6892
Comment:
|
← Revision 55 as of 2016-12-02 18:47:27 ⇥
8377
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
Participants: | Participants: Hirata, Takahashi, Okutomi, Shoda, Sato, Tanaka, Fujii, Enzo, Mark, Fabian, Aso, Raffaele, Akutsu |
Line 29: | Line 29: |
* '''Need to order geophones immediately (Takahashi)''' |
|
Line 41: | Line 43: |
* PR3 will be returned to Mitaka today. Need to transport it to Kashiwa. |
|
Line 51: | Line 55: |
without magnets/standoff for initial alignment scheduled in January. | without magnets/standoff for initial alignment scheduled in January (Need to be confirmed). * '''We need to suspend the mirrors with magnets and standoffs. Will arrange with Hirose-san for the gluing work (Aso)''' |
Line 56: | Line 61: |
* Need to contacted with Hirose-san about the time when the mirrors are prepared. | * Need to contacted with Hirose-san: |
Line 71: | Line 76: |
* Dropbox. | * will be uploaded to dropbox. |
Line 74: | Line 79: |
* PZT holder: ask FCL to make quotation. | * PZT holder: asked FCL to make quotation. |
Line 76: | Line 81: |
* D-sub holders; We had two but now one of it was used for MCo. | * D-sub holders; We had two holders but now one of it was used for MCo. |
Line 88: | Line 93: |
* Unfortunately I could not have find breadboard legs. | * Unfortunately I could not have find breadboard(GIF) legs. |
Line 92: | Line 97: |
* For initial alignment, planned in January, I think only Pico-motors will be necessary. (Coils will not be used for initial alignment.) |
* For initial alignment, planned in January, I think only Pico-motors will be necessary. (Need to be confirmed; Coils will not be used for initial alignment.) |
Line 110: | Line 115: |
* Put a report here | * Test on the central power supply shows that the regulator chip is over heated. * Preparing a test for a smaller power supply circuit put on each WD board. |
Line 116: | Line 122: |
* BS: will avoid any dangerous work because there will be only two people * Type-A transportation: Carefully watch the company workers. Insist to handle the items carefully. |
|
Line 120: | Line 128: |
* Shoda-san showed the current design. Basically the design seems OK. * The modification of the mirror box (shorten the rods and modify the lids) is difficult to do quickly because mirrors are already in the boxes. * We will postpone the modification of the mirror box to after the test hanging is started * Other modifications (tying the sliders together, adding pulling screws to the RM base and adding fixing screws for the RM) will be performed before the test hanging starts. * '''Mark will send the RM base parts from Kamioka on Monday. Shoda-san will send Mark details of what to look for where'''. |
|
Line 133: | Line 147: |
* Shoda: | * Shoda: 12/7-12/8 f2f, 12/9 Kashiwa |
Line 136: | Line 150: |
* Okutomi: * Fujii: |
* Okutomi: 12/7-12/8 f2f * Fujii: 12/7-12/8 f2f |
Line 142: | Line 156: |
* Ohishi: | * Ohishi: 12/5-12/6 Hongo |
Line 146: | Line 160: |
* Shoda: | * Shoda: 12/12-13 Assembly frame, 12/15 or 16 (Kashiwa) |
Line 150: | Line 164: |
* Fujii: | * Fujii: 12/15 or 16 (Kashiwa) |
Line 154: | Line 168: |
* Enzo: 12/12-12/16 (for Type B) | * Enzo: 12/12-12/16 (for Type B ) |
Agenda/Minutes of the VIS Meeting on 2016/12/2
2016/12/2 13:30 -
Participants: Hirata, Takahashi, Okutomi, Shoda, Sato, Tanaka, Fujii, Enzo, Mark, Fabian, Aso, Raffaele, Akutsu
Progress report
Type-A (Takahashi)
- Installation: The first transportation to Y-end for Type-A items is scheduled on 7-9th. The second one is scheduled in early January.
- Pre-isolator: Cable connection and check were finished. Two sets have been shipped on 1st.
- EQ stop, release sensor, dummy payload: The parts remained will be delivered on 12th.
- BF damper: The production is on going.
- Maraging wire: Ordered. The first set will be delivered by 20th January.
- Tooling for installation: The hoist tool was ordered.
Type B (Mark)
- Mark worked on task lists and schedule.
Mark worked on an update of the BS Electronic Items doc (E1505111) and started a SRx Electronics Items doc (E1605886).
- Mark did a summary spreadsheet of Takahashi-san's cable orders to see what needed to be ordered immediately (new BS TM OSEM cables; geophone adapters) and later (for SRx).
Mark worked on an update of the In-Vacuum Cable doc (E1503901), including information on final lengths that Fabian and Hirata-san had decided when making adapter cables.
Mark considered an alternative cabling scheme for the geophones (with a different adapter cable to put the signals and power on different lines and a matching unscrambler) but ended up concluding that the existing design would probably be OK. See 00 Revised Geophone-v2.PDF.
- Fabian worked on a redesign of the EQ stops for the BS (2 of 4 screws under the RM are opposite large holes and there are no screws to restrain the RM front/back at either top or bottom).
- Hirata-san worked on PR/SR mirror box modifications with Shoda-san (on-going).
- Hirata-san partially assembled a bottom filter for use in fit tests of the PRx BF recoil mass.
Need to order geophones immediately (Takahashi)
Type-Bp (Shoda)
- Installation preperation
Flag removing is postponed because we found that some of the parts are required to be re-manufactured.
- We will try again at 9th Dec.
- New assembly frame will be constructed on 12th and 13th Dec.
