KAGRA/Subgroups/VIS/VISMinutes20170915について、ここに記述してください。 | = Agenda/Minutes of the VIS Meeting on 2017/9/15 = 2017/9/15 13:30 - Participants: == Progress report == === Schedule Chart === Type-A & Bp : ([[https://www.dropbox.com/s/k1dhwpiqwg4fgyz/VIS%20Overall%20Schedule-20170906.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/8mob3ezt9dnln0p/VIS%20Overall%20Schedule-20170906.mpp?dl=0|MPP]]) Type-B: ([[https://www.dropbox.com/s/u6gl1ld8n3b70hu/BS%20Install%202017-07-28%20export.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/s2p3dq8c5oyt3s6/BS%20Install%202017-07-28%20export.mpp?dl=0|MPP]]) * Type-A: * Type-B: * Type-Bp: === Type-A (Takahashi) === ==== Past week report ==== ==== Plan for coming weeks ==== === Type B (Mark) === ==== Past week report ==== ==== Plan for coming weeks ==== === Type-Bp (Shoda) === ==== Past week report ==== ==== Plan for coming weeks ==== === OMMT & OSTM (Ohishi) === ==== Past week report ==== ==== Plan for coming weeks ==== === Watchdog system (Tanaka) === ==== Past week report ==== ==== Plan for coming weeks ==== === Other site works === * End of Aug. to Nov.: Mozumi entrance will be closed === Safety === * Incidents: * Foreseen risks * Type-A: * Type-B: * Type-Bp: == Discussion == == Travel Plans == * Travel (Week of 9/18): * Takahashi: 19-22 * Okutomi: 19-22 * Sato: 19-22 * Ishizaki: 19-21 * Mark: 19-22 * Fabian: 19-22 * Hirata: 19-22 * Enzo: 19-22 * Shoda: 19-22 * Ohishi: * Fujii: * Tanaka: * Yoshioka (Toyama): 18,21 * Kozu (ICRR): 19-22 * Arai (ICRR): * Travel (Week of 9/25): * Takahashi: * Okutomi: * Sato: * Ishizaki: * Mark: * Fabian: * Hirata: * Enzo: * Shoda: * Ohishi: * Fujii: * Tanaka: * Yoshioka (Toyama): * Kozu (ICRR): * Arai (ICRR): == Next meeting == On 2017/9/22(Fri) |
Agenda/Minutes of the VIS Meeting on 2017/9/15
2017/9/15 13:30 -
Participants:
Progress report
Schedule Chart
- Type-A:
- Type-B:
- Type-Bp:
Type-A (Takahashi)
Past week report
Plan for coming weeks
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Plan for coming weeks
Other site works
- End of Aug. to Nov.: Mozumi entrance will be closed
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
Travel Plans
* Travel (Week of 9/18):
- Takahashi: 19-22
- Okutomi: 19-22
- Sato: 19-22
- Ishizaki: 19-21
- Mark: 19-22
- Fabian: 19-22
- Hirata: 19-22
- Enzo: 19-22
- Shoda: 19-22
- Ohishi:
- Fujii:
- Tanaka:
- Yoshioka (Toyama): 18,21
- Kozu (ICRR): 19-22
- Arai (ICRR):
- Travel (Week of 9/25):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Yoshioka (Toyama):
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2017/9/22(Fri)