* Put a report here | * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]] * Installation: Transportation of Type-A items was divided to two times. The first transportation is scheduled on 7-9th December. The second one is scheduled in early January. We are asking to modify the piston system for the corn bellows to the company. * Pre-isolator: Two sets will be shipped on 1st December. The PIs for SR were transported on 21st from Akeno. * EQ stop, release sensor, dummy payload: Some parts have been delivered to Kamioka. The parts remained will be delivered on 12th December. * BF damper: The production is on going. * Maraging wire: Asking UT ordering them. One set for the first Type-A system can be delivered by 20th January. * Tooling for installation: Still asking some companies a quotation of the hoist tool. |
Agenda/Minutes of the VIS Meeting on 2016/11/25
2016/11/25 13:30 -
Participants:
Progress report
Schedule Chart (PDF,MPP) To Be Updated
Type-A (Takahashi)
- Installation: Transportation of Type-A items was divided to two times.
- The first transportation is scheduled on 7-9th December. The second one is scheduled in early January. We are asking to modify the piston system for the corn bellows to the company.
- Pre-isolator: Two sets will be shipped on 1st December.
- The PIs for SR were transported on 21st from Akeno.
- EQ stop, release sensor, dummy payload: Some parts have been delivered to Kamioka. The parts remained will be delivered on 12th December.
- BF damper: The production is on going.
- Maraging wire: Asking UT ordering them. One set for the first Type-A system can be delivered by 20th January.
- Tooling for installation: Still asking some companies a quotation of the hoist tool.
Type B (Mark)
- Put a report here
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- Put a report here
Safety
- Incidents
- Foreseen risks
Discussion
- PR3 accident: future actions
- Two ideas for improvement
- Making the long rods shorter
- For the disassembly, fix the mirror in the RM first, then open it and move the mirror to the mirror box.
- Status of consideration (Shoda, Takahashi, Hirata)
- Two ideas for improvement
Site work plan for the next week
- Mon:
- Tue: Power outage preparation/recovery (Aso)
- Wed:
- Thu:
- Fri:
Travel Plans
- Travel (Week of 11/28):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki: 12/1-2 (receive PI)
- Hirata:
- Sato:
- Enzo:
- Ohishi:
- Travel (Week of 12/5):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Enzo:
- Ohishi:
All the teams should update the schedule from Dec. by the next meeting, so that the above travel plans become more realistic.
Next meeting
On 2016/12/2(Fri) F2F in Mitaka