Line 19: Line 19:

[X-end]
  * Started the replacement of cables from 15th.
  * Dismounted the pre-isolator.
  * Removed the cables above the F1.
  * Removed some screws from the inside of F1.

[ITM]
  * The items from Akeno and Mitaka were delivered on 14th.
  * Transported the bridge frame from the X-end to the center area on 14th.
  * Lifting up the items to the 2nd floor by MESCO on 17th.
Line 20: Line 32:
  * X-end: Reassembly of the EQ stop and the cabling from 20th.
  * Y-end: Connection to the cryo-payload from 27th.
Line 27: Line 41:
 * Top rid of PR2 and PR3 vacuum tank were fixed
  * Note that the feedthrough flanges are not closed yet.
  * During the fixing, we accidentally moved the injection beam of the Oplev. Alignment was lost.
  * We need to re-align the main beam. So far, we are planning to do it in the week of the commissioning WS.
 * PR mirror position was measured by FARO.
  * The position of the mirror is off from the design by:
   * PR2: (-9.4, +0.5, -6.4)
   * PR3: (-3.5, -0.5, -4.9)
   * PRM: (+4.7, 4.6, -1.5) Note: PRM is fixed
     Note that these values are relative to the side flange of the vacuum tank at the HR side. x is the norm of the flange surface, and z is the norm of optical bench.
Line 28: Line 53:
 * Release PRM. Setup the oplev
 * WD test
Line 31: Line 58:
 * Checked and ordered missing parts of hanging jig.
 * Checked glueing jig parts.
Line 32: Line 61:

=== Watchdog system (Tanaka) ===
 * Order some glueing jig parts that have defect.
 * Revise Type-C assembly [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/IMC%20Suspension?action=AttachFile&do=view&target=sus2_02_v2.pdf|manual]].
Line 56: Line 85:
  * Takahashi:
  * Okutomi:
  * Sato:
  * Ishizaki:
  * Takahashi: 22 - 24
  * Okutomi: 20 - 24
  * Sato: 20 - 24
  * Ishizaki: 20 - 24
Line 64: Line 93:
  * Shoda:   * Shoda: 20 - 22
Line 67: Line 96:
  * Tanaka:   * Tanaka: 20 -22
Line 69: Line 98:
  * Arai (ICRR):   * Arai (ICRR): 20 - 24
Line 73: Line 102:
  * Takahashi:
  * Okutomi:
  * Sato:
  * Ishizaki:
  * Mark:
  * Fabian:
  * Hirata:
  * Enzo:
  * Shoda:
  * Takahashi: 27 - 12/1
  * Okutomi: 29 - 12/1
  * Sato: 27 - 12/1
  * Ishizaki: 27 - 12/1
  * Mark: 27 - 12/1
  * Fabian: 27 - 12/1
  * Hirata: 27 - 12/1
  * Enzo: 27 - 12/1
  * Shoda: 27 - 12/1
Line 85: Line 114:
  * Kozu (ICRR):
  * Arai (ICRR):
  * Kozu (ICRR): 27 - 12/1
  * Arai (ICRR): 27 - 12/1

Agenda/Minutes of the VIS Meeting on 2017/11/17

2017/11/17 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

[X-end]

  • Started the replacement of cables from 15th.
  • Dismounted the pre-isolator.
  • Removed the cables above the F1.
  • Removed some screws from the inside of F1.

[ITM]

  • The items from Akeno and Mitaka were delivered on 14th.
  • Transported the bridge frame from the X-end to the center area on 14th.
  • Lifting up the items to the 2nd floor by MESCO on 17th.

Plan for coming weeks

  • X-end: Reassembly of the EQ stop and the cabling from 20th.
  • Y-end: Connection to the cryo-payload from 27th.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

  • Top rid of PR2 and PR3 vacuum tank were fixed
    • Note that the feedthrough flanges are not closed yet.
    • During the fixing, we accidentally moved the injection beam of the Oplev. Alignment was lost.
    • We need to re-align the main beam. So far, we are planning to do it in the week of the commissioning WS.
  • PR mirror position was measured by FARO.
    • The position of the mirror is off from the design by:
      • PR2: (-9.4, +0.5, -6.4)
      • PR3: (-3.5, -0.5, -4.9)
      • PRM: (+4.7, 4.6, -1.5) Note: PRM is fixed
        • Note that these values are relative to the side flange of the vacuum tank at the HR side. x is the norm of the flange surface, and z is the norm of optical bench.

Plan for coming weeks

  • Release PRM. Setup the oplev
  • WD test

OMMT & OSTM (Ohishi)

Past week report

  • Checked and ordered missing parts of hanging jig.
  • Checked glueing jig parts.

Plan for coming weeks

  • Order some glueing jig parts that have defect.
  • Revise Type-C assembly manual.

Past week report

Plan for coming weeks

Other site works

  • Crane inspection: Nov. 22 11:30 - 12:30
  • Commissioning Workshop: Nov. 27 to Dec. 1st

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Plan for the coming months

Travel Plans

  • Travel (Week of 11/20):
    • Takahashi: 22 - 24
    • Okutomi: 20 - 24
    • Sato: 20 - 24
    • Ishizaki: 20 - 24
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda: 20 - 22
    • Ohishi:
    • Fujii:
    • Tanaka: 20 -22
    • Kozu (ICRR):
    • Arai (ICRR): 20 - 24
  • Travel (Week of 11/27):
    • Takahashi: 27 - 12/1
    • Okutomi: 29 - 12/1
    • Sato: 27 - 12/1
    • Ishizaki: 27 - 12/1
    • Mark: 27 - 12/1
    • Fabian: 27 - 12/1
    • Hirata: 27 - 12/1
    • Enzo: 27 - 12/1
    • Shoda: 27 - 12/1
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR): 27 - 12/1
    • Arai (ICRR): 27 - 12/1

Next meeting

On 2017/11/24(Fri)