Line 7: Line 7:
 * Put a report here  * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]]
 * Pre-isolator: Started the assembly of pre-isolator in ATC. Measured the sensitivities of 3 ACCs at the site.
 * EQ stop, release sensor, dummy payload: Production is on going.
 * BF damper: The bidding was announced on 14th. Open bidding is on 9th November.
 * Maraging wire: Obuchi-san redesigned of the wire for Type-A with safety margin of 2.
 * Installation: Making assy. drawings. Designed the hoist tool. Consult with company.
Line 12: Line 18:
 * Put a report here  * BFRM
  * Still waiting for ordering process.
  * Maraging rod drawing is approved.
  * Some minor updates are done.
  * I and Saito-san agreed that the assembly test will be done in Mitaka.

 * Stab Flags
  * Hirata-san made the drawings. We will ask for the cost estimation soon.

 * Assembly frame
  * Asking cost estimate

 * Install procedure
  * I will draw some pictures how to install whole suspension chain into the chamber.

 * Flag removing jig.
  * Being late. Simon told me that it is safe to have the OSEM flags because of the circuits preparation.
Line 60: Line 82:
On 2016/10/21(Fri) we will not have a meeting due to the preparation for the open day. However, people are asked to put progress reports.
VIS F2F: Oct. 28, Nov. 18, Dec. 2
On 2016/10/28(Fri) F2F@Mitaka
VIS F2F: Nov. 18, Dec. 2

VIS progress reports on 2016/10/21

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Pre-isolator: Started the assembly of pre-isolator in ATC. Measured the sensitivities of 3 ACCs at the site.
  • EQ stop, release sensor, dummy payload: Production is on going.
  • BF damper: The bidding was announced on 14th. Open bidding is on 9th November.
  • Maraging wire: Obuchi-san redesigned of the wire for Type-A with safety margin of 2.
  • Installation: Making assy. drawings. Designed the hoist tool. Consult with company.

Type B (Mark)

  • Put a report here

Type-Bp (Shoda)

  • BFRM
    • Still waiting for ordering process.
    • Maraging rod drawing is approved.
    • Some minor updates are done.
    • I and Saito-san agreed that the assembly test will be done in Mitaka.
  • Stab Flags
    • Hirata-san made the drawings. We will ask for the cost estimation soon.
  • Assembly frame
    • Asking cost estimate
  • Install procedure
    • I will draw some pictures how to install whole suspension chain into the chamber.
  • Flag removing jig.
    • Being late. Simon told me that it is safe to have the OSEM flags because of the circuits preparation.

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Put a report here

Safety

  • Any issue ?

Site work plan for the next week

  • Mon: BS test hanging
  • Tue: BS test hanging
  • Wed: BS test hanging
  • Thu: BS test hanging
  • Fri:

Travel Plans

  • Travel (Week of 10/24):
    • Takahashi:
    • Shoda:
    • Mark: 24-27 (BS)
    • Fabian: 24-27 (BS)
    • Okutomi: 24-27 (PI realtime model development)
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:
  • Travel (Week of 10/31):
    • Takahashi:
    • Shoda:
    • Mark: 31-11/4 (BS)
    • Fabian: 31-11/3 (BS)
    • Okutomi: 31-11/4 (PI realtime model development)
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:

Next meeting

On 2016/10/28(Fri) F2F@Mitaka VIS F2F: Nov. 18, Dec. 2