 * Type B Past Week Summary - weeks of 8/22 and 8/29 ==== Discussion ====
*  ==== Type B Past Week Summary - weeks of 8/22 and 8/29 ====
Line 48: Line 50:
  * Saito-san made some updates around the LVDT coils. Shoda is implimenting them into the 3D CAD model.   * Saito-san made some updates around the LVDT coils. Shoda is implementing them into the 3D CAD model.

Agenda/Minutes of the VIS Meeting on 2016/9/2

2016/9/2 13:30 - @ Room 210

Participants: Mark, Takahashi, Ohishi, Aso, Hirata, Okutomi, Sato, Tanaka, Ishizaki, Fabian, Shoda, Raffaele

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Top chamber: Installation and leak test will be postponed to January due to delay of cooling test of the cryostat.
  • EQ stop, release sensor, dummy payload: Procurement is in the bidding process. Open bidding is on 13th September.
  • BF damper: Assembling the LVDT prototype.
  • Maraging wire: Stress concentration around the head was pointed out by CRY. Now investigationg.

Type-B (Mark)

Discussion

Type B Past Week Summary - weeks of 8/22 and 8/29

  • Fabian, Mark, Zhao-kun and Yokogawa-kun did BS installation at Kamioka:
    • Weighed the BF, SF and dummy BS (in mirror box).
    • Moved the geophones onto the optical table, clamped them down and took another time series for analysis.
    • Aligned the IM, installed the extra trim masses, tested the picos and weighed the whole assembly.
    • Placed vacuum flanges and cleaned D-Sub cables ready for routing to the rack.
    • Realigned and immobilized the optical table (which had been bumped).
    • Made safety improvements on the second floor (new safety rail, new arrangement of floor pieces, caution tape around holes)
    • Suspended the dummy BS. Currently however it is not hanging correctly, but is off in the +Y direction by several mm relative to the mirror box.
    • We set up the BS OL, using one of the wheeled chests of drawers as a base and using the OL breadboard from the PR2 assembly frame.
  • Hirata-san made a 3D assembly model for SR2 and added the optical design.
  • Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  • Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  • Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
  • Type B ongoing issues
    • Longer cables for BF->PI and SF->PI - RECEIVED

  • Longer term to-do list
    • Decide position of BS rack - DONE
    • Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
    • Write more of payload assembly procedure (Fabian) - ONGOING
    • Write more of BS Assembly Procedure E1504235, E1504235 draft (Mark) - ONGOING

    • Lower breadboard installation to be incorporated into the procedure document.
    • Work on BS simulation (Fabian)
    • Do BS Simulink model (Mark, Kokeyama)
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)

Type-Bp (Shoda)

  • Type-Bp modification
    • Saito-san made some updates around the LVDT coils. Shoda is implementing them into the 3D CAD model.
    • Obuchi-san provided the result of the structure analysis. Shoda will gather the information and write the design document.
    • Saito-san is asking the cost estimate to Techno-port and still waiting for the reply. We asked him to ask the cost estimate to another company.
    • Shoda is preparing the specification sheets for the ordering.
    • We are planing to have the final design reciew from 12 - 14th September.
  • Additional ordering for PRs.
    • additional masses for IM: Hirata-san made the drawing.
    • additional masses for BF: Shoda is making the model.
    • IM flags: Hirata-san will make the drawing for the additional machinig.
    • TM flags: Discussion is ongoing with Aso-san, Mark, and Hirata-san. (Old design parts will be ordered together with BF modification parts just in case.)
    • 1st wire breakers: will be ordered with BF modification parts
    • 2nd wire breakers: will be ordered with BF modification parts
    • the correts for the hexagon cable clamps: the CAD model of the maraging rod is wrong. Re-design will be done by Hirata-san.
    • maraging rods for BFRM: will be ordered with Type-A maraging rods.
    • signal cables: will be ordered with Type-A.
    • BF EQ stop ring: will be ordered together with the assembly frame.
  • Assembly frame
    • Design is almost fixed: shown via Seevogh
  • Optical bench
    • Installation jigs: shown via Seevogh
    • Adapters: shown via Seevogh
    • wires: shown via Seevogh (the hook analysis is necessary?)
    • missing hooks: shown via Seevogh
    • Shoda is preparing the specification sheets for the ordering (together with the assembly frame).
  • Washing
    • EQ stop: 3sets are in Akeno, un-washed. Takahashi-san will order the washing.
    • OB-IM, OB-MD: 3sets are not ordered yet. Takahashi-san will order them.
  • Bottom filter cup
    • The thickness of the top plate of the cup is different from the design. (12mm -> 11mm)

  • Mirror preparation
    • Hirose-san and Shoda are preparing jigs for the flag detaching. [[|Catoon]]
  • A/I

    • Prepare for the final design review. (Shoda)
    • Make the design document (Shoda, Fujii)
    • Ordering preparation (Shoda)
    • Design work around flags (Hirata, Mark)

IMMT (Ohishi)

  • Measured location of things in IFI and IMMT chamber with Kasuya-san on 23-24th Aug.
    • It smelled bad (musty) outflow air from the vacuum chamber.
  • Consider to install IMMT2 suspension from the Top flange of the chamber.
    • Discussing with Somiya-san, Hirose-san and Kawamura-san.
  • Kitazawa-san (Toyama Univ.) is coming to help coupling measurement of the small OSEMs for IMMT.
  • 3D2D drawings of current IMMT suspension almost completed.
  • Next week, MCF chamber will be opened.

Watchdog system (Tanaka)

  • Progress report(For Power circuit re-design)PDF

Safety

  • Any issue ?

Discussion

  • Insufficient strength of the maraging rods ?
    • Asked ATC to do FEA.
      • Type-B top wire has the first priority
    • Will ask KEK to perform the strength test. ~ 3 weeks to complete.
    • What to do if the safety margin is not enough
      • Make new wires
      • Modify or make new receptacle parts and replace them
    • Should contact
    • When do we need. Type-Bp beg. Dec. Type-B mid Oct.
  • Local sensor to monitor the TM motion during assembly

Site work plan for the next week

  • Mon: BS test hanging (Mark, Fabian, Zhao)
  • Tue: BS test hanging (Mark, Fabian, Zhao)
  • Wed: BS test hanging (Mark, Fabian, Zhao)
  • Thu: BS test hanging (Mark, Fabian, Zhao)
  • Fri: BS test hanging (Mark, Fabian, Zhao)

Travel Plans

  • Travel (Week of 9/5):
    • Takahashi:
    • Shoda:
    • Mark: 5 - 8
    • Fabian: 5 - 8
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:
  • Travel (Week of 9/12):
    • Takahashi:
    • Shoda:
    • Mark: 12 - 15
    • Fabian: 12 - 15
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:

Next meeting

2016/9/9(Fri) 13:30 - in Mitaka