Line 35: Line 35:
 * Please put a report here   * Ordering
   New flags, OB related parts, and the assembly frame were ordered. We are now asking the delivery time.

 * Flag removing jigs
   The parts for the jigs are delivered at Mitaka. Some parts are passed to Fukushima-san for machining.

 * TM OSEM flag
   We found the one of the TM OSEM flags are detached from the mirror when we opened the vacuum tank.
   Since TFs that Fujii-kun measured were not weird, it seems to be detached after the measurement. (Will be reported next week again.)

Agenda/Minutes of the VIS Meeting on 2016/11/11

2016/11/11 13:30 -

Participants: Shoda, Kasuya, Akutsu, Mark, Hirata, Okutomi, Aso, Fujii, Sato, Ishizaki, Tanaka, Ohishi, Enzo, Raffaele, Takahashi

Progress report

Schedule Chart (PDF,MPP) To Be Updated

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Installation: Asking a company the cost and schedule for transportation of Type-A items from the center area to the 2F of Y-end.
  • Pre-isolator: Assembly work will be concentrated to the next week. The PI for SRs will be transported on 21st from Akeno. 5 ACCs were measured at the site.
  • EQ stop, release sensor, dummy payload: Production is on going.
  • BF damper: Open bidding was on 9th. A production company was decided.
  • Maraging wire: Asking the company a quotation. The company is checking procurement of the material.

Type B (Mark)

  • Type B Past Week Summary
    • Mark and Hirata-san at Mitaka
      • Gathered parts for cable making.
    • Mark and Hirata-san at Kamioka:
      • Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame.
      • Installed two more LPCDs and the stepper motor driver in the PR2 rack.
      • Ran cables from the rack to the second and third sat amps (for the IRM OSEMs).
      • Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs.
      • Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement.
      • Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4).
      • Added extension to the IM pico cable for the BF yaw pico.
      • Made LVDT adapter cable.
      • BS mirror box was shipped back.
    • Mark worked on schedule.

Type-Bp (Shoda)

  • Ordering
    • New flags, OB related parts, and the assembly frame were ordered. We are now asking the delivery time.
  • Flag removing jigs
    • The parts for the jigs are delivered at Mitaka. Some parts are passed to Fukushima-san for machining.
  • TM OSEM flag
    • We found the one of the TM OSEM flags are detached from the mirror when we opened the vacuum tank. Since TFs that Fujii-kun measured were not weird, it seems to be detached after the measurement. (Will be reported next week again.)
  • The clump plates for IM may have to be re-manufactured. The current ones have pressed lines by wires.

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Schematic and PCB designJGW-E1605760-v2(PDF)

  • Wearing a terminating resistor(for OSEM sensor deferential out) on both sides.
    • And the value of terminating resistor is changed from 3k to 30k.
  • Design and preparation(investigation of procurement) for production.JGW-E1605791-v4(PDF)

Safety

  • Incidents
    • A strong incandescent light was put close to the plastic sheets of the clean booth, which is probably flammable.
    • A temporary pillar in the PR clean booth near MCF came off when people moved the coach filters and hit it.
  • Foreseen risks
    • Type-B team will lift the suspension system from the BF to measure the weight. Mark will write up a procedure and circulate to the VIS people.
    • Type-A team will continue the assembly of the PI. A crane work to combine the IP and TF is foreseen. Make sure to have at least two people doing the work.

Discussion

  • JPS/ASJ meetings
    • VIS overall talk: Takahashi (JPS)
    • TYpe-A: Okutomi (JPS)
    • Type-B: Mark (JPS)
    • Type-Bp: Shoda (JPS)
    • Fujii may present his data analysis work at ASJ
  • PR3 accident
    • What happened
      • When the suspension system was put back to the assembly frame, the position and height of the IM was not correct.
      • During the adjustment process of the IM position, the mirror moved too much in roll.
      • The mirror slept out of the wires and hit the mirror box (MB)
      • MB and the recoil mass (RM) moved on the rail by the shock creating a gap between them.
      • The mirror fell in the gap between the MB and RM.
    • What was wrong
      • Mechanism
        • The assembly jigs were designed only with the assembly procedure in mind. Disassembly was not taken into account at the time.
        • Insufficient adjustment mechanism of the IM position.
        • Long rod from the mirror box interfered with the work
        • No slit on one wire breaker
        • Base for the RM is not fixed. RM was not fixed to the base.
        • MB base and the RM base were not connected together.
      • Procedure
        • Did not review the disassembly procedure beforehand.
        • Adjustment of the mirror position should have been done while the mirror is inside the RM.
        • Adjustment of the mirror position took 2 hours. People got tired.
      • Organization
        • There was only one expert in the team. Should have had at least two.
        • The allocated time for the PR3 disassembly was too short.
        • Communicating in English while doing a complicated assembly work was difficult.
        • Needed to take more rest.
    • We will discuss on how to solve the technical problems as well as increase the overall safety of the VIS works in the future at the next meeting.
    • Shoda will write a report on this accident: What happened, What was wrong, and what are we going to do.

Site work plan for the next week

  • Mon:
  • Tue:
  • Wed: BS
  • Thu: BS
  • Fri: BS

Travel Plans

  • Travel (Week of 11/14):
    • Takahashi:
    • Shoda:
    • Mark: 16-18
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata: 16-18
    • Sato:
    • Enzo: 16-18
    • Ohishi:
  • Travel (Week of 11/21):
    • Takahashi: 21 Akeno
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Ohishi:

Next meeting

On 2016/11/18(Fri) in Mitaka

VIS F2F: Nov. 18, Dec. 2