Differences between revisions 1 and 2
Revision 1 as of 2016-11-03 22:25:43
Size: 1762
Editor: YoichiAso
Comment:
Revision 2 as of 2016-11-04 08:36:25
Size: 2171
Comment:
Deletions are marked like this. Additions are marked like this.
Line 12: Line 12:
 * Put a report here  * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]]
 * Installation: The review was held on 4th.
 * Pre-isolator: The new shaft screws of motor were delivered. They will be replaced.
 * EQ stop, release sensor, dummy payload: Production is on going.
 * BF damper: Open bidding is on 9th.
 * Maraging wire: New design was checked by CRY. Asking the company a quotation.

Agenda/Minutes of the VIS Meeting on 2016/11/4

2016/11/4 13:30 -

Participants:

Progress report

Schedule Chart (PDF,MPP) To Be Updated

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Installation: The review was held on 4th.
  • Pre-isolator: The new shaft screws of motor were delivered. They will be replaced.
  • EQ stop, release sensor, dummy payload: Production is on going.
  • BF damper: Open bidding is on 9th.
  • Maraging wire: New design was checked by CRY. Asking the company a quotation.

Type B (Mark)

  • Put a report here

Type-Bp (Shoda)

  • Put a report here

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Put a report here

Safety

  • Any issue ?

Discussion

  • Any topics ?

Site work plan for the next week

  • Mon: Accelerometer test, PR3 disassemble, Extended Chief Meeting
  • Tue: BS Test Hanging, Accelerometer test, PR3 disassemble, Fire Drill
  • Wed: BS Test Hanging, Accelerometer test, PR3 disassemble
  • Thu: BS Test Hanging, PR3 disassemble
  • Fri: BS Test Hanging, PR3 disassemble

Travel Plans

  • Travel (Week of 11/7):
    • Takahashi: 7-9 (Extended chief meeting/Fire drill/Accelerometer test)
    • Shoda: 7-11 (Extended chief meeting/Fire drill/PR3 disassemble)
    • Mark: 8 - 11 (Fire drill/BS)
    • Fabian:
    • Okutomi: 7 - 11 (Extended chief meeting/Fire drill/Accelerometer test/Realtime code)
    • Fujii: ? (Fire drill)
    • Ishizaki:
    • Hirata: 8 - 11 (Fire drill/BS)
    • Sato: 7-9 (Fire drill/Accelerometer test)
    • Enzo: 8-11 (PR3 disassembly)
    • Ohishi:
  • Travel (Week of 11/14):
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Ohishi:

Next meeting

On 2016/11/11(Fri)

VIS F2F: Nov. 18, Dec. 2

KAGRA/Subgroups/VIS/VISMinutes20161104 (last edited 2016-11-10 17:10:39 by NobuyukiTanaka)