Line 3: Line 3:
2017/10/27 13:30 - 2017/10/27 13:30 - 15:00
Line 5: Line 5:
Participants: Participants: Okutomi, Ishizaki, Aso, Mark, Sato, Hirata, Simon, Enzo, Fabian, Ohishi, Shoda, Tanaka
Line 19: Line 20:

[X-end]
  * Recovered the black out.
  * Checked signals for the BF damper.
  * Set the remote operation of the stepping motors.
  * Closed the top chamber.
  * Closed the cross tube.
  * Set the remote monitor of the vacuum gauge.

[Mitaka]
  * Assembled the BFs. One BF was completed. The other was assembled by a half.
  * Checked the ACCs. Two of six units have a problem.
Line 20: Line 34:
  * Start evacuation in X-end.
  * Finish the assembly of BFs.
  * Service the ACCs.

[Plan in November]
  * 11/6-10 X-end: Disassembly of the EQ stop and the cabling.
  * 11/13-17 Transportation of the items from Akeno and Mitaka to the 2F in KAGRA.
  * 11/20-12/1 X-end: Reassembly of the EQ stop and the cabling.
Line 23: Line 45:
==== Plan for coming weeks ==== At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san did an inventory of SR and other parts at Kamioka.
 * Mark and Enzo finalized the geometry matrices for the IP, entered them in MEDM and updated the safe.snap.
 * Mark, Enzo and Fabian worked with Izumi-san et al. to align the BS. We got the +Y beam fairly close to aligned (to the second gate valve, near IY).
Line 25: Line 50:
==== Plan for week of 10/30 ====

Kamioka: Mark and Enzo
 * Continue alignment of BS.
 * Realign OL.
 * Work on servos.

Mitaka: Fabian and Hirata-san
 * SR procurement.
 * New PI GAS FR design.
 * BS LBB ballast mass design.
 * SR cable lamp design.
Line 27: Line 64:
 * We had a big problem on k1pr0 after the blackout.
 * PR2 recovered smoothly.
 * Now PR3 is recovered after several problems.
  * TFs are checked. The suspension status looks good.

 * Problems to be solved:
  * large noise in PR2 OSEMs.
  * TF gain decrease by 30dB (Pr3 BF GAS)
Line 35: Line 81:
  *Creation of extended I/O PCB plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->
     *Wiring and Testing for EX I/O box(19 inch chassis) were completed.
     *Connection test with WDS and digital I/O card's emulation tool.
  
  *I held a meeting to make estimates with several vendors.-->
     *I got an estimate from the vendor(Denseisirius).
     *About 5.3 million yen.
  *Request for fabrication of JGW-D1605239(Binary IO Converter Chassis) for use with WDS(JGW-T1707285(docx)).-->Wait for results.
Line 36: Line 90:
  *Execution of the final version operation test for mass production ->Detailed exam(Ongoing).
Line 37: Line 92:
  *I want to start ordering mass production version.
  
  *I'd like to conduct the final exam in KAGRA.-->On the experiment plan at the KAGRA site of the WDS system[[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0067/E1706737/001/Project%20WDS%20Experiment%20plan%20Drifts%20version%20170516.pdf|JGW-E1706737(PDF)]].
    *Experiments in phase 2 and phase 3(However,only one 4ch WDS main box is to be tested).
    *The target is a Low power type.
    *My desired test period is from 7th Nov to 9th Nov(6th Nov is move date and 10th Nov is preparation day).
  
Line 43: Line 105:
 * Incidents:  * Incidents: no
Line 46: Line 108:
  * Type-A:
  * Type-B:
  * Type-Bp:
  * Type-A: vacuum evacuation
  * Type-B: possible crane work
  * Type-Bp: no work
Line 51: Line 113:
 * Type-A accelerometers
  * We have only two spare accelerometers
  * These spare ones have different sensor heads. -> need to exchange the head when used.
  * We should consider restarting the collaboration with NIKHEF for the next generation of accelerometers.
Line 60: Line 126:
  * Mark:   * Mark: 10/30 - 11/2
Line 63: Line 129:
  * Enzo:   * Enzo: 10/30 - 11/2
Line 74: Line 140:
  * Okutomi:   * Okutomi: 6 - 10
Line 81: Line 147:
  * Shoda:   * Shoda: 6 - 10
Line 84: Line 150:
  * Tanaka:   * Tanaka: 6 - 10
Line 89: Line 155:
On 2017/10/27(Fri) On 2017/11/10(Fri)

Agenda/Minutes of the VIS Meeting on 2017/10/27

2017/10/27 13:30 - 15:00

Participants: Okutomi, Ishizaki, Aso, Mark, Sato, Hirata, Simon, Enzo, Fabian, Ohishi, Shoda, Tanaka

Progress report

Schedule Chart

Type-A : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

[X-end]

  • Recovered the black out.
  • Checked signals for the BF damper.
  • Set the remote operation of the stepping motors.
  • Closed the top chamber.
  • Closed the cross tube.
  • Set the remote monitor of the vacuum gauge.

