Size: 2111
Comment:
|
← Revision 15 as of 2017-01-27 20:06:09 ⇥
Size: 6009
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
Participants: | Participants: Tanaka, Mark, Sato, Ishizaki, Fabian, Hirata, Okutomi, Shoda, Enzo, Someya, Hashimoto, Akutsu |
Line 15: | Line 15: |
* Maraging wire: The wires are delivered on 31st. They are sent to the thermal proccess on 1st February. | * Maraging wire: The wires are delivered on 31st. They are sent to the thermal proccess on 1st February. To be shipped to Kamioka on Feb. 7th. |
Line 20: | Line 20: |
Next Week Plan * BF damping pre-assembly * Open the top chamber. * Set the assembly base. * Sato-san will stay in Mitaka to send the delivered rods to the heat treatment. Also incorporate cables into the Type-A CAD model. |
|
Line 21: | Line 29: |
* Put a report here | * Hirata-san: * Received many parts from i-ject for BFRM (took pictures and took them into ATC cleanroom). * Got quotes for PRM/SRM payload from i-ject. * Checked quotes and asked for some modifications.) * Washed parts (parts for type-A, small hexagons, screws, etc\) * Wiped 9 piano wires and sent to Kamioka for PR. * Updated Fabian's EQstop parts for BS recoilmass and updated EQstop assy drawings. * Fabian * Worked out geometry for blade adjustment. * Designed additional ballast masses for BS BF (and SR). * Mark and Enzo (at Kamioka) * Did two rounds of adjustment of the blades with help from Takahashi-san (one for position, one for frequency) * Surveyed the position of the rod using the vertical mode of the bubble level. * Got apparent improvement as judged at the IRM-IM EQ stops (but still not perfect). * Did one more round of blade adjustments (without Takahashi-san) * Got good agreement with IRM-IM EQ stops, so put BF cap on and raised the whole system to check for balance. * Found balance still fairly bad: about the same on the -X,+Y diagonal and about half on the +X,+Y diagonal (70 and 30 mm worth of motion of a single trim mass respectively; previous a bit over 70 mm each). Moreover, IRM-IM alignment no longer good. * From the imbalance torques, calculated the offset of rod as 2.3 mm in the direction 22 degrees to the +X side of -Y. * Calculated the blade adjustments required: {-0.325194, -1.79175, 2.11695} mm * Prepared to apply adjustments (removed cap etc). === Type-Bp (Shoda) === * '''Hanging Report''': TF measured, BF has been set. * EQ stop parts below the BF were assembled. * We measured TFs of RM using PSs. (Their alignment was not so easy.) * BF was placed on the EQ stop. (Traverser was moved out of the clean room for accesibility.) * BF and IM was connected. Not hanged yet. * BFRM parts were delivered. * Test assemble them in Mitaka on Feb. 2nd. |
Line 23: | Line 58: |
=== Type-Bp (Shoda) === * Put a report here |
* '''Next week task''': Hang IRM * Hang IM and adjust the weight. * Hang IRM and balance IM. * IRM and set OSEMs. |
Line 26: | Line 63: |
* A mirror box was sent to a company for modification * Flag bases were sent to a company for modification * Winch were sent to Mitaka for inspection * '''To do''' * Establish disassemble procedure * Buy the new tools |
|
Line 27: | Line 71: |
* Put a report here | * Last week we put IMMT mirrors in suspension. * This week, we have adjusted the mirror position and angle to be the same as old ones. * Beam profile measurement, which aims at adjusting the mirror position, was postponed to next week. |
Line 30: | Line 76: |
