2017/9/8 13:30 - 
2017/9/8 13:30 -
Line 13: Line 12:
 * Type-A:
 * Type-B: 
 * Type-Bp: 
 * Type-A: One week delay.
 * Type-B:
 * Type-Bp:
Line 19: Line 18:

[X-end]

4th(Mon)
  * Implemented the release sensors on the end plate for F1.
  * Put the F1 on the end plate.
  * Suspended the F2 and follows from the F1.
5th(Tue)
  * Calibrated the LVDT in F1.
  * Tuned the F1. The condition was changed by closing the cap. The lowest frequency was larger than 0.4Hz.
  * Assembled the twist pair flat cables.
  * Assembled the bridge frame.
6th(Wed)
  * Tuned the F1 changing the compression of blades.
7th(Thu)
  * Continued the F1 tuning. The lowest frequency was about 0.4 Hz.
  * Started the cabling between the F2 and the F1.
8th(Fri)
  * Continued the cabling.
Line 20: Line 39:
 * Lift down the F2 and F1 into the corrugate tube.
 * Adjust the load on BF from the cross tube.
 * Finish the installation of F1.
Line 24: Line 46:
Line 28: Line 49:
Line 32: Line 52:
Line 35: Line 54:
 *Creating the final version for mass production and running its operation test.-->Creating boards(WDS main board for Low power).

 *Waiting for concrete information on installation location.The type(High power,Low power)and number actually needed,and the peripheral equipment accompanying it.-->Waiting for information provision.
 
 *I held a meeting to make estimates with several vendors.-->Waiting for an estimate(Ongoing).
Line 36: Line 61:
 *Creating the final version for mass production and running its operation test.-->Implementation completion and operation test.

 *Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.
Line 38: Line 66:
Line 45: Line 72:
  * Type-A:    * Type-A:
Line 51: Line 78:
 * Coil driver circuit
  * [[attachment:LPwCoilDriver_V2sch+.pdf|Schematic]]
  * Watchdog
  * Output C
 * Parameter list for the sensitivity curve calculation
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0070/T1707038/006/kagra_sensitivity.pdf]]
 * Seismometers
  * [[attachment:comp.png]]
Line 71: Line 106:
  * Takahashi:
  * Okutomi:
  * Sato:
  * Ishizaki:
  * Mark: 
  * Fabian: 
  * Hirata: 
  * Enzo: 
  * Shoda: 
  * Ohishi: 
  * Takahashi: 19-22
  * Okutomi: 19-22
  * Sato: 19-22
  * Ishizaki: 19-21
  * Mark:
  * Fabian:
  * Hirata:
  * Enzo:
  * Shoda:
  * Ohishi:
Line 84: Line 119:
  * Kozu (ICRR): 
  * Arai (ICRR): 
  * Kozu (ICRR):
  * Arai (ICRR):
Line 88: Line 123:
On 2017/9/15(Fri)  On 2017/9/15(Fri)

Agenda/Minutes of the VIS Meeting on 2017/9/8

2017/9/8 13:30 -

Participants:

Progress report

Schedule Chart

Type-A & Bp : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A: One week delay.
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

[X-end]

4th(Mon)

  • Implemented the release sensors on the end plate for F1.
  • Put the F1 on the end plate.
  • Suspended the F2 and follows from the F1.

5th(Tue)

  • Calibrated the LVDT in F1.
  • Tuned the F1. The condition was changed by closing the cap. The lowest frequency was larger than 0.4Hz.
  • Assembled the twist pair flat cables.
  • Assembled the bridge frame.

6th(Wed)

  • Tuned the F1 changing the compression of blades.

7th(Thu)

  • Continued the F1 tuning. The lowest frequency was about 0.4 Hz.
  • Started the cabling between the F2 and the F1.

8th(Fri)

  • Continued the cabling.

Plan for coming weeks

  • Lift down the F2 and F1 into the corrugate tube.
  • Adjust the load on BF from the cross tube.
  • Finish the installation of F1.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

IMMT (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

  • Creating the final version for mass production and running its operation test.-->Creating boards(WDS main board for Low power).

  • Waiting for concrete information on installation location.The type(High power,Low power)and number actually needed,and the peripheral equipment accompanying it.-->Waiting for information provision.

  • I held a meeting to make estimates with several vendors.-->Waiting for an estimate(Ongoing).

Plan for coming weeks

  • Creating the final version for mass production and running its operation test.-->Implementation completion and operation test.

  • Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.

Other site works

  • End of Aug. to Nov.: Mozumi entrance will be closed

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Travel Plans

  • Travel (Week of 9/11):
    • Takahashi: 11-12 (13 JPS)
    • Okutomi: 11-15
    • Sato: 11-15
    • Ishizaki:
    • Mark: 11-15 (13)
    • Fabian: 14-15
    • Hirata: 11-15
    • Enzo: 11-15
    • Shoda: 11-15 (13)
    • Ohishi: 14-15
    • Fujii:
    • Tanaka:
    • Yoshioka (Toyama):
    • Kozu (ICRR): 11-15
    • Arai (ICRR): 11-15
  • Travel (Week of 9/18):
    • Takahashi: 19-22
    • Okutomi: 19-22
    • Sato: 19-22
    • Ishizaki: 19-21
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Yoshioka (Toyama):
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2017/9/15(Fri)