[X-end] * Recovered the black out. * Checked signals for the BF damper. * Set the remote operation of the stepping motors. * Closed the top chamber. * Closed the cross tube. * Set the remote monitor of the vacuum gauge. [Mitaka] * Assembled the BFs. One BF was completed. The other was assembled by a half. * Checked the ACCs. Two of six units have a problem. |
|
Line 20: | Line 33: |
* Start evacuation in X-end. * Finish the assembly of BFs. * Service the ACCs. [Plan in November] * 11/6-10 X-end: Disassembly of the EQ stop and the cabling. * 11/13-17 Transportation of the items from Akeno and Mitaka to the 2F in KAGRA. * 11/20-12/1 X-end: Reassembly of the EQ stop and the cabling. |
|
Line 23: | Line 44: |
==== Plan for coming weeks ==== | At Kamioka (Mark, Fabian, Enzo, Hirata-san): * Hirata-san did an inventory of SR and other parts at Kamioka. * Mark and Enzo finalized the geometry matrices for the IP, entered them in MEDM and updated the safe.snap. * Mark, Enzo and Fabian worked with Izumi-san et al. to align the BS. We got the +Y beam fairly close to aligned (to the second gate valve, near IY). |
Line 25: | Line 49: |
==== Plan for week of 10/30 ==== Kamioka: Mark and Enzo * Continue alignment of BS. * Realign OL. * Work on servos. Mitaka: Fabian and Hirata-san * SR procurement. * New PI GAS FR design. * BS LBB ballast mass design. * SR cable lamp design. |
|
Line 27: | Line 63: |
* We had a big problem on k1pr0 after the blackout. * PR2 recovered smoothly. * Now PR3 is recovered after several problems. * TFs are checked. The suspension status looks good. * Problems to be solved: * large noise in PR2 OSEMs. * TF gain decrease by 30dB (Pr3 BF GAS) |
|
Line 35: | Line 80: |
*Creation of extended I/O PCB plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).--> *Wiring and Testing for EX I/O box(19 inch chassis) were completed. *Connection test with WDS and digital I/O card's emulation tool. *I held a meeting to make estimates with several vendors.--> *I got an estimate from the vendor(Denseisirius). *About 5.3 million yen. *Request for fabrication of JGW-D1605239(Binary IO Converter Chassis) for use with WDS(JGW-T1707285(docx)).-->Wait for results. |
|
Line 36: | Line 89: |
*Execution of the final version operation test for mass production ->Detailed exam(Ongoing). | |
Line 37: | Line 91: |
*I want to start ordering mass production version. *I'd like to conduct the final exam in KAGRA.-->On the experiment plan at the KAGRA site of the WDS system[[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0067/E1706737/001/Project%20WDS%20Experiment%20plan%20Drifts%20version%20170516.pdf|JGW-E1706737(PDF)]]. *Experiments in phase 2 and phase 3(However,only one 4ch WDS main box is to be tested). *The target is a Low power type. *My desired test period is from 7th Nov to 9th Nov(6th Nov is move date and 10th Nov is preparation day). |
Agenda/Minutes of the VIS Meeting on 2017/10/27
2017/10/27 13:30 -
Participants:
Progress report
Schedule Chart
- Type-A:
- Type-B:
- Type-Bp:
Type-A (Takahashi)
Past week report
[X-end]
- Recovered the black out.
- Checked signals for the BF damper.
- Set the remote operation of the stepping motors.
- Closed the top chamber.
- Closed the cross tube.
- Set the remote monitor of the vacuum gauge.
[Mitaka]
- Assembled the BFs. One BF was completed. The other was assembled by a half.
- Checked the ACCs. Two of six units have a problem.
Plan for coming weeks
- Start evacuation in X-end.
- Finish the assembly of BFs.
- Service the ACCs.
[Plan in November]
- 11/6-10 X-end: Disassembly of the EQ stop and the cabling.
- 11/13-17 Transportation of the items from Akeno and Mitaka to the 2F in KAGRA.
- 11/20-12/1 X-end: Reassembly of the EQ stop and the cabling.
Type B (Mark)
Past week report
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
- Hirata-san did an inventory of SR and other parts at Kamioka.
- Mark and Enzo finalized the geometry matrices for the IP, entered them in MEDM and updated the safe.snap.
- Mark, Enzo and Fabian worked with Izumi-san et al. to align the BS. We got the +Y beam fairly close to aligned (to the second gate valve, near IY).
Plan for week of 10/30
Kamioka: Mark and Enzo
- Continue alignment of BS.
- Realign OL.
- Work on servos.
Mitaka: Fabian and Hirata-san
- SR procurement.
- New PI GAS FR design.
- BS LBB ballast mass design.
- SR cable lamp design.
Type-Bp (Shoda)
Past week report
- We had a big problem on k1pr0 after the blackout.
- PR2 recovered smoothly.
- Now PR3 is recovered after several problems.
- TFs are checked. The suspension status looks good.
- Problems to be solved:
- large noise in PR2 OSEMs.
- TF gain decrease by 30dB (Pr3 BF GAS)
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Creation of extended I/O PCB plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->
- Wiring and Testing for EX I/O box(19 inch chassis) were completed.
- Connection test with WDS and digital I/O card's emulation tool.
I held a meeting to make estimates with several vendors.-->
- I got an estimate from the vendor(Denseisirius).
- About 5.3 million yen.
Request for fabrication of JGW-D1605239(Binary IO Converter Chassis) for use with WDS(JGW-T1707285(docx)).-->Wait for results.
Plan for coming weeks
Execution of the final version operation test for mass production ->Detailed exam(Ongoing).
- I want to start ordering mass production version.
I'd like to conduct the final exam in KAGRA.-->On the experiment plan at the KAGRA site of the WDS systemJGW-E1706737(PDF).
- Experiments in phase 2 and phase 3(However,only one 4ch WDS main box is to be tested).
- The target is a Low power type.
- My desired test period is from 7th Nov to 9th Nov(6th Nov is move date and 10th Nov is preparation day).
Other site works
- Fire drill: Nov. 16 from 11AM - 12AM
- Commissioning Workshop: Nov. 27 to Dec. 1st
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
Plan for the coming months
Travel Plans
- Travel (Week of 10/30):
- Takahashi:
- Okutomi: 10/30 - 11/3
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 11/6):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2017/10/27(Fri)