* Put a report here | * WDS PCB Design Document.Main rack( Main board + peripheral board )design. *Correction of PCB design and correction by DRC(by manufacturer).[[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0061/E1706101/001/Project%20WDS%20PCB%20Design%20Ver1%28Detail%29170127.pdf|PDF(JGW-E1706101)]] |
Line 33: | Line 80: |
* Incidents: | * Incidents: cut finger with a stainless steel sheet * We need to wear globes for this kind of work Type-A: Type-B: Crane work to lift the BF up. Type-Bp: No heavy lifting. Mirror does not move. |
Line 36: | Line 89: |
* Type-A: * Type-B: * Type-Bp: |
* Type-A: Open the top chamber (a crane work). * Type-B: Crane work to lift the BF up. * Type-Bp: No heavy lifting. Mirror does not move. |
Line 43: | Line 96: |
* We will use the same PEEK (Ketron CA30). This material was chosen to avoid charging. | |
Line 45: | Line 99: |
* Mon: * Tue: * Wed: * Thu: * Fri: |
* Mon: BF blade adjustment (B)/Hang IM(Bp) * Tue: BF damper pre-assembly (A)/BF blade adjustment (B)/Assemble IMRM (Bp) * Wed: BF damper pre-assembly (A)/BF blade adjustment (B)/Assemble IMRM (Bp), Delivery of the parts for optical bench (Bp) * Thu: Open the chamber (A)/BF blade adjustment (B) * Fri: Set up assembly frame (A)/BF blade adjustment (B) |
Line 54: | Line 108: |
* Takahashi: 30-2/3 * Shoda: 31-2/3 |
* Takahashi: 31-2/3 * Shoda: 30-2/1 |
Line 57: | Line 111: |
* Fabian: | * Fabian: 30-2/3 |
Line 59: | Line 113: |
* Fujii: * Ishizaki: 30-2/3 |
* Fujii: * Ishizaki: 31-2/3 |
Line 62: | Line 116: |
* Sato: 30-2/3 | * Sato: |
Line 64: | Line 118: |
* Hashimoto (Hosei Univ.): * Someya (Hosei Univ.): |
* Hashimoto (Hosei Univ.): 30-2/1 * Someya (Hosei Univ.):30-2/1 |
Line 69: | Line 123: |
* Takahashi: * Shoda: * Mark: * Fabian: * Okutomi: |
* Takahashi: 6-10 * Shoda: 6-10 * Mark: 6-10 * Fabian: 6-10 * Okutomi: 6-10 |
Line 75: | Line 129: |
* Ishizaki: * Hirata: * Sato: * Enzo: * Hashimoto (Hosei Univ.): * Someya (Hosei Univ.): |
* Ishizaki: 6-10 * Hirata: 6-10 * Sato: 6-10 * Enzo: 6-10 * Hashimoto (Hosei Univ.): 6-10 * Someya (Hosei Univ.): 6-10 |
Line 86: | Line 140: |
March VIS F2F: March 10 ? |
Agenda/Minutes of the VIS Meeting on 2017/1/27
2017/1/27 13:30 -
Participants: Tanaka, Mark, Sato, Ishizaki, Fabian, Hirata, Okutomi, Shoda, Enzo, Someya, Hashimoto, Akutsu
Progress report
Type-A (Takahashi)
- EYV chamber: Top chamber was connected again.
- Pre-isolator: The pre-isolators for SR were packed and moved out of the large clean room on 23rd.
- BF damper: Checked delivered parts on 24th.
- Maraging wire: The wires are delivered on 31st. They are sent to the thermal proccess on 1st February. To be shipped to Kamioka on Feb. 7th.
- The 3.3m wire can be treated at Himeji facility of Kinzoku-giken.
- Preparation of installation: The floor of clean booth was covered by stainless steel sheet. The foot holds were assembled.
- Other large tools (rack, wagon, desk, so on) also were installed into the clean booth.
- BF damping pre-assembly
- Open the top chamber.
- Set the assembly base.
- Sato-san will stay in Mitaka to send the delivered rods to the heat treatment. Also incorporate cables into the Type-A CAD model.
Type B (Mark)
- Hirata-san:
- Received many parts from i-ject for BFRM (took pictures and took them into ATC cleanroom).
- Got quotes for PRM/SRM payload from i-ject.
- Checked quotes and asked for some modifications.)
- Washed parts (parts for type-A, small hexagons, screws, etc\)
- Wiped 9 piano wires and sent to Kamioka for PR.
- Updated Fabian's EQstop parts for BS recoilmass and updated EQstop assy drawings.
- Fabian
- Worked out geometry for blade adjustment.
- Designed additional ballast masses for BS BF (and SR).
