Line 20: Line 20:
* Type-Bp modification
 * Saito-san made some updates around the LVDT coils. Shoda is implimenting them into the 3D CAD model.
 * Obuchi-san provided the result of the structure analysis. Shoda will gather the information and write the design document.
 * Saito-san is asking the cost estimate to Techno-port and still waiting for the reply.
 * Type-Bp modification
  * Saito-san made some updates around the LVDT coils. Shoda is implimenting them into the 3D CAD model.
  * Obuchi-san provided the result of the structure analysis. Shoda will gather the information and write the design document.
  * Saito-san is asking the cost estimate to Techno-port and still waiting for the reply.
Line 25: Line 25:
 * Shoda is preparing the specification sheets for the ordering.
 * We are planing to have the final design reciew from 12 - 14th September.
  * Shoda is preparing the specification sheets for the ordering.
  * We are planing to have the final design reciew from 12 - 14th September.
Line 28: Line 28:
* Additional ordering for PRs.
 * additional masses for IM: Hirata-san made the drawing.
 * additional masses for BF: Shoda is making the model.
 * IM flags: Hirata-san will make the drawing for the additional machinig.
 * TM flags: Discussion is ongoing with Aso-san, Mark, and Hirata-san. (Old design parts will be ordered together with BF modification parts just in case.)
 * 1st wire breakers: will be ordered with BF modification parts
 * 2nd wire breakers: will be ordered with BF modification parts
 * the correts for the hexagon cable clamps: the CAD model of the maraging rod is wrong. Re-design will be done by Hirata-san.
 * maraging rods for BFRM: will be ordered with Type-A maraging rods.
 * signal cables: will be ordered with Type-A.
 * BF EQ stop ring: will be ordered together with the assembly frame.
 * Additional ordering for PRs.
  * additional masses for IM: Hirata-san made the drawing.
  * additional masses for BF: Shoda is making the model.
  * IM flags: Hirata-san will make the drawing for the additional machinig.
  * TM flags: Discussion is ongoing with Aso-san, Mark, and Hirata-san. (Old design parts will be ordered together with BF modification parts just in case.)
  * 1st wire breakers: will be ordered with BF modification parts
  * 2nd wire breakers: will be ordered with BF modification parts
  * the correts for the hexagon cable clamps: the CAD model of the maraging rod is wrong. Re-design will be done by Hirata-san.
  * maraging rods for BFRM: will be ordered with Type-A maraging rods.
  * signal cables: will be ordered with Type-A.
  * BF EQ stop ring: will be ordered together with the assembly frame.
Line 40: Line 40:
* Assembly frame
 * Design is almost fixed: shown via Seevogh
 * Assembly frame
  * Design is almost fixed: shown via Seevogh
Line 43: Line 43:
* Optical bench
 * Installation jigs: shown via Seevogh
 * Adapters: shown via Seevogh
 * wires: shown via Seevogh (the hook analysis is necessary?)
 * missing hooks: shown via Seevogh
 * Shoda is preparing the specification sheets for the ordering (together with the assembly frame).
 * Optical bench
  * Installation jigs: shown via Seevogh
  * Adapters: shown via Seevogh
  * wires: shown via Seevogh (the hook analysis is necessary?)
  * missing hooks: shown via Seevogh
  * Shoda is preparing the specification sheets for the ordering (together with the assembly frame).
Line 50: Line 50:
* Washing
 * EQ stop: 3sets are in Akeno, un-washed. Takahashi-san will order the washing.
 * OB-IM, OB-MD: 3sets are not ordered yet. Takahashi-san will order them.
 * Washing
  * EQ stop: 3sets are in Akeno, un-washed. Takahashi-san will order the washing.
  * OB-IM, OB-MD: 3sets are not ordered yet. Takahashi-san will order them. 
Line 54: Line 54:
* Bottom filter weight
 * The thickness of the top plate of the cup is different from the design. (12mm -> 11mm)
 * Bottom filter cup
  * The thickness of the top plate of the cup is different from the design. (12mm -> 11mm)
Line 57: Line 57:
* Mirror preparation
 * Hirose-san and Shoda are preparing jigs for the flag detaching. [[|Catoon]]
 * Mirror preparation
  * Hirose-san and Shoda are preparing jigs for the flag detaching. [[|Catoon]]
Line 60: Line 60:
* '''A/I'''
 * Prepare for the final design review. (Shoda)
 * Make the design document (Shoda, Fujii)
 * Ordering preparation (Shoda)
 * Design work around flags (Hirata, Mark)
 * '''A/I'''
  * Prepare for the final design review. (Shoda)
  * Make the design document (Shoda, Fujii)
  * Ordering preparation (Shoda)
  * Design work around flags (Hirata, Mark)

