Differences between revisions 1 and 2
Revision 1 as of 2017-10-25 15:45:14
Size: 1514
Editor: YoichiAso
Comment:
Revision 2 as of 2017-10-27 10:24:21
Size: 2219
Comment:
Deletions are marked like this. Additions are marked like this.
Line 19: Line 19:

[X-end]
  * Recovered the black out.
  * Checked signals for the BF damper.
  * Set the remote operation of the stepping motors.
  * Closed the top chamber.
  * Closed the cross tube.
  * Set the remote monitor of the vacuum gauge.

[Mitaka]
  * Assembled the BFs. One BF was completed. The other was assembled by a half.
  * Checked the ACCs. Two of six units have a problem.
Line 20: Line 33:
  * Start evacuation in X-end.
  * Finish the assembly of BFs.
  * Service the ACCs.

[Plan in November]
  * 6-10 X-end: Disassembly of the EQ stop and the cabling.
  * 13-17 Transportation of the items from Akeno and Mitaka to the 2F in KAGRA.
  * 20-23 X-end: Reassembly of the EQ stop and the cabling.

Agenda/Minutes of the VIS Meeting on 2017/10/27

2017/10/27 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

[X-end]

  • Recovered the black out.
  • Checked signals for the BF damper.
  • Set the remote operation of the stepping motors.
  • Closed the top chamber.
  • Closed the cross tube.
  • Set the remote monitor of the vacuum gauge.

[Mitaka]

  • Assembled the BFs. One BF was completed. The other was assembled by a half.
  • Checked the ACCs. Two of six units have a problem.

Plan for coming weeks

  • Start evacuation in X-end.
  • Finish the assembly of BFs.
  • Service the ACCs.

[Plan in November]

  • 6-10 X-end: Disassembly of the EQ stop and the cabling.
  • 13-17 Transportation of the items from Akeno and Mitaka to the 2F in KAGRA.
  • 20-23 X-end: Reassembly of the EQ stop and the cabling.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

Plan for coming weeks

Other site works

  • Fire drill: Nov. 16 from 11AM - 12AM
  • Commissioning Workshop: Nov. 27 to Dec. 1st

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Plan for the coming months

Travel Plans

  • Travel (Week of 10/30):
    • Takahashi:
    • Okutomi: 10/30 - 11/3
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):
  • Travel (Week of 11/6):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2017/10/27(Fri)