[Mitaka]

  • Assembled the BFs. One BF was completed. The other was assembled by a half.
  • Checked the ACCs. Two of six units have a problem.

Plan for coming weeks

  • Start evacuation in X-end.
  • Finish the assembly of BFs.
  • Service the ACCs.

[Plan in November]

  • 11/6-10 X-end: Disassembly of the EQ stop and the cabling.
  • 11/13-17 Transportation of the items from Akeno and Mitaka to the 2F in KAGRA.
  • 11/20-12/1 X-end: Reassembly of the EQ stop and the cabling.

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Hirata-san):

  • Hirata-san did an inventory of SR and other parts at Kamioka.
  • Mark and Enzo finalized the geometry matrices for the IP, entered them in MEDM and updated the safe.snap.
  • Mark, Enzo and Fabian worked with Izumi-san et al. to align the BS. We got the +Y beam fairly close to aligned (to the second gate valve, near IY).

Plan for week of 10/30

Kamioka: Mark and Enzo

  • Continue alignment of BS.
  • Realign OL.
  • Work on servos.

Mitaka: Fabian and Hirata-san

  • SR procurement.
  • New PI GAS FR design.
  • BS LBB ballast mass design.
  • SR cable lamp design.

Type-Bp (Shoda)

Past week report

  • We had a big problem on k1pr0 after the blackout.
  • PR2 recovered smoothly.
  • Now PR3 is recovered after several problems.
    • TFs are checked. The suspension status looks good.
  • Problems to be solved:
    • large noise in PR2 OSEMs.
    • TF gain decrease by 30dB (Pr3 BF GAS)

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

  • Creation of extended I/O PCB plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->

    • Wiring and Testing for EX I/O box(19 inch chassis) were completed.
    • Connection test with WDS and digital I/O card's emulation tool.
  • I held a meeting to make estimates with several vendors.-->

    • I got an estimate from the vendor(Denseisirius).
    • About 5.3 million yen.
  • Request for fabrication of JGW-D1605239(Binary IO Converter Chassis) for use with WDS(JGW-T1707285(docx)).-->Wait for results.

Plan for coming weeks

  • Execution of the final version operation test for mass production ->Detailed exam(Ongoing).

  • I want to start ordering mass production version.
  • I'd like to conduct the final exam in KAGRA.-->On the experiment plan at the KAGRA site of the WDS systemJGW-E1706737(PDF).

    • Experiments in phase 2 and phase 3(However,only one 4ch WDS main box is to be tested).
    • The target is a Low power type.
    • My desired test period is from 7th Nov to 9th Nov(6th Nov is move date and 10th Nov is preparation day).

Other site works

  • Fire drill: Nov. 16 from 11AM - 12AM
  • Commissioning Workshop: Nov. 27 to Dec. 1st

Safety

  • Incidents: no
  • Foreseen risks
    • Type-A: vacuum evacuation
    • Type-B: possible crane work
    • Type-Bp: no work

Discussion

  • Type-A accelerometers
    • We have only two spare accelerometers
    • These spare ones have different sensor heads. -> need to exchange the head when used.

    • We should consider restarting the collaboration with NIKHEF for the next generation of accelerometers.

Plan for the coming months

Travel Plans

  • Travel (Week of 10/30):
    • Takahashi:
    • Okutomi: 10/30 - 11/3
    • Sato:
    • Ishizaki:
    • Mark: 10/30 - 11/2
    • Fabian:
    • Hirata:
    • Enzo: 10/30 - 11/2
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):
  • Travel (Week of 11/6):
    • Takahashi:
    • Okutomi: 6 - 10
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda: 6 - 10
    • Ohishi:
    • Fujii:
    • Tanaka: 6 - 10
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2017/11/10(Fri)