Line 93: Line 93:
 * Tue: Gluing(PR3)
 * Wed: Inventory update, Mirror hanging(PR3)
 * Thu: Mirror hanging(PR3)
 * Fri: Mirror hanging, RM inserting?(PR3)
 * Tue: Gluing(PR3); inspection of BF by Takahishi-san, adjustment of IM and IRM (BS)
 * Wed: Inventory update, mirror hanging (PR3); TFs from IRM OSEMs to IM and IRM (BS)
 * Thu: Mirror hanging (PR3); cabling, testing of BF LVDT and fishing rod (BS)
 * Fri: Mirror hanging, RM inserting? (PR3); removal/packing/shipping of BF (BS)
Line 103: Line 103:
  * Mark:
  * Fabian:  
  * Mark: 10-13
  * Fabian: 10-13
Line 116: Line 116:
  * Mark:
  * Fabian:  
  * Mark: 16-20?
  * Fabian: 16-20?

Agenda/Minutes of the VIS Meeting on 2017/1/6

2017/1/6 13:30 -

Participants:

Progress report

Schedule Chart (PDF,MPP) (To Be Updated)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Transportation: The second transportation for EQ stop parts and tools is scheduled in 10-11th from Mitaka to Kamioka by Kamoshida, on 12th to Y-end by Kamioka-kogyo, and on 13th to 2F by MESCO.
  • EYV chamber: The top chamber was connected on 20th in December. Two cross tubes were assembled too. The piston system was modified, so cone bellows were not necessary. We started pump down the EYV system on 21st in December.
  • Pre-isolator: The assembly of two pre-isolators for SR were almost finished in ATC. The boxes are necessary for packing.
  • EQ stop, release sensor, dummy payload: Delivered parts were checked on 21st and 22nd in December.
  • BF damper: The production is on going.
  • Maraging wire: The production is on going.
  • Tooling for installation: The fiber scope was ordered. The items were packed on 4th to ship.

Type B (Mark)

  • Activity report for weeks of 12/26 and 1/2
    • Hirata-san:
      • Modified parts list and screw list for payload.
      • Sent lists to i-ject and asked for preliminary quotes.
      • Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps).
      • For Type Bp:
        • Searched for PR gluing jigs.
        • Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
        • Washed additional masses for IM and sent them to Kamioka.
      • For others:
        • Washed IMMT plate and sent them to Kamioka.
    • Fabian
      • Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one).
      • Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version.
      • Worked on design of additional trim mass (≈18 kg) for the BS BF.
      • Checked assembly PR/SR drawings. There were a few corrections/changes.
      • Checked fastener list. There were few corrections/changes.
      • Checked component list for the manufacture order. There were few corrections/changes.
      • Helped in searching for the PR gluing jigs.
    • Mark
      • Started design of SR assembly frame (but then passed it to Fabian).
      • Worked on task lists and schedule.
  • Plan for 1/10-13
    • Mark and Fabian at Kamioka (Enzo not available):
      • Finish rebalance of IM
      • Reinstall IRM, adjust OSEMs
      • Replace broken Type 3 cable.
      • Do TFs from IRM OSEMs to IRM and IM OSEMs.
      • Cable up and test BF LVDT and fishing rod (time permitting).
      • Disconnect BF and ship back to Mitaka (time permitting).
    • Hirata-san:
      • More SR procurement.

Type-Bp (Shoda)

  • Mirror gluing jig was found in TAMA experiment room.
  • Shoda made PR inventory file and gathered some information.

    • Parts for the first set is ready except for the new parts. Some of the 2nd set should be checked, especially screws, IRM, and EQ stops. Also I found that some of the 3rd and 4th IM parts are missing.
  • Asking a cost estimate for flag base modification and additional 1 set. Then we will have 6 sets of flag assemblies and 1 set for test hanging without grooves. now waiting for a reply.
  • Next week task. Goal: Hang the spare mirror

    • Glue the flags and wire breakers on the mirror (Tue.)
    • Inventory update (Tue. & Wed.)

    • Start mirror hanging (Wed.-Fri.)
  • To do

    • Check the number of screws and parts we need, not only for PR3 but also for all the suspensions.
    • Inventory update
    • Establish the payload disassembly procedure.
    • Buy gluing tools for KAGRA use.

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Put a report here

Safety

  • Incidents:
  • Foreseen risks

Discussion

  • How to track design changes ?
  • How to keep track of items
  • Smaller coils/magnet bases (Aso)

Site work plan for the next week

  • Mon:
  • Tue: Gluing(PR3); inspection of BF by Takahishi-san, adjustment of IM and IRM (BS)
  • Wed: Inventory update, mirror hanging (PR3); TFs from IRM OSEMs to IM and IRM (BS)
  • Thu: Mirror hanging (PR3); cabling, testing of BF LVDT and fishing rod (BS)
  • Fri: Mirror hanging, RM inserting? (PR3); removal/packing/shipping of BF (BS)

Travel Plans

  • Travel (Week of 1/9):
    • Takahashi: 10-13
    • Shoda: 10-13
    • Mark: 10-13
    • Fabian: 10-13
    • Okutomi: 10-13
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato: 10-13
    • Enzo: 10-13
    • Ohishi:
  • Travel (Week of 1/16):
    • Takahashi:
    • Shoda: 16-20
    • Mark: 16-20?
    • Fabian: 16-20?
    • Okutomi: 16-20
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Ohishi:

Next meeting

On 2017/1/13(Fri)