Agenda/Minutes of the VIS Meeting on 2017/10/13

2017/10/13 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

Plan for coming weeks

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

Plan for coming weeks

Other site works

  • Fire drill: Nov. 9 (Thu) or Nov. 16 (Thu), 11AM - 12AM
  • End of Aug. to Nov.: Mozumi entrance will be closed

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Plan for the coming months

Travel Plans

  • Travel (Week of 10/16):
    • Takahashi: ??
    • Okutomi: 16 - 20
    • Sato: ??
    • Ishizaki: ??
    • Mark:
    • Fabian: 16 - 20
    • Hirata: 16- 20
    • Enzo: 16- 20
    • Shoda:
    • Ohishi:
    • Fujii: 16 - 20
    • Tanaka:
    • Kozu (ICRR): 16 - 20
    • Arai (ICRR): 16 - 20
  • Travel (Week of 10/23):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2017/10/20(Fri)

KAGRA/Subgroups/VIS/VISMinutes20171013 (last edited 2017-10-13 23:26:47 by YoichiAso)