Agenda/Minutes of the VIS Meeting on 2016/12/2
2016/12/2 13:30 -
Participants:
Progress report
Type-A (Takahashi)
- Installation: The first transportation to Y-end for Type-A items is scheduled on 7-9th. The second one is scheduled in early January.
- Pre-isolator: Cable connection and check were finished. Two sets have been shipped on 1st.
- EQ stop, release sensor, dummy payload: The parts remained will be delivered on 12th.
- BF damper: The production is on going.
- Maraging wire: Ordered. The first set will be delivered by 20th January.
- Tooling for installation: The hoist tool was ordered.
Type B (Mark)
- Put a report here
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- Schedule
- Most of the parts will be assembled and delivered to Kamioka on 28th Dec
- (I will be taking winter holiday on 28th but I think I can chek it on 30th Dec.).
- It depend on the mirror and jig status, but I think the mirror will be hung
- without magnets/standoff for initial alignment planned in January.
- Hanging and installation will start from 4th January.
- Two people from FCL are coming for hanging and installation till 12th January.
- Most of the parts will be assembled and delivered to Kamioka on 28th Dec
- Mirror
- Have not contacted with Hirose-san.
- Magnet and standoff fixture jig
- Perhaps still in Kashiwa.
- Need at least two new parts and two sims for different thickness of the mirror.
- Hanging jig
- Now in Mitaka.
- Drawings
- Dropbox.
- Remaining parts status
- PZT holder
- Hanging and Installation Procedure:
- Inside the IFI chamber, there already is set large IFI;
- it is so crowded and seems to be difficult installing IMMT suspension from the side flange.
- We are planning to install IMMT2 from the top flange.
- Need discussion with Hirose-san about cleanliness control.
- IMMTs are not on the center line where cranes move.
- So perhaps we need to move IMMT by hand after we install it from the top flange.
- Inside the IFI chamber, there already is set large IFI;
- Place for hanging:
- Unfortunately I could not have find breadboard legs.
- Ask Kawamura-san if I can use small optical table that was used at MC recently replaced with larger optical bench.
- Cables:
- For initial alignment, planned in January, I think only Pico-motors will be necessary.
- (Coils will not be used for initial alignment.)
- There already cables used when it was used for iKAGRA ETMs.
- Check the place where cables are now.
- For initial alignment, planned in January, I think only Pico-motors will be necessary.
- Digital models
- Have not prepared yet.
- IMMT picomotor drivers are located in Mozumi now.
- Ask Miyo-san for preparation.
- Others
- Japan Tungsten Company will give us sample of wires.
Watchdog system (Tanaka)
- Put a report here
Safety
- Incidents:
- Foreseen risks:
Discussion
- Mirror box modification
Site work plan for the next week
- Mon: BS
- Tue: BS
- Wed: BS/Type-A transportation
- Thu: BS/Type-A transportation
- Fri: BS/Type-A transportation
Travel Plans
- Travel (Week of 12/5):
- Takahashi: 12/6-12/9
- Shoda:
- Mark: 12/5-12/9
- Fabian: 12/5-12/9
- Okutomi:
- Fujii:
- Ishizaki: 12/6-12/9
- Hirata:
- Sato:
- Enzo: 12/5-12/9
- Ohishi:
- Travel (Week of 12/12):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Enzo:
- Ohishi:
Next meeting
On 2016/12/9(Fri)