Agenda/Minutes of the VIS Meeting on 2016/9/2

2016/9/2 13:30 - @ Room 210

Participants:

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Top chamber: Installation and leak test will be postponed to January due to delay of cooling test of the cryostat.
  • EQ stop, release sensor, dummy payload: Procurement is in the bidding process. Open bidding is on 13th September.
  • BF damper: Assembling the LVDT prototype.
  • Maraging wire: Stress concentration around the head was pointed out by CRY. Now investigationg.

Type-B (Mark)

  • Put a report her

Type-Bp (Shoda)

  • Type-Bp modification
    • Saito-san made some updates around the LVDT coils. Shoda is implimenting them into the 3D CAD model.
    • Obuchi-san provided the result of the structure analysis. Shoda will gather the information and write the design document.
    • Saito-san is asking the cost estimate to Techno-port and still waiting for the reply. We asked him to ask the cost estimate to another company.
    • Shoda is preparing the specification sheets for the ordering.
    • We are planing to have the final design reciew from 12 - 14th September.
  • Additional ordering for PRs.
    • additional masses for IM: Hirata-san made the drawing.
    • additional masses for BF: Shoda is making the model.
    • IM flags: Hirata-san will make the drawing for the additional machinig.
    • TM flags: Discussion is ongoing with Aso-san, Mark, and Hirata-san. (Old design parts will be ordered together with BF modification parts just in case.)
    • 1st wire breakers: will be ordered with BF modification parts
    • 2nd wire breakers: will be ordered with BF modification parts
    • the correts for the hexagon cable clamps: the CAD model of the maraging rod is wrong. Re-design will be done by Hirata-san.
    • maraging rods for BFRM: will be ordered with Type-A maraging rods.
    • signal cables: will be ordered with Type-A.
    • BF EQ stop ring: will be ordered together with the assembly frame.
  • Assembly frame
    • Design is almost fixed: shown via Seevogh
  • Optical bench
    • Installation jigs: shown via Seevogh
    • Adapters: shown via Seevogh
    • wires: shown via Seevogh (the hook analysis is necessary?)
    • missing hooks: shown via Seevogh
    • Shoda is preparing the specification sheets for the ordering (together with the assembly frame).
  • Washing
    • EQ stop: 3sets are in Akeno, un-washed. Takahashi-san will order the washing.
    • OB-IM, OB-MD: 3sets are not ordered yet. Takahashi-san will order them.
  • Bottom filter cup
    • The thickness of the top plate of the cup is different from the design. (12mm -> 11mm)

  • Mirror preparation
    • Hirose-san and Shoda are preparing jigs for the flag detaching. [[|Catoon]]
  • A/I

    • Prepare for the final design review. (Shoda)
    • Make the design document (Shoda, Fujii)
    • Ordering preparation (Shoda)
    • Design work around flags (Hirata, Mark)

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Progress report(For Power circuit re-design)PDF

Safety

  • Any issue ?

Discussion

  • Insufficient strength of the maraging rods ?
  • Local sensor to monitor the TM motion during assembly

Site work plan for the next week

  • Mon: BS test hanging (Mark, Fabian, Zhao)
  • Tue: BS test hanging (Mark, Fabian, Zhao)
  • Wed: BS test hanging (Mark, Fabian, Zhao)
  • Thu: BS test hanging (Mark, Fabian, Zhao)
  • Fri: BS test hanging (Mark, Fabian, Zhao)

Travel Plans

  • Travel (Week of 9/5):
    • Takahashi:
    • Shoda:
    • Mark: 5 - 8
    • Fabian: 5 - 8
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:
  • Travel (Week of 9/12):
    • Takahashi:
    • Shoda:
    • Mark: 12 - 15
    • Fabian: 12 - 15
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:

Next meeting

2016/9/9(Fri) 13:30 - in Mitaka

KAGRA/Subgroups/VIS/VISMinutes20160902 (last edited 2016-09-02 16:15:00 by YoichiAso)