- Flag/Wire breaker glueing will be done on 15th and 16th Dec.
- Hopefully, the mirror will be sent to Kamioka on 19th and we can start hanging from 20th Dec. (19th is extended chief MTG.)
- Design
- For the installation of the main suspension chain, a clean chain block is ordered. Pararelly, removable jacks on the inner frame is being prepared.
- 3D design of the mirror box modification is almost done. 2D drawings have to be prepared.
- PR3 will be returned to Mitaka today. Need to transport it to Kashiwa.
IMMT (Ohishi)
- Schedule
- Most of the parts will be assembled and delivered to Kamioka on 28th Dec.
- Dec 20th:Processing completion
- Dec 21th-22th:Assembly
- Dec 26th :Optional extra day
- Dec 27th:Shipping
- It depends on the mirror and jig status, but I think the mirror will be hung
- without magnets/standoff for initial alignment scheduled in January (Need to be confirmed).
We need to suspend the mirrors with magnets and standoffs. Will arrange with Hirose-san for the gluing work (Aso)
- Hanging and installation will start from 4th January.
- Two people from FCL are coming for hanging and installation till 12th January.
- Most of the parts will be assembled and delivered to Kamioka on 28th Dec.
- Mirror
- Need to contacted with Hirose-san:
- IMMT1:
- Ø: 99.77 mm; Thickness at thinnest point: 51.76 mm; Wedge: 2.45°
- IMMT2:
- Ø: 99.75 mm; Thickness at thinnest point: 52.93 mm; Wedge: 2.45°
- Thickness of the mirrors are 1.17mm different.
- IMMT1:
- Need to contacted with Hirose-san:
- Magnet and standoff fixture jig
- Plan to modify MC jig
- MC jig: perhaps still in Kashiwa.
- Need at least two new parts and two sims for different thickness of the mirror.
- Hanging jig
- Now in Mitaka. Will be delivered to Kamioka by Tatsumi-san.
- Drawings
- will be uploaded to dropbox.
- Remaining parts status
- PZT holder: asked FCL to make quotation.
- coil holders: drawings exist. need to check before ordering.
- D-sub holders; We had two holders but now one of it was used for MCo.
- Need to make another one.
- Hanging and Installation Procedure:
- Because it is difficult to install IMMT2 from side flange,
- we are planning to install IMMT2 from the top flange.
- Need discussion with Hirose-san about cleanliness control.
- IMMTs are not on the center line where crane moves.
- So perhaps we need to move IMMT by hand after we install it from the top flange.
- Prepare hanging and installation manual next week.
- Because it is difficult to install IMMT2 from side flange,
- Place for hanging:
- Unfortunately I could not have find breadboard(GIF) legs.
- Ask Kawamura-san if I can use small optical table that was used at MC recently replaced with larger optical bench.
- Cables:
- For initial alignment, planned in January, I think only Pico-motors will be necessary. (Need to be confirmed; Coils will not be used for initial alignment.)
- There already cables used when it was used for iKAGRA ETMs.
- Check the place where cables are now; flippers are in branch office.
- Check Flange
- Digital models
- Have not prepared yet.
- IMMT picomotor drivers are located in Mozumi now.
- Miyo-san said he already setup IP for IMMT drivers and will prepare network port in IOO rack next next week.
- Others
- Nippon Tungsten Company will give us sample of wires.
- Pushers: Ask MIF to prepare it.
- IMMT2 frame were modified to secure +/-1cm range for pico-motor.
- However, IMMT1 frame were not modified so the range is +/-5mm (originally).
Watchdog system (Tanaka)
- Test on the central power supply shows that the regulator chip is over heated.
- Preparing a test for a smaller power supply circuit put on each WD board.
Safety
- Incidents:
- Foreseen risks:
- BS: will avoid any dangerous work because there will be only two people
- Type-A transportation: Carefully watch the company workers. Insist to handle the items carefully.
Discussion
- Mirror box modification
- Shoda-san showed the current design. Basically the design seems OK.
- The modification of the mirror box (shorten the rods and modify the lids) is difficult to do quickly because mirrors are already in the boxes.
- We will postpone the modification of the mirror box to after the test hanging is started
- Other modifications (tying the sliders together, adding pulling screws to the RM base and adding fixing screws for the RM) will be performed before the test hanging starts.
Mark will send the RM base parts from Kamioka on Monday. Shoda-san will send Mark details of what to look for where.
Site work plan for the next week
- Mon: BS
- Tue: BS
- Wed: BS/Type-A transportation
- Thu: BS/Type-A transportation
- Fri: BS/Type-A transportation
Travel Plans
- Travel (Week of 12/5):
- Takahashi: 12/6-12/9
- Shoda: 12/7-12/8 f2f, 12/9 Kashiwa
- Mark: 12/5-12/9
- Fabian: 12/5-12/9
- Okutomi: 12/7-12/8 f2f
- Fujii: 12/7-12/8 f2f
- Ishizaki: 12/6-12/9
- Hirata:
- Sato:
- Enzo: 12/7-12/8 f2f (Hongo)
- Ohishi: 12/5-12/6 Hongo
- Travel (Week of 12/12):
- Takahashi:
- Shoda: 12/12-13 Assembly frame, 12/15 or 16 (Kashiwa)
- Mark: 12/12-12/16 (depending on BS vs SRx progress)
- Fabian: 12/12-12/16
- Okutomi:
- Fujii: 12/15 or 16 (Kashiwa)
- Ishizaki:
- Hirata:
- Sato:
- Enzo: 12/12-12/16 (for Type B )
- Ohishi:
Next meeting
On 2016/12/9(Fri)