VIS progress reports on 2016/10/21
Progress report
Type-A (Takahashi)
- Pre-isolator: Started the assembly of pre-isolator in ATC. Measured the sensitivities of 3 ACCs at the site.
- EQ stop, release sensor, dummy payload: Production is on going.
- BF damper: The bidding was announced on 14th. Open bidding is on 9th November.
- Maraging wire: Obuchi-san redesigned of the wire for Type-A with safety margin of 2.
- Installation: Making assy. drawings. Designed the hoist tool. Consult with company.
Type B (Mark)
- Put a report here
Type-Bp (Shoda)
- BFRM
- Still waiting for ordering process.
- Maraging rod drawing is approved.
- Some minor updates are done.
- I and Saito-san agreed that the assembly test will be done in Mitaka.
- Stab Flags
- Hirata-san made the drawings. We will ask for the cost estimation soon.
- Assembly frame
- Asking cost estimate
- Install procedure
- I will draw some pictures how to install whole suspension chain into the chamber.
- Flag removing jig.
- Being late. Simon told me that it is safe to have the OSEM flags because of the circuits preparation.
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- Put a report here
Safety
- Any issue ?
Site work plan for the next week
- Mon: BS test hanging
- Tue: BS test hanging
- Wed: BS test hanging
- Thu: BS test hanging
- Fri:
Travel Plans
- Travel (Week of 10/24):
- Takahashi:
- Shoda:
- Mark: 24-27 (BS)
- Fabian: 24-27 (BS)
- Okutomi: 24-27 (PI realtime model development)
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
- Travel (Week of 10/31):
- Takahashi:
- Shoda:
- Mark: 31-11/4 (BS)
- Fabian: 31-11/3 (BS)
- Okutomi: 31-11/4 (PI realtime model development)
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
Next meeting
On 2016/10/28(Fri) F2F@Mitaka VIS F2F: Nov. 18, Dec. 2