaka |
Agenda/Minutes of the VIS Meeting on 2016/9/2
2016/9/2 13:30 - @ Room 210
Participants:
Progress report
Type-A (Takahashi)
- Put a report here
Type-B (Mark)
- Put a report her
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- Put a report here
Safety
- Any issue ?
Discussion
- Insufficient strength of the maraging rods ?
- Local sensor to monitor the TM motion during assembly
Site work plan for the next week
- Mon: BS test hanging (Mark, Fabian, Zhao)
- Tue: BS test hanging (Mark, Fabian, Zhao)
- Wed: BS test hanging (Mark, Fabian, Zhao)
- Thu: BS test hanging (Mark, Fabian, Zhao)
- Fri: BS test hanging (Mark, Fabian, Zhao)
Travel Plans
- Travel (Week of 9/5):
- Takahashi:
- Shoda:
- Mark: 5 - 8
- Fabian: 5 - 8
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
- Travel (Week of 9/12):
- Takahashi:
- Shoda:
- Mark: 12 - 15
- Fabian: 12 - 15
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
Next meeting
2016/9/9(Fri) 13:30 - in Mitaka