Agenda/Minutes of the VIS Meeting on 2017/6/2

2017/6/2 13:30 -

Participants:

Progress report

Schedule Chart : (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

Plan for coming weeks

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

  • PR3 chamber closed. PR3 (almost) completed!!
    • We finalized the cabling. Miyo-kun is still working on networking the motors, and BIO.
    • We closed the chamber.
    • We moved some parts, tools, a desk, a rack to PR2 clean booth.
  • Preparation for PR2 assembly is on going.
    • 2nd floor next to the assembly frame was closed.
    • Optical bench intermediate ring and damper ring are set inside the chamber.
  • PR2 flags are close to be detached hopefully.

Plan for coming weeks

  • Set assembly frame
  • Set the IM and the slider on the assembly frame
  • Prepare circuits for PR2/PRM
  • BF LVDT calibration

IMMT (Ohishi)

Past week report

  • Sent draft drawings to FCL.
  • Uploaded pastelist and drawings to KAGRA Dropbox

Plan for coming weeks

  • IMMT mirror removal from IMMT chamber(1/3):

Watchdog system (Tanaka)

Past week report

  • Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.

  • Examination of experimental preamplifier circuit(design)-->For measurement of background noise at KAGRA site.

Plan for coming weeks

  • Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.

  • Examination of experimental preamplifier circuit(design)-->Circuit fabrication.

Other site works

  • 6/5-6: Cross tube installation at IXYC (CRY)
  • 6/5-6: IYC view ports installation ? (AOS)
  • 6/6: EYA anchor hole drilling (CAL)

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

  • Preparation for the power outage on 6/19
    • Shut down all the electronics by 6/16
    • Close the chambers
    • Aso and Ohishi will take care of the works on 6/19
  • Budget for completing bKAGRA phase 3
    • Contingency budget to improve the VIS or fix problems: 50MJPY
    • Other suspensions (output steering mirror, OMC, etc)
  • Analog electronics (interface boards etc)

Travel Plans

  • Travel (Week of 6/5):
    • Takahashi: 6-9
    • Shoda: 6-9
    • Mark: 6-9
    • Fabian: 6-9
    • Okutomi: 6-9
    • Fujii:
    • Ishizaki: 6-9
    • Hirata: 6-9
    • Sato: 6-9
    • Enzo: 6-9
    • Ohishi:
    • Tanaka:
    • Akiyama(Hosei): 6-9
    • Hashimoto(Hosei): 5-9
  • Travel (Week of 6/12):
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Ohishi:
    • Tanaka:
    • Akimoto(Hosei):
    • Hashimoto(Hosei):

Next meeting

On 2017/6/9(Fri) Next F2F: 6/30(Fri) ?