- Mark and Enzo (at Kamioka)
- Did two rounds of adjustment of the blades with help from Takahashi-san (one for position, one for frequency)
- Surveyed the position of the rod using the vertical mode of the bubble level.
- Got apparent improvement as judged at the IRM-IM EQ stops (but still not perfect).
- Did one more round of blade adjustments (without Takahashi-san)
- Got good agreement with IRM-IM EQ stops, so put BF cap on and raised the whole system to check for balance.
- Found balance still fairly bad: about the same on the -X,+Y diagonal and about half on the +X,+Y diagonal (70 and 30 mm worth of motion of a single trim mass respectively; previous a bit over 70 mm each). Moreover, IRM-IM alignment no longer good.
- From the imbalance torques, calculated the offset of rod as 2.3 mm in the direction 22 degrees to the +X side of -Y.
- Calculated the blade adjustments required: {-0.325194, -1.79175, 2.11695} mm
- Prepared to apply adjustments (removed cap etc).
Type-Bp (Shoda)
Hanging Report: TF measured, BF has been set.
- EQ stop parts below the BF were assembled.
- We measured TFs of RM using PSs. (Their alignment was not so easy.)
- BF was placed on the EQ stop. (Traverser was moved out of the clean room for accesibility.)
- BF and IM was connected. Not hanged yet.
- BFRM parts were delivered.
- Test assemble them in Mitaka on Feb. 2nd.
Next week task: Hang IRM
- Hang IM and adjust the weight.
- Hang IRM and balance IM.
- IRM and set OSEMs.
- A mirror box was sent to a company for modification
- Flag bases were sent to a company for modification
- Winch were sent to Mitaka for inspection
To do
- Establish disassemble procedure
- Buy the new tools
IMMT (Ohishi)
- Last week we put IMMT mirrors in suspension.
- This week, we have adjusted the mirror position and angle to be the same as old ones.
- Beam profile measurement, which aims at adjusting the mirror position, was postponed to next week.
Watchdog system (Tanaka)
- WDS PCB Design Document.Main rack( Main board + peripheral board )design.
Correction of PCB design and correction by DRC(by manufacturer).PDF(JGW-E1706101)
Safety
- Incidents: cut finger with a stainless steel sheet
- We need to wear globes for this kind of work
Type-A: Type-B: Crane work to lift the BF up. Type-Bp: No heavy lifting. Mirror does not move.
- Foreseen risks
- Type-A: Open the top chamber (a crane work).
- Type-B: Crane work to lift the BF up.
- Type-Bp: No heavy lifting. Mirror does not move.
Discussion
- Smaller coil design status update (Aso)
- We will use the same PEEK (Ketron CA30). This material was chosen to avoid charging.
Site work plan for the next week
- Mon: BF blade adjustment (B)/Hang IM(Bp)
- Tue: BF damper pre-assembly (A)/BF blade adjustment (B)/Assemble IMRM (Bp)
- Wed: BF damper pre-assembly (A)/BF blade adjustment (B)/Assemble IMRM (Bp), Delivery of the parts for optical bench (Bp)
- Thu: Open the chamber (A)/BF blade adjustment (B)
- Fri: Set up assembly frame (A)/BF blade adjustment (B)
Travel Plans
- Travel (Week of 1/30):
- Takahashi: 31-2/3
- Shoda: 30-2/1
- Mark: 30-2/3
- Fabian: 30-2/3
- Okutomi: 30-2/3
- Fujii:
- Ishizaki: 31-2/3
- Hirata:
- Sato:
- Enzo: 30-2/3
- Hashimoto (Hosei Univ.): 30-2/1
- Someya (Hosei Univ.):30-2/1
- Ohishi:
- Travel (Week of 2/6):
- Takahashi: 6-10
- Shoda: 6-10
- Mark: 6-10
- Fabian: 6-10
- Okutomi: 6-10
- Fujii:
- Ishizaki: 6-10
- Hirata: 6-10
- Sato: 6-10
- Enzo: 6-10
- Hashimoto (Hosei Univ.): 6-10
- Someya (Hosei Univ.): 6-10
- Ohishi:
Next meeting
On 2017/2/3(Fri) VIS F2F: Feb. 17th March VIS F2F: March 10 ?