Line 7: Line 7:
 * Put a report here  * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]]
 * Pre-isolator: Started the assembly of pre-isolator in ATC. Measured the sensitivities of 3 ACCs at the site.
 * EQ stop, release sensor, dummy payload: Production is on going.
 * BF damper: The bidding was announced on 14th. Open bidding is on 9th November.
 * Maraging wire: Obuchi-san redesigned of the wire for Type-A with safety margin of 2.
 * Installation: Making assy. drawings. Designed the hoist tool. Consult with company.

VIS progress reports on 2016/10/21

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Pre-isolator: Started the assembly of pre-isolator in ATC. Measured the sensitivities of 3 ACCs at the site.
  • EQ stop, release sensor, dummy payload: Production is on going.
  • BF damper: The bidding was announced on 14th. Open bidding is on 9th November.
  • Maraging wire: Obuchi-san redesigned of the wire for Type-A with safety margin of 2.
  • Installation: Making assy. drawings. Designed the hoist tool. Consult with company.

Type B (Mark)

  • Put a report here

Type-Bp (Shoda)

  • Put a report here

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Put a report here

Safety

  • Any issue ?

Site work plan for the next week

  • Mon: BS test hanging
  • Tue: BS test hanging
  • Wed: BS test hanging
  • Thu: BS test hanging
  • Fri:

Travel Plans

  • Travel (Week of 10/24):
    • Takahashi:
    • Shoda:
    • Mark: 24-27 (BS)
    • Fabian: 24-27 (BS)
    • Okutomi: 24-27 (PI realtime model development)
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:
  • Travel (Week of 10/31):
    • Takahashi:
    • Shoda:
    • Mark: 31-11/4 (BS)
    • Fabian: 31-11/3 (BS)
    • Okutomi: 31-11/4 (PI realtime model development)
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Ohishi:

Next meeting

On 2016/10/28(Fri) F2F@Mitaka VIS F2F: Nov. 18, Dec. 2