[X-end]

10th(Tue)
  * Mounted the horizontal geophone pod.
  * Adjusted the weight on DP. The wire for DP was broken. It was replaced.
11th(Wed)
  * Tuned the BF.
  * Tuned the TF.
  * Adjusted the yaw rotation of BF.
12th(Thu)
  * Adjusted the LVDT position of TF and calibrated the LVDT again.
  * Released the IP and adjusted the tilt of IP using the jack through cone bellows.
  * Calibrated the LVDTs of IP.
  * Calibrated the ACCs.
13th(Fri)
  * Calibrated the ACCs.
  * Checked the motor sliders of IP.
Line 20: Line 39:
 * Tune the IP.
 * Set the BF damper.
 * Close the chamber.
Line 89: Line 111:

Agenda/Minutes of the VIS Meeting on 2017/10/13

2017/10/13 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

[X-end]

10th(Tue)

  • Mounted the horizontal geophone pod.
  • Adjusted the weight on DP. The wire for DP was broken. It was replaced.

11th(Wed)

  • Tuned the BF.
  • Tuned the TF.
  • Adjusted the yaw rotation of BF.

12th(Thu)

  • Adjusted the LVDT position of TF and calibrated the LVDT again.
  • Released the IP and adjusted the tilt of IP using the jack through cone bellows.
  • Calibrated the LVDTs of IP.
  • Calibrated the ACCs.

13th(Fri)

  • Calibrated the ACCs.
  • Checked the motor sliders of IP.

Plan for coming weeks

  • Tune the IP.
  • Set the BF damper.
  • Close the chamber.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

Plan for coming weeks

Other site works

  • Fire drill: Nov. 9 (Thu) or Nov. 16 (Thu), 11AM - 12AM
  • End of Aug. to Nov.: Mozumi entrance will be closed

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Plan for the coming months

Travel Plans

  • Travel (Week of 10/16):
    • Takahashi: ??
    • Okutomi: 16 - 20
    • Sato: ??
    • Ishizaki: ??
    • Mark:
    • Fabian: 16 - 20
    • Hirata: 16- 20
    • Enzo: 16- 20
    • Shoda:
    • Ohishi:
    • Fujii: 16 - 20
    • Tanaka:
    • Kozu (ICRR): 16 - 20
    • Arai (ICRR): 16 - 20
  • Travel (Week of 10/23):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2017/10/20(Fri)