Differences between revisions 1 and 3 (spanning 2 versions)
Revision 1 as of 2016-11-15 14:40:54
Size: 1561
Editor: YoichiAso
Comment:
Revision 3 as of 2016-11-17 15:07:31
Size: 2353
Comment:
Deletions are marked like this. Additions are marked like this.
Line 12: Line 12:
 * Put a report here  * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]]
 * Installation: Asking a company the cost and schedule for transportation of Type-A items from the center area to the 2F of Y-end.
 * Pre-isolator: Mechanical assembly of two sets were finished. They will be shipped on 1st December.
  The PI for SRs will be transported on 21st from Akeno.
  6 ACCs were measured at the site.
 * EQ stop, release sensor, dummy payload: Production is on going.
 * BF damper: There was a meeting with the production company on 15th.
 * Maraging wire: Asking the company a quotation. The procurement of material was confirmed.
 * Tooling for installation: Main tools (foothold, chain block, lifer) were ordered. Still asking companies a quotation of the hoist tool.

Agenda/Minutes of the VIS Meeting on 2016/11/18

2016/11/18 13:30 -

Participants:

Progress report

Schedule Chart (PDF,MPP) To Be Updated

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Installation: Asking a company the cost and schedule for transportation of Type-A items from the center area to the 2F of Y-end.
  • Pre-isolator: Mechanical assembly of two sets were finished. They will be shipped on 1st December.
    • The PI for SRs will be transported on 21st from Akeno. 6 ACCs were measured at the site.
  • EQ stop, release sensor, dummy payload: Production is on going.
  • BF damper: There was a meeting with the production company on 15th.
  • Maraging wire: Asking the company a quotation. The procurement of material was confirmed.
  • Tooling for installation: Main tools (foothold, chain block, lifer) were ordered. Still asking companies a quotation of the hoist tool.

Type B (Mark)

  • Put a report here

Type-Bp (Shoda)

  • Put a report here

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Put a report here

Safety

  • Incidents
  • Foreseen risks

Discussion

  • PR3 accident: future actions

Site work plan for the next week

  • Mon:
  • Tue:
  • Wed: BS
  • Thu: BS
  • Fri: BS

Travel Plans

  • Travel (Week of 11/14):
    • Takahashi:
    • Shoda:
    • Mark: 16-18
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata: 16-18
    • Sato:
    • Enzo: 16-18
    • Ohishi:
  • Travel (Week of 11/21):
    • Takahashi: 21 Akeno
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Ohishi:
  • Long term travel plan
    • Takahashi: Dec. -> Mar.

    • Shoda: Dec. -> Mar.

    • Mark: Dec. -> Mar.

    • Fabian: Dec. -> Mar.

    • Okutomi: Dec. -> Mar.

    • Fujii:
    • Ishizaki: Dec. -> Mar.

    • Hirata: Dec. -> Mar.

    • Sato: Dec. -> Mar.

    • Enzo: Dec. -> Mar.

    • Ohishi:

Next meeting

On 2016/11/25(Fri)

VIS F2F: Dec. 2

KAGRA/Subgroups/VIS/VISMinutes20161118 (last edited 2016-11-19 00:40:48 by YoichiAso)