Line 6: Line 6:

----
Line 27: Line 29:
 * PRM installed
  * The suspension was installed.
  * But we found that the tank cannot be placed at the +y side of the PRM, since the space inside the clean booth was so tight. The tank was moved to the -y side using the fork lift and crane thanks to Kimura-san, Sawada-san, and Endo-san.
  * Cabling was almost done, but not yet checked.
  * Pylons for oplevs are installed. But no view port, nor oplev setup.
Line 28: Line 36:
 * No site work in the week of Sep. 25th
 * In the week of Nov. 2nd:
  * Cabling check
  * Remove all the FC for the interferometer alignment, which will start from Nov. 10th.
  * Oplev setup, including viewport.
  * Suspension release and status check.

  * PR2 BF GAS status check. Turning on PR2 damping.
Line 35: Line 52:

*Waiting for concrete information on installation location.The type(High power,Low power)and number actually needed,and the peripheral equipment accompanying it.-->Waiting for information provision.

*I held a meeting to make estimates with several vendors.-->Price negotiation failed.Because the assumed price is too low(The estimate of the manufacturing cost of the chassis was higher than expected).
  (Current assumed price about 900,000 yen -->Vendor's quotation price about 2,000,000 yen)

*Creating the final version for mass production and running its operation test.-->Implementation is complete and completion of the initial operation test.
Line 36: Line 61:

*Execution of the final version operation test for mass production ->Start of detailed exam.

*Creation of extended I/O PCB plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing(Start of mechanical design).

----
Line 39: Line 70:
 * Regular inspection of the forklift: Sept. 26 (Tue) 11:30~12:30
Line 50: Line 82:
----
Line 53: Line 86:
----
==== Oct. - Nov. 2017 ====
'''Type-A'''
Line 54: Line 90:
 * Task list
  * In-vac test (EX)
  * Swap cables (EX)
  * Transpotation of IPs and SFs (ITM)
  * Assembly of BF (ITM)
  * Check ACCs (ITM)
  * Lift up items (ITM)
  * Site preparation (ITM)

 * Man power
  * Takahashi
  * Okutomi
  * Sato
  * Ishizaki


'''Type-B'''

 * Task list
  * Order necessary items for SR including payloads
  * Make an inventory of SR parts
  * Assembly of SR IMs
  * Assembly of SRM PI
  * ??

 * Man power
  * Mark
  * Fabian
  * Hirata
  * Enzo
  * Kozu

'''Type-Bp'''

 * Task list
  * Tuning
  * Mirror position measurements

 * Man power
  * Shoda
  * Arai

----
==== Dec. 2017 - Mar. 2018 ====

'''Type-A'''

 * Man power
  * Takahashi
  * Sato
  * Ishizaki
  * Fujii (?)
  * Arai (?)
  * (Okutomi)

'''Type-B'''

 * Man power
  * Mark
  * Fabian
  * Hirata
  * Enzo
  * Kozu
  * Shoda (?)

----

Agenda/Minutes of the VIS Meeting on 2017/9/22

2017/9/22 13:30 -

Participants:


Progress report

Schedule Chart

Type-A & Bp : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

Plan for coming weeks

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

  • PRM installed
    • The suspension was installed.
    • But we found that the tank cannot be placed at the +y side of the PRM, since the space inside the clean booth was so tight. The tank was moved to the -y side using the fork lift and crane thanks to Kimura-san, Sawada-san, and Endo-san.
    • Cabling was almost done, but not yet checked.
    • Pylons for oplevs are installed. But no view port, nor oplev setup.

Plan for coming weeks

  • No site work in the week of Sep. 25th
  • In the week of Nov. 2nd:
    • Cabling check
    • Remove all the FC for the interferometer alignment, which will start from Nov. 10th.
    • Oplev setup, including viewport.
    • Suspension release and status check.
    • PR2 BF GAS status check. Turning on PR2 damping.

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

*Waiting for concrete information on installation location.The type(High power,Low power)and number actually needed,and the peripheral equipment accompanying it.-->Waiting for information provision.

*I held a meeting to make estimates with several vendors.-->Price negotiation failed.Because the assumed price is too low(The estimate of the manufacturing cost of the chassis was higher than expected).

  • (Current assumed price about 900,000 yen -->Vendor's quotation price about 2,000,000 yen)

*Creating the final version for mass production and running its operation test.-->Implementation is complete and completion of the initial operation test.

Plan for coming weeks

*Execution of the final version operation test for mass production ->Start of detailed exam.

*Creation of extended I/O PCB plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing(Start of mechanical design).


Other site works

  • Regular inspection of the forklift: Sept. 26 (Tue) 11:30~12:30
  • BS duct connection: Oct 2 - 6
  • End of Aug. to Nov.: Mozumi entrance will be closed

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:


Discussion

Plan for the coming months


Oct. - Nov. 2017

Type-A

  • Task list
    • In-vac test (EX)
    • Swap cables (EX)
    • Transpotation of IPs and SFs (ITM)
    • Assembly of BF (ITM)
    • Check ACCs (ITM)
    • Lift up items (ITM)
    • Site preparation (ITM)
  • Man power
    • Takahashi
    • Okutomi
    • Sato
    • Ishizaki

Type-B

  • Task list
    • Order necessary items for SR including payloads
    • Make an inventory of SR parts
    • Assembly of SR IMs
    • Assembly of SRM PI
    • ??
  • Man power
    • Mark
    • Fabian
    • Hirata
    • Enzo
    • Kozu

Type-Bp

  • Task list
    • Tuning
    • Mirror position measurements
  • Man power
    • Shoda
    • Arai


Dec. 2017 - Mar. 2018

Type-A

  • Man power
    • Takahashi
    • Sato
    • Ishizaki
    • Fujii (?)
    • Arai (?)
    • (Okutomi)

Type-B

  • Man power
    • Mark
    • Fabian
    • Hirata
    • Enzo
    • Kozu
    • Shoda (?)


Travel Plans

  • Travel (Week of 9/25):
    • Takahashi: 25-29
    • Okutomi: 25-29
    • Sato: 25-29
    • Ishizaki: 25-29
    • Mark: 25-29
    • Fabian: 25-29
    • Hirata: 25-29
    • Enzo: 25-26
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Yoshioka (Toyama): 26,27,29
    • Kozu (ICRR): ??
    • Arai (ICRR):
  • Travel (Week of 10/2):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2017/9/29(Fri)