Differences between revisions 12 and 13
Revision 12 as of 2017-11-10 14:11:57
Size: 5370
Editor: MarkBarton
Comment:
Revision 13 as of 2017-11-10 15:02:10
Size: 5524
Editor: YoichiAso
Comment:
Deletions are marked like this. Additions are marked like this.
Line 141: Line 141:
  * Takahashi:
  * Okutomi:
  * Sato:
  * Ishizaki:
  * Mark:
  * Fabian:
  * Takahashi: 14-17
  * Okutomi: 13 - 17
  * Sato: 13 - 17
  * Ishizaki: 13 - 17
  * Mark: 13 - 17
  * Fabian: 13 - 17
Line 149: Line 149:
  * Shoda:   * Shoda: 13 - 17
Line 153: Line 153:
  * Kozu (ICRR):
  * Arai (ICRR):
  * Kozu (ICRR): 13,15,16 (Mitaka)
  * Arai (ICRR): 13 - 17
  * Iida (ICRR): 13,14
Line 158: Line 159:
  * Takahashi:
  * Okutomi:
  * Sato:
  * Ishizaki:
  * Takahashi: 22 - 24
  * Okutomi: 20 - 24
  * Sato: 20 - 24
  * Ishizaki: 20 - 24
Line 166: Line 167:
  * Shoda:   * Shoda: 20 - 22
Line 169: Line 170:
  * Tanaka:   * Tanaka: 20 - 22
Line 171: Line 172:
  * Arai (ICRR):   * Arai (ICRR): 20 - 24

Agenda/Minutes of the VIS Meeting on 2017/11/10

2017/11/10 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

[X-end]

  • Started evacuation on 1st.
  • Established remort control of the stepper motors.
  • Adjusted DC position of the IP.
  • Measured transfer functions.

[Mitaka]

  • Finished asembly of the BFs.
  • Assembled the FRs for SF.
  • Checked the ACCs and the drivers. They can work.

Plan for coming weeks

  • 11/13 Shipping in Akeno. Preparation for the center area.
  • 11/14 Delivery in Kamika. Transortation of the bridge frame.
  • 11/17 Lifting of the items by MESCO.
  • 11/15-17 Replacement of cables in X-end.

Type B (Mark)

Past two weeks report

Kamioka (Mark, Enzo, Kozu-kun):

  • Supported IA team.
  • Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
  • Re-zeroed OL after significant change of beam position during IA.
  • Re-laid-out OL to improve focus of lens to LEN QPD.
  • Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
  • Enzo worked on design of control loops using the OL.
  • Kozu-kun worked on diagonalizing the OL.

Mitaka (Fabian, Hirata-san):

  • Fabian did mechanical design:
    • F0 FR
    • Cable clamps for the SR IP base.
    • New SR recoil ballast masses.
    • LBB ballast.
    • Update of BS 3D CAD with the as-built ballast.
  • Hirata-san
    • made and updated inventory list for SR.
    • made order list and asked some quotes.
    • Ordered some parts.
    • Talked with mirapro about SRM optical bench.
    • Made some drawings for SR preparation.

Plan for week of 11/13

Enzo and Kozu-kun at Mitaka

  • Servos
  • Diagonalization of OL
  • TFs of BF
  • Documentation

Mark and Fabian at Kamioka.

  • Mark attends Initial Alignment Closeout Meeting at U Toyama.
  • Support BF characterization work.
  • Prepare for mirror gluing.
  • Prepare for IM assembly.

Hirata-san at Mitaka

  • SR procurement.
  • Get BS prism-gluing jigs reworked for use with PR/SR mirror box.

Type-Bp (Shoda)

Past week report

  • We found the mirror slips and the tilt changes when the large force was applied.
    • It was observed both in PR2 and PR3.
    • In PR2 case: the guardian script was not proper. Since the DC control in GAS filter was turned off first when we turned the control off, the oplev beam went off from the QPD with the Oplev control was on. Therefore, the large force was applied on the IM.
    • In PR3 case: the AC power supply for the IO chassis was plugged out accidentally.
    • The WD threshold on IM stage may be too large. (But it seems not for GAS filters.) -> Request some modification on the coil drivers to AEL?

    • Should we slightly change the way to hang the mirror for SRs? (like putting a little bit of glue at the bottom to stop slipping...)

Plan for coming weeks

  • Mirror position measurement
  • Adjust the height of the optical table
  • Close the PR2 and 3 tanks.

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

  • Check the existing parts and order missing parts of hanging jig.
  • Check the drawings of glueing jig.

Watchdog system (Tanaka)

Past week report

*I want to start ordering mass production version.-->Waiting.

*Execution of the final version operation test for mass production -->Completed(Clear all operation test).

*Experiments in phase 2 and phase 3(However,only one 4ch WDS main box is to be tested).-->Waiting(Changing travel schedule).

*Designing and manufacturing testing tools for mass production equipment.-->Completed.

Plan for coming weeks

*Star of order related works.

*Operation test of the testing tool for mass production equipment.

*Business trip plan.--> I stay at Toyama on the 19th.And experiment in Kamioka from 20th to 22nd.

Other site works

  • In the week of Nov. 13th: Fixing the water leaks around the BS area.
  • Fire drill: Nov. 16 from 11AM - 12AM
  • Commissioning Workshop: Nov. 27 to Dec. 1st

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Plan for the coming months

Travel Plans

  • Travel (Week of 11/13):
    • Takahashi: 14-17
    • Okutomi: 13 - 17
    • Sato: 13 - 17
    • Ishizaki: 13 - 17
    • Mark: 13 - 17
    • Fabian: 13 - 17
    • Hirata:
    • Enzo:
    • Shoda: 13 - 17
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR): 13,15,16 (Mitaka)
    • Arai (ICRR): 13 - 17
    • Iida (ICRR): 13,14
  • Travel (Week of 11/20):
    • Takahashi: 22 - 24
    • Okutomi: 20 - 24
    • Sato: 20 - 24
    • Ishizaki: 20 - 24
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda: 20 - 22
    • Ohishi:
    • Fujii:
    • Tanaka: 20 - 22
    • Kozu (ICRR):
    • Arai (ICRR): 20 - 24

Next meeting

On 2017/11/17(Fri)

KAGRA/Subgroups/VIS/VISMinutes20171110 (last edited 2017-11-10 15:35:02 by YoichiAso)