Agenda/Minutes of the VIS Meeting on 2017/10/13
2017/10/13 13:30 -
Participants:
Progress report
Schedule Chart
- Type-A:
- Type-B:
- Type-Bp:
Type-A (Takahashi)
Past week report
[X-end]
10th(Tue)
- Mounted the horizontal geophone pod.
- Adjusted the weight on DP. The wire for DP was broken. It was replaced.
11th(Wed)
- Tuned the BF.
- Tuned the TF.
- Adjusted the yaw rotation of BF.
12th(Thu)
- Adjusted the LVDT position of TF and calibrated the LVDT again.
- Released the IP and adjusted the tilt of IP using the jack through cone bellows.
- Calibrated the LVDTs of IP.
- Calibrated the ACCs.
13th(Fri)
- Calibrated the ACCs.
- Checked the motor sliders of IP.
Plan for coming weeks
- Tune the IP.
- Set the BF damper.
- Close the chamber.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Plan for coming weeks
Other site works
- Fire drill: Nov. 9 (Thu) or Nov. 16 (Thu), 11AM - 12AM
- End of Aug. to Nov.: Mozumi entrance will be closed
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
Plan for the coming months
Travel Plans
- Travel (Week of 10/16):
- Takahashi: ??
- Okutomi: 16 - 20
- Sato: ??
- Ishizaki: ??
- Mark:
- Fabian: 16 - 20
- Hirata: 16- 20
- Enzo: 16- 20
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR): 16 - 20
- Arai (ICRR): 16 - 20
- Travel (Week of 10/23):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2017/10/20(Fri)