Differences between revisions 7 and 8
Revision 7 as of 2017-01-27 11:33:40
Size: 2372
Comment:
Revision 8 as of 2017-01-27 13:28:29
Size: 3063
Editor: AyakaShoda
Comment:
Deletions are marked like this. Additions are marked like this.
Line 24: Line 24:
 * Put a report here  * '''Hanging Report''': TF measured, BF has been set.
  * EQ stop parts below the BF were assembled.
  * We measured TFs of RM using PSs. (Their alignment was not so easy.)
  * BF was placed on the EQ stop. (Traverser was moved out of the clean room for accesibility.)
  * BF and IM was connected. Not hanged yet.
  * BFRM parts were delivered.
Line 26: Line 31:
 * '''Next week task''': Hang IRM
  * Hang IM and adjust the weight.
  * Hang IRM and balance IM.
  * IRM and set OSEMs.

 * A mirror box was sent to a company for modification
 * Flag bases were sent to a company for modification
 * Winch were sent to Mitaka for inspection

 * '''To do'''
  * Establish disassemble procedure
  * Buy the new tools

Agenda/Minutes of the VIS Meeting on 2017/1/27

2017/1/27 13:30 -

Participants:

Progress report

Schedule Chart : (PDF,MPP)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • EYV chamber: Top chamber was connected again.
  • Pre-isolator: The pre-isolators for SR were packed and moved out of the large clean room on 23rd.
  • BF damper: Checked delivered parts on 24th.
  • Maraging wire: The wires are delivered on 31st. They are sent to the thermal proccess on 1st February.
    • The 3.3m wire can be treated at Himeji facility of Kinzoku-giken.
  • Preparation of installation: The floor of clean booth was covered by stainless steel sheet. The foot holds were assembled.
    • Other large tools (rack, wagon, desk, so on) also were installed into the clean booth.

Type B (Mark)

  • Put a report here

Type-Bp (Shoda)

  • Hanging Report: TF measured, BF has been set.

    • EQ stop parts below the BF were assembled.
    • We measured TFs of RM using PSs. (Their alignment was not so easy.)
    • BF was placed on the EQ stop. (Traverser was moved out of the clean room for accesibility.)
    • BF and IM was connected. Not hanged yet.
    • BFRM parts were delivered.
  • Next week task: Hang IRM

    • Hang IM and adjust the weight.
    • Hang IRM and balance IM.
    • IRM and set OSEMs.
  • A mirror box was sent to a company for modification
  • Flag bases were sent to a company for modification
  • Winch were sent to Mitaka for inspection
  • To do

    • Establish disassemble procedure
    • Buy the new tools

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • WDS PCB Design Document.Main rack( Main board + peripheral board )design.

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

  • Smaller coil design status update (Aso)

Site work plan for the next week

  • Mon:
  • Tue:
  • Wed:
  • Thu:
  • Fri:

Travel Plans

  • Travel (Week of 1/30):
    • Takahashi: 30-2/3
    • Shoda: 31-2/3
    • Mark: 30-2/3
    • Fabian:
    • Okutomi: 30-2/3
    • Fujii:
    • Ishizaki: 30-2/3
    • Hirata:
    • Sato: 30-2/3
    • Enzo: 30-2/3
    • Hashimoto (Hosei Univ.):
    • Someya (Hosei Univ.):
    • Ohishi:
  • Travel (Week of 2/6):
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Hashimoto (Hosei Univ.):
    • Someya (Hosei Univ.):
    • Ohishi:

Next meeting

On 2017/2/3(Fri) VIS F2F: Feb. 17th