Size: 1683
Comment:
|
Size: 5723
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
Participants: | Participants: Mark, Shoda, Ishizaki, Sato, Okutomi, Aso, Takahashi, Ohishi, Hirata, Fabian, Enzo, Fujii, Tanaka |
Line 7: | Line 8: |
Schedule Chart : ([[https://www.dropbox.com/s/rlnmlt3uipcsai8/VIS%20Overall%20Schedule-20170121.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/rlnmlt3uipcsai8/VIS%20Overall%20Schedule-20170121.pdf?dl=0|MPP]]) | Schedule Chart : ([[https://www.dropbox.com/s/3xa42dccpteurm0/VIS%20Overall%20Schedule-20170209.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/sw2y0d9v65u4o4z/VIS%20Overall%20Schedule-20170209.mpp?dl=0|MPP]]) * Type-A: Mostly on schedule * Type-B: 1 week delay * Type-Bp: On schedule now, but expect to have one week delay in the next week. |
Line 11: | Line 16: |
* [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]] * Installation in Y-end * 7(Tue): Assembled the dummy payload and the EQ stop for it. Pre-assembled BF damper. Assembled the EQ stop for BF. * 8(Wed): Assembled the BF. Measured the weight of BF (105.7kg). * 9(Thu): Installed the dummy payload and the BF with athe EQ stop into the top chamber. * Maraging wire: The wires after aging were delivered on 7th. The 3.3m wire will be treated at Himeji facility of Kinzoku-giken. |
|
Line 12: | Line 23: |
* Install the protection net ring. * Tune the weight of dummy payload. * Assemble the BF damper with the support ring. * Lift down the dummy payload. * Set the EQ stop for F3. |
|
Line 15: | Line 31: |
* Hirata-san: * Did drawings of SR damper. * Mark, Fabian, Enzo and Hirata-san (at Kamioka): * Took the end plate off the IM to get access to the pitch/roll picos. * Found the pitch pico was unreliable and replaced it. * Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer. * Reassembled and rebalanced the IM. * Reassembled and adjusted the IRM. * Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF. * Adjusted IM OSEMs to half-way. * Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san). * Installed an improved LVDT cable made by Hirata-san. * Made and hung posters for the Elites meeting visitors.==== Plan for coming weeks ==== |
|
Line 16: | Line 45: |
* Enzo to stay in Mitaka and concentrate on getting drivers' license * Mark and Fabian to come to Kamioka and finish adjusting OSEMs and take TFs. * Assorted procedure writing and design tasks (SR frame etc) ==== Discussion ==== * Omit detailed TF measurements to expedite the work |
|
Line 19: | Line 54: |
* Main suspension * Active damping for IM are implemented. * BF FR was tested with the new driver chassis. * BF GAS LVDT was calibrated by inserting 1 mm sims. * New BF LVDTs are assembled. * BF cap, BFRM, and the EQ stop parts bewlo the SF are assembled. The BFRM is now sitting on the spacer attached on the BF. * Note: the company delivered other coated screws for the screws which we assigned as SDC with a vent hole. Be careful. * Optical bench suspension * Optical bench installation jigs, wire adapters for the optical bench, and optical bench suspension rods are assembled. * The OB installation jigs was tested a little. * Others * The temporally clean booth was cleaned and the floor sheet will be changed. * The EQ stop bars below the IM did not seem to be dirty now. -> Only old aluminum parts should be re-made. * BFRM suspension rods are delivered -> 2nd assembly test at Mitaka? |
|
Line 20: | Line 74: |
* Optical bench suspension test. * Assemble magnets on the OB Damper * Suspend the OB damper, OB intermediate mass, and OB for the test. ==== Discussion ==== * The support jig for the optical bench installation * The structure seems OK for supporting the damper ring. Try carefully in the next week's test assembly. Ask Shindo-san to help the work. * For extra safety, improved support jig will be ordered to Mirapro (Shoda) * Oxidized(?) aluminum parts * Type-Bp team will inspect the stored ones to see if we need to re-make them or not. * |
|
Line 23: | Line 88: |
Looking for jig parts http://klog.icrr.u-tokyo.ac.jp/osl/?r=2439 | |
Line 33: | Line 99: |
* Type-A: * Type-B: * Type-Bp: |
* Type-A: Crane works. Be careful not to drop things. * Type-B: no dangerous work foreseen * Type-Bp: Optical bench installation work needs to be done carefully. |
Line 38: | Line 104: |
* Disassembly procedure proposal (Shoda) [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=6132|document]] * It is better to avoid the flipping of the RM+TM. * A better procedure was found during the discussion at the meeting. * Hirata-san will design necessary jigs for this procedure in the next week. |
|
Line 39: | Line 109: |
== Site work plan for the next week == * Mon: Type-A, B, Bp * Tue: Type-A, B, Bp * Wed: Type-A, B, Bp * Thu: Type-A, B, Bp * Fri: Type-A, B, Bp |
|
Line 56: | Line 119: |
* Ishizaki: 13-16 | * Ishizaki: |
Line 65: | Line 128: |
* Travel (Week of 2/13): * Takahashi: * Shoda: * Mark: * Fabian: * Okutomi: |
* Travel (Week of 2/20): * Takahashi: 20- 24 * Shoda: 21 - 24 * Mark: 20 - 24 * Fabian: 20 - 24 * Okutomi: 20 - 22 |
Line 72: | Line 135: |
* Ishizaki: * Hirata: * Sato: * Enzo: * Hashimoto (Hosei Univ.): * Someya (Hosei Univ.): |
* Ishizaki: 20 - 24 * Hirata: 20 - 24 * Sato: 20 - 24 * Enzo: 20 - 24 * Hashimoto (Hosei Univ.): 20 - 24 |
Agenda/Minutes of the VIS Meeting on 2017/2/10
2017/2/10 13:30 -
Participants: Mark, Shoda, Ishizaki, Sato, Okutomi, Aso, Takahashi, Ohishi, Hirata, Fabian, Enzo, Fujii, Tanaka
Progress report
- Type-A: Mostly on schedule
- Type-B: 1 week delay
- Type-Bp: On schedule now, but expect to have one week delay in the next week.
