Differences between revisions 1 and 10 (spanning 9 versions)
Revision 1 as of 2016-12-26 13:29:43
Size: 1375
Editor: YoichiAso
Comment:
Revision 10 as of 2017-01-06 13:14:23
Size: 3343
Editor: KokiOkutomi
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
 * Put a report here  * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]]
 * Transportation: The second transportation for EQ stop parts and tools is scheduled in 10-11th from Mitaka to Kamioka by Kamoshida, on 12th to Y-end by Kamioka-kogyo, and on 13th to 2F by MESCO.
 * EYV chamber: The top chamber was connected on 20th in December. Two cross tubes were assembled too. The piston system was modified, so cone bellows were not necessary. We started pump down the EYV system on 21st in December.
 * Pre-isolator: The assembly of two pre-isolators for SR were almost finished in ATC. The boxes are necessary for packing.
 * EQ stop, release sensor, dummy payload: Delivered parts were checked on 21st and 22nd in December.
 * BF damper: The production is on going.
 * Maraging wire: The production is on going.
 * Tooling for installation: The fiber scope was ordered. The items were packed on 4th to ship.
Line 17: Line 24:
 * Put a report here  * Mirror gluing jig was found in TAMA experiment room.
 * Shoda made [[https://www.dropbox.com/s/ub7nmc8i4pj607i/PRs_inventory.xlsx?dl=0|PR inventory file]] and gathered some information.
  Parts for the first set is ready except for the new parts.
  Some of the 2nd set should be checked, especially screws, IRM, and EQ stops.
  Also I found that some of the 3rd and 4th IM parts are missing.
 * Asking a cost estimate for flag base modification and additional 1 set. Then we will have 6 sets of flag assemblies and 1 set for test hanging without grooves. now waiting for a reply.

 * '''Next week task.''' Goal: Hang the spare mirror
  * Glue the flags and wire breakers on the mirror (Tue.)
  * Inventory update (Tue. & Wed.)
  * Start mirror hanging (Wed.-Fri.)

 * '''To do'''
  * Check the number of screws and parts we need, not only for PR3 but also for all the suspensions.
  * Inventory update
  * Establish the payload disassembly procedure.
  * Buy gluing tools for KAGRA use.
Line 33: Line 56:
 * How to keep track of items
Line 37: Line 61:
 * Tue:
 * Wed:
 * Thu:
 * Fri:
 * Tue: Gluing(PR3)
 * Wed: Inventory update, Mirror hanging(PR3)
 * Thu: Mirror hanging(PR3)
 * Fri: Mirror hanging, RM inserting?(PR3)
Line 44: Line 68:
 * Travel (Week of 1/9):
  * Takahashi: 10-13
  * Shoda: 10-13
  * Mark:
  * Fabian:
  * Okutomi: 10-13
  * Fujii:
  * Ishizaki:
  * Hirata:
  * Sato: 10-13
  * Enzo: 10-13
  * Ohishi:
Line 47: Line 83:
  * Shoda:   * Shoda: 16-20
Line 50: Line 86:
  * Okutomi: 19-22 (Ext. Cheif Meeting/PR3 test hanging)   * Okutomi: 16-20
Line 52: Line 88:
  * Ishizaki: 20-22 (PI install)   * Ishizaki:
Line 55: Line 91:
  * Enzo: 20-22 (PR3 test hanging)
  * Ohishi: 19 (Kashiwa)

 * Travel (Week of 12/26):
  * Takahashi:
  * Shoda: 26-28
  * Mark:
  * Fabian:
  * Okutomi: 26-28
  * Fujii:
  * Ishizaki:
  * Hirata:
  * Sato:
  * Enzo: 26-28
  * Enzo:
Line 72: Line 95:
On 2017/1/6(Fri) On 2017/1/13(Fri)

Agenda/Minutes of the VIS Meeting on 2017/1/6

2017/1/6 13:30 -

Participants:

Progress report

Schedule Chart (PDF,MPP) (To Be Updated)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Transportation: The second transportation for EQ stop parts and tools is scheduled in 10-11th from Mitaka to Kamioka by Kamoshida, on 12th to Y-end by Kamioka-kogyo, and on 13th to 2F by MESCO.
  • EYV chamber: The top chamber was connected on 20th in December. Two cross tubes were assembled too. The piston system was modified, so cone bellows were not necessary. We started pump down the EYV system on 21st in December.
  • Pre-isolator: The assembly of two pre-isolators for SR were almost finished in ATC. The boxes are necessary for packing.
  • EQ stop, release sensor, dummy payload: Delivered parts were checked on 21st and 22nd in December.
  • BF damper: The production is on going.
  • Maraging wire: The production is on going.
  • Tooling for installation: The fiber scope was ordered. The items were packed on 4th to ship.

Type B (Mark)

  • Put a report here

Type-Bp (Shoda)

  • Mirror gluing jig was found in TAMA experiment room.
  • Shoda made PR inventory file and gathered some information.

    • Parts for the first set is ready except for the new parts. Some of the 2nd set should be checked, especially screws, IRM, and EQ stops. Also I found that some of the 3rd and 4th IM parts are missing.
  • Asking a cost estimate for flag base modification and additional 1 set. Then we will have 6 sets of flag assemblies and 1 set for test hanging without grooves. now waiting for a reply.
  • Next week task. Goal: Hang the spare mirror

    • Glue the flags and wire breakers on the mirror (Tue.)
    • Inventory update (Tue. & Wed.)

    • Start mirror hanging (Wed.-Fri.)
  • To do

    • Check the number of screws and parts we need, not only for PR3 but also for all the suspensions.
    • Inventory update
    • Establish the payload disassembly procedure.
    • Buy gluing tools for KAGRA use.

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Put a report here

Safety

  • Incidents:
  • Foreseen risks

Discussion

  • How to track design changes ?
  • How to keep track of items
  • Smaller coils/magnet bases (Aso)

Site work plan for the next week

  • Mon:
  • Tue: Gluing(PR3)
  • Wed: Inventory update, Mirror hanging(PR3)
  • Thu: Mirror hanging(PR3)
  • Fri: Mirror hanging, RM inserting?(PR3)

Travel Plans

  • Travel (Week of 1/9):
    • Takahashi: 10-13
    • Shoda: 10-13
    • Mark:
    • Fabian:
    • Okutomi: 10-13
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato: 10-13
    • Enzo: 10-13
    • Ohishi:
  • Travel (Week of 1/16):
    • Takahashi:
    • Shoda: 16-20
    • Mark:
    • Fabian:
    • Okutomi: 16-20
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Ohishi:

Next meeting

On 2017/1/13(Fri)