Agenda/Minutes of the VIS Meeting on 2017/9/8
2017/9/8 13:30 -
Participants:
Progress report
Schedule Chart
- Type-A: One week delay.
- Type-B:
- Type-Bp:
Type-A (Takahashi)
Past week report
[X-end]
4th(Mon)
- Implemented the release sensors on the end plate for F1.
- Put the F1 on the end plate.
- Suspended the F2 and follows from the F1.
5th(Tue)
- Calibrated the LVDT in F1.
- Tuned the F1. The condition was changed by closing the cap. The lowest frequency was larger than 0.4Hz.
- Assembled the twist pair flat cables.
- Assembled the bridge frame.
6th(Wed)
- Tuned the F1 changing the compression of blades.
7th(Thu)
- Continued the F1 tuning. The lowest frequency was about 0.4 Hz.
- Started the cabling between the F2 and the F1.
8th(Fri)
- Continued the cabling.
Plan for coming weeks
- Lift down the F2 and F1 into the corrugate tube.
- Adjust the load on BF from the cross tube.
- Finish the installation of F1.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
IMMT (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Creating the final version for mass production and running its operation test.-->Creating boards(WDS main board for Low power).
Waiting for concrete information on installation location.The type(High power,Low power)and number actually needed,and the peripheral equipment accompanying it.-->Waiting for information provision.
I held a meeting to make estimates with several vendors.-->Waiting for an estimate(Ongoing).
Plan for coming weeks
Creating the final version for mass production and running its operation test.-->Implementation completion and operation test.
Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.
Other site works
- End of Aug. to Nov.: Mozumi entrance will be closed
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
- Sub-chiefs
- Coil driver circuit
- Watchdog
- Output C
- Parameter list for the sensitivity curve calculation
- Seismometers
Travel Plans
- Travel (Week of 9/11):
- Takahashi: 11-12 (13 JPS)
- Okutomi: 11-15
- Sato: 11-15
- Ishizaki:
- Mark: 11-15 (13)
- Fabian: 14-15
- Hirata: 11-15
- Enzo: 11-15
- Shoda: 11-15 (13)
- Ohishi: 14-15
- Fujii:
- Tanaka:
- Yoshioka (Toyama):
- Kozu (ICRR): 11-15
- Arai (ICRR): 11-15
- Travel (Week of 9/18):
- Takahashi: 19-22
- Okutomi: 19-22
- Sato: 19-22
- Ishizaki: 19-21
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Yoshioka (Toyama):
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2017/9/15(Fri)