Type-A (Takahashi)
Past week report
- Installation in Y-end
- 7(Tue): Assembled the dummy payload and the EQ stop for it. Pre-assembled BF damper. Assembled the EQ stop for BF.
- 8(Wed): Assembled the BF. Measured the weight of BF (105.7kg).
- 9(Thu): Installed the dummy payload and the BF with athe EQ stop into the top chamber.
- Maraging wire: The wires after aging were delivered on 7th. The 3.3m wire will be treated at Himeji facility of Kinzoku-giken.
Plan for coming weeks
- Install the protection net ring.
- Tune the weight of dummy payload.
- Assemble the BF damper with the support ring.
- Lift down the dummy payload.
- Set the EQ stop for F3.
Type B (Mark)
Past week report
- Hirata-san:
- Did drawings of SR damper.
- Mark, Fabian, Enzo and Hirata-san (at Kamioka):
- Took the end plate off the IM to get access to the pitch/roll picos.
- Found the pitch pico was unreliable and replaced it.
- Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer.
- Reassembled and rebalanced the IM.
- Reassembled and adjusted the IRM.
- Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF.
- Adjusted IM OSEMs to half-way.
- Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san).
- Installed an improved LVDT cable made by Hirata-san.
- Made and hung posters for the Elites meeting visitors.==== Plan for coming weeks ====
Plan for coming weeks
- Enzo to stay in Mitaka and concentrate on getting drivers' license
- Mark and Fabian to come to Kamioka and finish adjusting OSEMs and take TFs.
- Assorted procedure writing and design tasks (SR frame etc)
Discussion
- Omit detailed TF measurements to expedite the work
Type-Bp (Shoda)
Past week report
- Main suspension
- Active damping for IM are implemented.
- BF FR was tested with the new driver chassis.
- BF GAS LVDT was calibrated by inserting 1 mm sims.
- New BF LVDTs are assembled.
- BF cap, BFRM, and the EQ stop parts bewlo the SF are assembled.
- The BFRM is now sitting on the spacer attached on the BF.
- Note: the company delivered other coated screws for the screws which we assigned as SDC with a vent hole. Be careful.
- Optical bench suspension
- Optical bench installation jigs, wire adapters for the optical bench, and optical bench suspension rods are assembled.
- The OB installation jigs was tested a little.
- Others
- The temporally clean booth was cleaned and the floor sheet will be changed.
The EQ stop bars below the IM did not seem to be dirty now. -> Only old aluminum parts should be re-made.
BFRM suspension rods are delivered -> 2nd assembly test at Mitaka?
Plan for coming weeks
- Optical bench suspension test.
- Assemble magnets on the OB Damper
- Suspend the OB damper, OB intermediate mass, and OB for the test.
Discussion
- The support jig for the optical bench installation
- The structure seems OK for supporting the damper ring. Try carefully in the next week's test assembly. Ask Shindo-san to help the work.
- For extra safety, improved support jig will be ordered to Mirapro (Shoda)
- Oxidized(?) aluminum parts
- Type-Bp team will inspect the stored ones to see if we need to re-make them or not.
IMMT (Ohishi)
Past week report
Looking for jig parts http://klog.icrr.u-tokyo.ac.jp/osl/?r=2439
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Plan for coming weeks
Safety
- Incidents:
- Foreseen risks
- Type-A: Crane works. Be careful not to drop things.
- Type-B: no dangerous work foreseen
- Type-Bp: Optical bench installation work needs to be done carefully.
Discussion
Disassembly procedure proposal (Shoda) document
- It is better to avoid the flipping of the RM+TM.
- A better procedure was found during the discussion at the meeting.
- Hirata-san will design necessary jigs for this procedure in the next week.
Travel Plans
- Travel (Week of 2/13):
- Takahashi: 13-16
- Shoda: 13-16
- Mark: 13-16
- Fabian: 13-16
- Okutomi: 13-16
- Fujii:
- Ishizaki:
- Hirata:
- Sato: 13-16
- Enzo:
- Hashimoto (Hosei Univ.): 13-16
- Someya (Hosei Univ.): 13-16
- Ohishi:
- Travel (Week of 2/20):
- Takahashi: 20- 24
- Shoda: 21 - 24
- Mark: 20 - 24
- Fabian: 20 - 24
- Okutomi: 20 - 22
- Fujii:
- Ishizaki: 20 - 24
- Hirata: 20 - 24
- Sato: 20 - 24
- Enzo: 20 - 24
- Hashimoto (Hosei Univ.): 20 - 24
- Ohishi:
- Tanaka:
Next meeting
On 2017/2/17(Fri) in Mitaka
March VIS F2F: March 3