Agenda/Minutes of the VIS Meeting on 2016/11/11
2016/11/11 13:30 -
Participants:
Progress report
Schedule Chart (PDF,MPP) To Be Updated
Type-A (Takahashi)
- Installation: Asking a company the cost and schedule for transportation of Type-A items from the center area to the 2F of Y-end.
- Pre-isolator: Assembly work will be concentrated to the next week. The PI for SRs will be transported on 21st from Akeno. 5 ACCs were measured at the site.
- EQ stop, release sensor, dummy payload: Production is on going.
- BF damper: Open bidding was on 9th. A production company was decided.
- Maraging wire: Asking the company a quotation. The company is checking procurement of the material.
Type B (Mark)
- Please put a report here
Type-Bp (Shoda)
- Please put a report here
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- Please put a report here
Safety
- Any issue ?
Discussion
- JPS/ASJ meetings
Site work plan for the next week
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
Travel Plans
- Travel (Week of 11/14):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Enzo:
- Ohishi:
- Travel (Week of 11/21):
- Takahashi: 21 Akeno
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Enzo:
- Ohishi:
Next meeting
On 2016/11/18(Fri) in Mitaka
VIS F2F: Nov. 18, Dec. 2