Agenda/Minutes of the VIS Meeting on 2017/1/27
2017/1/27 13:30 -
Participants:
Progress report
Type-A (Takahashi)
- EYV chamber: Top chamber was connected again.
- Pre-isolator: The pre-isolators for SR were packed and moved out of the large clean room on 23rd.
- BF damper: Checked delivered parts on 24th.
- Maraging wire: The wires are delivered on 31st. They are sent to the thermal proccess on 1st February.
- The 3.3m wire can be treated at Himeji facility of Kinzoku-giken.
- Preparation of installation: The floor of clean booth was covered by stainless steel sheet. The foot holds were assembled.
- Other large tools (rack, wagon, desk, so on) also were installed into the clean booth.
Type B (Mark)
- Put a report here
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- WDS PCB Design Document.Main rack( Main board + peripheral board )design.
Correction of PCB design and correction by DRC(by manufacturer).PDF(JGW-E1706101)
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
- Smaller coil design status update (Aso)
Site work plan for the next week
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
Travel Plans
- Travel (Week of 1/30):
- Takahashi: 30-2/3
- Shoda: 31-2/3
- Mark: 30-2/3
- Fabian:
- Okutomi: 30-2/3
- Fujii:
- Ishizaki: 30-2/3
- Hirata:
- Sato: 30-2/3
- Enzo: 30-2/3
- Hashimoto (Hosei Univ.):
- Someya (Hosei Univ.):
- Ohishi:
- Travel (Week of 2/6):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Enzo:
- Hashimoto (Hosei Univ.):
- Someya (Hosei Univ.):
- Ohishi:
Next meeting
On 2017/2/3(Fri) VIS F2F: Feb. 17th